FERC Accepts PJM Generation Interconnection Agreement for Barrelhead Solar

Favicon for changeflow.com FERC eLibrary: All Orders
Published
Detected
Email

Summary

FERC issued a delegated order accepting PJM Interconnection's amended filing of a Generation Interconnection Agreement involving Barrelhead Solar, LLC and East Kentucky Power Cooperative, Inc. under Docket ER26-1337. The letter order approves the interconnection agreement for a solar generation facility connecting to PJM's transmission grid in the East Kentucky service territory.

What changed

FERC's Office of Energy Market Regulation issued a letter order accepting PJM Interconnection's amended Generation Interconnection Agreement filing under ER26-1337. The agreement covers interconnection of Barrelhead Solar, LLC's solar generation facility with East Kentucky Power Cooperative's transmission system.

Affected parties including solar developers, electric cooperatives, and regional transmission organizations should note this acceptance as establishing precedent for similar interconnection agreement filings in PJM's service territory. Energy companies pursuing generation interconnections should ensure compliance with FERC's interconnection queue requirements and PJM's filed service agreements.

What to do next

  1. Monitor interconnection agreement implementation timelines
  2. Ensure updated interconnection queue management compliance
  3. Review FERC requirements for future solar generation interconnections

Archived snapshot

Apr 9, 2026

GovPing captured this document from the original source. If the source has since changed or been removed, this is the text as it existed at that time.

Document Info for Accession Number: 20260409-3048

Details Document: 04/09/2026
Filed: 04/09/2026
Posted: 04/09/2026 12:15:08 PM
First Received Date: 04/09/2026 11:48:34 AM
Security Level: Public
Official: Yes
E-filing: No
Non-decisional: No
Category: Issuance
Library: Electric
Aperture: 0
File Type:
Description* :** Letter order accepting PJM Interconnection, L.L.C.'s 02/11/2026, as amended on 04/02/2026, filing of a Generation Interconnection Agreement with Barrelhead Solar, LLC and East Kentucky Power Cooperative, Inc. etc. under ER26-1337.
File List

| Docket | Sub-Docket | Type |
| --- | --- | --- |
| ER26-1337 | 001 | On Document |

| Document Class | Document Type |
| --- | --- |
| Order/Opinion | Delegated Order |

| Correspondent | Last Name | First Name | MI | Role/Org |
| --- | --- | --- | --- | --- |
| AUTHOR | Khammal | L | | OFFICE OF ENERGY MARKET REGULATION |
| RECIPIENT | * | * | | PJM INTERCONNECTION, L.L.C. |

Named provisions

Generation Interconnection Agreement

Get daily alerts for FERC eLibrary: All Orders

Daily digest delivered to your inbox.

Free. Unsubscribe anytime.

About this page

What is GovPing?

Every important government, regulator, and court update from around the world. One place. Real-time. Free. Our mission

What's from the agency?

Source document text, dates, docket IDs, and authority are extracted directly from FERC.

What's AI-generated?

The plain-English summary, classification, and "what to do next" steps are AI-generated from the original text. Cite the source document, not the AI analysis.

Last updated

Classification

Agency
FERC
Published
April 9th, 2026
Instrument
Rule
Legal weight
Binding
Stage
Final
Change scope
Minor
Document ID
ER26-1337
Docket
ER26-1337

Who this affects

Applies to
Energy companies Government agencies
Industry sector
2210 Electric Utilities
Activity scope
Power grid interconnection Renewable energy generation Transmission service
Geographic scope
United States US

Taxonomy

Primary area
Energy
Operational domain
Compliance
Topics
Banking Environmental Protection

Get alerts for this source

We'll email you when FERC eLibrary: All Orders publishes new changes.

Free. Unsubscribe anytime.

You're subscribed!