Mammoth Pool Pre-Inspection Report Accepted by FERC

Favicon for changeflow.com FERC eLibrary: All Orders
Published
Detected
Email

Summary

FERC's San Francisco Regional Office accepted Southern California Edison Company's Pre-Inspection Preparation Report dated March 26, 2026, for the Mammoth Pool Development under Project P-2085. This acceptance letter is a routine administrative step in the hydroelectric project licensing process, confirming that the pre-inspection documentation meets FERC requirements. The project may now proceed to the inspection phase.

What changed

FERC issued a letter accepting the Pre-Inspection Preparation Report submitted by Southern California Edison Company for the Mammoth Pool Development (P-2085). The acceptance confirms the report's adequacy for proceeding to the next licensing phase.

For Southern California Edison and other hydroelectric project operators, this acceptance represents a routine milestone in the FERC licensing process. No immediate compliance obligations are created beyond continued adherence to existing license conditions for Project P-2085.

What to do next

  1. Monitor for inspection scheduling notifications from FERC
  2. Continue preparation activities for Mammoth Pool Development inspection

Archived snapshot

Apr 9, 2026

GovPing captured this document from the original source. If the source has since changed or been removed, this is the text as it existed at that time.

Document Info for Accession Number: 20260409-3075

Details Document: 04/09/2026
Filed: 04/09/2026
Posted: 04/09/2026 03:49:05 PM
First Received Date: 04/09/2026 03:36:45 PM
Security Level: Public
Official: Yes
E-filing: No
Non-decisional: No
Category: Issuance
Library: Hydro
Aperture: 0
File Type:
Description* :** Letter to Southern California Edison Company accepting the 03/26/2026 Pre-Inspection Preparation Report for the Mammoth Pool Development, part of the Mammoth Pool Project under P-2085.
File List

| Docket | Sub-Docket | Type |
| --- | --- | --- |
| P-2085 | 000 | On Document |

| Document Class | Document Type |
| --- | --- |
| FERC Correspondence With Applicant | Compliance Directives |
| Order/Opinion | Delegated Order |

| Correspondent | Last Name | First Name | MI | Role/Org |
| --- | --- | --- | --- | --- |
| RECIPIENT | Allen | W | P | SOUTHERN CALIFORNIA EDISON COMPANY |
| AUTHOR | BLACKETT | F | L | SAN FRANCISCO REGIONAL OFFICE |

Get daily alerts for FERC eLibrary: All Orders

Daily digest delivered to your inbox.

Free. Unsubscribe anytime.

About this page

What is GovPing?

Every important government, regulator, and court update from around the world. One place. Real-time. Free. Our mission

What's from the agency?

Source document text, dates, docket IDs, and authority are extracted directly from FERC.

What's AI-generated?

The plain-English summary, classification, and "what to do next" steps are AI-generated from the original text. Cite the source document, not the AI analysis.

Last updated

Classification

Agency
FERC
Published
April 9th, 2026
Instrument
Notice
Legal weight
Non-binding
Stage
Final
Change scope
Minor
Document ID
Accession No. 20260409-3075
Docket
P-2085

Who this affects

Applies to
Energy companies Government agencies Investors
Industry sector
2210 Electric Utilities
Activity scope
Hydroelectric project licensing Pre-inspection compliance Infrastructure approval
Geographic scope
United States US

Taxonomy

Primary area
Energy
Operational domain
Compliance
Topics
Environmental Protection Government Contracting

Get alerts for this source

We'll email you when FERC eLibrary: All Orders publishes new changes.

Optional. Personalizes your daily digest.

Free. Unsubscribe anytime.