FERC Accepts Alabama Power Jordan Dam Safety Plan and Schedule
Summary
FERC's Atlanta Regional Office issued a delegated order accepting Alabama Power Company's plan and schedule to update dam safety follow-up items identified during the 2026 Dam Safety Inspection for the Jordan Dam Project (P-618). The utility must now proceed with implementing the accepted safety measures according to the filed timeline.
What changed
FERC accepted Alabama Power Company's plan and schedule submitted on March 30, 2026, which addresses Item 1 follow-up items from the 2026 Dam Safety Inspection for the Jordan Dam Project under license P-618. The acceptance confirms the utility's proposed timeline and safety measures meet FERC requirements.
Alabama Power must now execute the accepted plan according to the filed schedule. Dam operators and licensees under FERC jurisdiction should ensure their safety inspection follow-up items are addressed promptly to maintain compliance with federal dam safety standards.
What to do next
- Implement the accepted dam safety plan per the filed schedule
- Update Item 1 follow-up items as required by the 2026 Dam Safety Inspection
Archived snapshot
Apr 8, 2026GovPing captured this document from the original source. If the source has since changed or been removed, this is the text as it existed at that time.
Document Info for Accession Number: 20260408-3003
Details Document: 04/08/2026
Filed: 04/08/2026
Posted: 04/08/2026 09:15:17 AM
First Received Date: 04/08/2026 07:19:59 AM
Security Level: Public
Official: Yes
E-filing: No
Non-decisional: No
Category: Issuance
Library: Hydro
Aperture: 0
File Type:
Description* :** Letter to Alabama Power Company accepting the 03/30/2026 plan and schedule to update Item 1 from the 2026 Dam Safety Inspection follow-up items for the Jordan Dam Project under P-618.
File List
| Docket | Sub-Docket | Type |
| --- | --- | --- |
| P-618 | 000 | On Document |
| Document Class | Document Type |
| --- | --- |
| Order/Opinion | Delegated Order |
| Correspondent | Last Name | First Name | MI | Role/Org |
| --- | --- | --- | --- | --- |
| RECIPIENT | Green | S | J | ALABAMA POWER COMPANY |
| AUTHOR | BROWN | W | J | ATLANTA REGIONAL OFFICE |
Related changes
Get daily alerts for FERC eLibrary: All Orders - ChangeBridge
Daily digest delivered to your inbox.
Free. Unsubscribe anytime.
Source
About this page
Every important government, regulator, and court update from around the world. One place. Real-time. Free. Our mission
Source document text, dates, docket IDs, and authority are extracted directly from FERC.
The plain-English summary, classification, and "what to do next" steps are AI-generated from the original text. Cite the source document, not the AI analysis.
Classification
Who this affects
Taxonomy
Browse Categories
Get alerts for this source
We'll email you when FERC eLibrary: All Orders - ChangeBridge publishes new changes.