Letter to Brookfield accepting Ellsworth Development plan schedule P-2727
Summary
FERC's New York Regional Office issued a letter to Brookfield Renewable Power accepting the development plan and schedule submitted on January 16, 2026 for the Ellsworth Development under the Ellsworth-Graham Lake Hydroelectric Project P-2727. The acceptance allows the project to proceed according to the submitted schedule.
What changed
FERC's New York Regional Office issued a letter formally accepting the development plan and schedule submitted by Brookfield Renewable Power on January 16, 2026 for the Ellsworth Development component of the Ellsworth-Graham Lake Project (P-2727). The acceptance, issued by J. Spain on behalf of the New York Regional Office, is a routine administrative action confirming compliance with the commission's procedural requirements.
Affected parties developing hydroelectric projects under FERC jurisdiction should note this acceptance does not create new compliance obligations but rather confirms that the project may proceed according to the accepted schedule. No changes to existing regulatory requirements or reporting obligations are imposed by this action.
What to do next
- Monitor for updates
Archived snapshot
Apr 8, 2026GovPing captured this document from the original source. If the source has since changed or been removed, this is the text as it existed at that time.
Document Info for Accession Number: 20260407-3042
Details Document: 04/07/2026
Filed: 04/07/2026
Posted: 04/07/2026 12:47:06 PM
First Received Date: 04/07/2026 12:38:27 PM
Security Level: Public
Official: Yes
E-filing: No
Non-decisional: No
Category: Issuance
Library: Hydro
Aperture: 0
File Type:
Description* :** Letter to Brookfield Renewable Power accepting the 01/16/2026 plan and schedule for the Ellsworth Development under Ellsworth-Graham Lake Project P-2727.
File List
| Docket | Sub-Docket | Type |
| --- | --- | --- |
| P-2727 | 000 | On Document |
| Document Class | Document Type |
| --- | --- |
| Order/Opinion | Delegated Order |
| Correspondent | Last Name | First Name | MI | Role/Org |
| --- | --- | --- | --- | --- |
| AUTHOR | SPAIN | J | | NEW YORK REGIONAL OFFICE |
| RECIPIENT | Bernier | K | | BROOKFIELD RENEWABLE POWER |
Related changes
Get daily alerts for FERC eLibrary: All Orders - ChangeBridge
Daily digest delivered to your inbox.
Free. Unsubscribe anytime.
Source
About this page
Every important government, regulator, and court update from around the world. One place. Real-time. Free. Our mission
Source document text, dates, docket IDs, and authority are extracted directly from FERC.
The plain-English summary, classification, and "what to do next" steps are AI-generated from the original text. Cite the source document, not the AI analysis.
Classification
Who this affects
Taxonomy
Browse Categories
Get alerts for this source
We'll email you when FERC eLibrary: All Orders - ChangeBridge publishes new changes.