Changeflow GovPing Government General Delegated Order Accepting PJM Generation Interc...
Routine Rule Added Final

Delegated Order Accepting PJM Generation Interconnection Agreement with Pigeon Run Solar

Favicon for changeflow.com FERC eLibrary: All Orders
Published
Detected
Email

Summary

FERC issued a delegated order accepting PJM Interconnection, L.L.C.'s filing of a Generation Interconnection Agreement with Pigeon Run Solar, LLC under Docket ER26-1255. The order accepts the original February 4, 2026 filing as supplemented on February 24, 2026 and amended on April 3, 2026.

What changed

FERC's Office of Energy Market Regulation issued a delegated order accepting PJM Interconnection's Generation Interconnection Agreement filing with Pigeon Run Solar, LLC under ER26-1255. The acceptance covers the original filing dated February 4, 2026, as supplemented February 24, 2026, and amended April 3, 2026.

For Pigeon Run Solar, LLC, this acceptance enables progression of their solar generation project's interconnection with PJM's transmission grid. PJM Interconnection can proceed with implementation of the interconnection agreement. No significant compliance burden is imposed on other market participants as this is a routine interconnection agreement acceptance.

What to do next

  1. No immediate action required for affected parties

Archived snapshot

Apr 9, 2026

GovPing captured this document from the original source. If the source has since changed or been removed, this is the text as it existed at that time.

Document Info for Accession Number: 20260409-3042

Details Document: 04/09/2026
Filed: 04/09/2026
Posted: 04/09/2026 11:57:09 AM
First Received Date: 04/09/2026 11:28:13 AM
Security Level: Public
Official: Yes
E-filing: No
Non-decisional: No
Category: Issuance
Library: Electric
Aperture: 0
File Type:
Description* :** Letter order accepting PJM Interconnection, L.L.C.'s 02/04/2026, as supplemented on 02/24/2026, and as amended on 04/03/2026, filing of a Generation Interconnection Agreement with Pigeon Run Solar, LLC etc. under ER26-1255.
File List

Docket Sub-Docket Type
ER26-1255 001 On Document
Document Class Document Type
Order/Opinion Delegated Order
Correspondent Last Name First Name MI Role/Org
RECIPIENT * * PJM INTERCONNECTION, L.L.C.
AUTHOR Khammal L OFFICE OF ENERGY MARKET REGULATION

Get daily alerts for FERC eLibrary: All Orders

Daily digest delivered to your inbox.

Free. Unsubscribe anytime.

About this page

What is GovPing?

Every important government, regulator, and court update from around the world. One place. Real-time. Free. Our mission

What's from the agency?

Source document text, dates, docket IDs, and authority are extracted directly from FERC.

What's AI-generated?

The summary, classification, recommended actions, deadlines, and penalty information are AI-generated from the original text and may contain errors. Always verify against the source document.

Last updated

Classification

Agency
FERC
Published
April 9th, 2026
Instrument
Rule
Legal weight
Binding
Stage
Final
Change scope
Minor
Document ID
Docket No. ER26-1255-001
Docket
ER26-1255

Who this affects

Applies to
Energy companies Government agencies
Industry sector
2210 Electric Utilities
Activity scope
Power grid interconnection Renewable energy facility development
Geographic scope
United States US

Taxonomy

Primary area
Energy
Operational domain
Compliance
Topics
Environmental Protection

Get alerts for this source

We'll email you when FERC eLibrary: All Orders publishes new changes.

Free. Unsubscribe anytime.

You're subscribed!