Changeflow GovPing Government General Brookfield Dam Safety Surveillance Report Accep...
Routine Notice Added Final

Brookfield Dam Safety Surveillance Report Accepted by FERC

Favicon for changeflow.com FERC eLibrary: All Orders - ChangeBridge
Published April 7th, 2026
Detected April 7th, 2026
Email

Summary

FERC's New York Regional Office accepted Brookfield Renewable Power's 2025 Dam Safety Surveillance and Monitoring Report for the Glens Falls hydroelectric project (P-2385). The acceptance confirms the dam operator's compliance with FERC's dam safety reporting requirements. No new obligations or modifications to existing license conditions were imposed.

What changed

FERC issued a delegated order accepting Brookfield Renewable Power's 2025 Dam Safety Surveillance and Monitoring Report for the Glens Falls Project. The acceptance indicates that FERC found the report adequate and the project remains in compliance with dam safety requirements under the project license.

For Brookfield Renewable Power and other hydroelectric dam operators, this acceptance confirms their compliance posture with FERC's Dam Safety Division. Operators should maintain ongoing surveillance programs, retain all monitoring documentation, and ensure future periodic reports continue to meet FERC's dam safety program standards.

What to do next

  1. Continue dam safety surveillance and monitoring per FERC license requirements
  2. Retain documentation of dam safety monitoring activities
  3. Prepare for future periodic dam safety reporting obligations

Source document (simplified)

Document Info for Accession Number: 20260407-3028

Details Document: 04/07/2026
Filed: 04/07/2026
Posted: 04/07/2026 12:23:07 PM
First Received Date: 04/07/2026 12:12:57 PM
Security Level: Public
Official: Yes
E-filing: No
Non-decisional: No
Category: Issuance
Library: Hydro
Aperture: 0
File Type:
Description* :** Letter to Brookfield Renewable Power accepting the 2025 Dam Safety Surveillance and Monitoring Report filed by letter dated 03/31/2026, for the Glens Falls Project under P-2385.
File List

| Docket | Sub-Docket | Type |
| --- | --- | --- |
| P-2385 | 000 | On Document |

| Document Class | Document Type |
| --- | --- |
| Order/Opinion | Delegated Order |

| Correspondent | Last Name | First Name | MI | Role/Org |
| --- | --- | --- | --- | --- |
| RECIPIENT | PARKER | T | | BROOKFIELD RENEWABLE POWER |
| AUTHOR | SPAIN | J | | NEW YORK REGIONAL OFFICE |

Named provisions

Dam Safety Surveillance and Monitoring Report

Get daily alerts for FERC eLibrary: All Orders - ChangeBridge

Daily digest delivered to your inbox.

Free. Unsubscribe anytime.

Source

Analysis generated by AI. Source diff and links are from the original.

Classification

Agency
FERC
Published
April 7th, 2026
Instrument
Notice
Legal weight
Non-binding
Stage
Final
Change scope
Minor
Document ID
P-2385
Docket
P-2385

Who this affects

Applies to
Energy companies
Industry sector
2210 Electric Utilities
Activity scope
Hydroelectric generation Dam safety monitoring Infrastructure compliance
Geographic scope
United States US

Taxonomy

Primary area
Energy
Operational domain
Compliance
Topics
Environmental Protection Public Safety

Get alerts for this source

We'll email you when FERC eLibrary: All Orders - ChangeBridge publishes new changes.

Optional. Personalizes your daily digest.

Free. Unsubscribe anytime.