Sediment characterization services for Willapa Bay environmental assessment
Summary
The U.S. Army Corps of Engineers Seattle District issued an updated solicitation for sediment characterization services in Willapa Bay, Washington. The contract opportunity (W912DW26QA035) is set aside for small businesses under NAICS 541620 (Environmental Consulting Services). Proposals are due April 6, 2026.
What changed
The U.S. Army Corps of Engineers Seattle District issued an updated solicitation (W912DW26QA035) for sediment characterization services in Willapa Bay, Washington. The updated notice includes revised Performance Work Statement (PWS) provisions, particularly CLIN 6 - EIM Data requirements, and a question-and-answer document from potential vendors. The contract supports USACE's authorized maintenance dredging activities at Tokeland Marina, Bay Center, and Nahcotta. The solicitation is a Total Small Business Set-Aside under NAICS 541620.
Environmental consulting firms and contractors interested in bidding should review the updated PWS document and Q&A attachments before submitting proposals. The deadline for offers is April 6, 2026 at 11:00 am PDT. The contract is a non-personnel services agreement where contractors will provide their own personnel, equipment, and materials to perform sediment characterization tasks.
What to do next
- Review the updated PWS with CLIN 6 - EIM Data changes before submitting a quote
- Download and review the Q&A document for clarifications on solicitation requirements
- Submit proposal by April 6, 2026 at 11:00 am PDT
Source document (simplified)
FY26 Willapa Sediment Characterization Service
Active Contract Opportunity Notice ID W912DW26QA035 Related Notice Department/Ind. Agency DEPT OF DEFENSE Sub-tier DEPT OF THE ARMY Major Command US ARMY CORPS OF ENGINEERS Sub Command ENGINEER DIVISION NORTHWESTERN Sub Command 2 ENDIST SEATTLE Office W071 ENDIST SEATTLE
Looking for contract opportunity help?
APEX Accelerators are an official government contracting resource for small businesses. Find your local APEX Accelerator for free government expertise related to contract opportunities.
APEX Accelerators are funded in part through a cooperative agreement with the Department of Defense.
The APEX Accelerators program was formerly known as the Procurement Technical Assistance Program (PTAP).
General Information View Changes
- Contract Opportunity Type: Solicitation (Updated)
- Updated Published Date: Mar 28, 2026 01:47 pm PDT
- Original Published Date: Mar 20, 2026 12:17 pm PDT
- Updated Date Offers Due: Apr 06, 2026 11:00 am PDT
- Original Date Offers Due: Apr 06, 2026 11:00 am PDT
- Inactive Policy: 15 days after date offers due
- Updated Inactive Date: Apr 21, 2026
- Original Inactive Date: Apr 21, 2026
- Initiative:
- None
Classification
- Original Set Aside: Total Small Business Set-Aside (FAR 19.5)
- Product Service Code: B510 - SPECIAL STUDIES/ANALYSIS- ENVIRONMENTAL ASSESSMENTS
- NAICS Code:
- 541620 - Environmental Consulting Services
- Place of Performance: South Bend, WA USA
Description View Changes
UPDATED INFORMATION PROVIDED. Please see updated PWS with changes outlined in 5.2.6 CLIN 6 - EIM Data. Additionally, there is a word document with questions and answers that were submitted by a potential vendor. Please see attached with updated information that may be beneficial in quote submission.
//// END OF UPDATE ////
PART 1 – GENERAL INFORMATION
This is a non-personnel services contract to provide technical services for a sediment characterization in Willapa Bay, Washington (Figure 1). The U.S. Army Corps of Engineers (USACE) will not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers will be accountable solely to the Contractor who, in turn, is responsible to the USACE.
1. DESCRIPTION OF SERVICES / INTRODUCTION
Provide all personnel, equipment, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform the tasks for a sediment characterization in Willapa Bay as defined in this Performance Work Statement (PWS) except as specified in Section 3 as USACE-furnished property and services. Perform to the standards in this contract.
- BACKGROUND
As authorized by Congress, the Seattle District, U.S. Army Corps of Engineers (USACE) is responsible for maintenance dredging of the Willapa Bay project components including the entrance channel at Tokeland Marina, the entrance channel and mooring basin access lane at Bay Center, and the entrance channel and mooring basin access lane at Nahcotta, in Pacific County, Washington.
USACE last dredged portions of the Willapa Bay navigation project in 2002. Since then, the Port of Willapa has used a small private cutterhead dredge to maintain portions of the project every two to six years. USACE has continued to evaluate the project, with sediment testing completed in 2007 at Tokeland, 2011 at Bay Center, 2014 at Tokeland, Bay Center, and Nahcotta, and 2020 at Tokeland, Bay Center, and Nahcotta. In the most recent characterization, all dredged material was found to be suitable for open-water disposal (DMMP 2021). Table 1 summarizes details regarding the dimensions of project features and estimated volume above authorized depth. The USACE is responsible for dredging portions of the authorized project as needed to maintain navigation.
3. Previous Sediment Characterizations
The navigation channel is ranked “low” by the Dredged Material Management Program (DMMP) agencies for concern for potential contamination. Descriptions of the historical characterization efforts follow.
- Tokeland
- 1991. A single composited dredged material management unit (DMMU) sample representing the marina (including marina area P1) was collected in 1991 and analyzed for DMMP chemicals of concern (COCs). Three COCs (4-methylphenol, phenol, and pyrene) had detected exceedances; non-detect exceedances occurred for an additional number of chemicals. Bioassay testing was conducted, and the DMMP agencies determined that the dredged material was suitable for unconfined open-water disposal (DMMP 1991).
- 1998. Twelve individual grab samples were collected in March 1998 and composited into three DMMUs to represent 76,000 cubic yards (CY) from the entrance channel, marina, and marina area P1. There were no COC detections or non-detect concentrations that exceeded the DMMP screening levels. All material was found suitable for open-water disposal (DMMP 1998a).
- 2006. A total of eleven grab samples were collected from the entrance channel, marina, and marina area P1 in August 2006; the grab samples were composited into three composites to represent the entrance channel, marina, and marina area P1. Based on the two previous sequential testing rounds conducted in 1991 and 1998, the marina and marina area P1 were re-ranked from moderate to low-moderate for testing purposes. No COCs were detected above the DMMP screening levels. Five non-detected chemicals (hexachlorobenzene, dimethylphenol, benzoic acid, N-nitrosodiphenylamine, and alpha-chlordane) had detection limits that exceeded DMMP screening levels in one or all three DMMUs; bioassay testing was thus required for all three DMMUs. The results from the bioassay testing indicated that all of the material was suitable for unconfined open-water disposal (DMMP 2007).
- 2014. Eight cores were collected from the entrance channel, marina, and marina area P1 in September 2014 and composited into four DMMUs (2 surface and 2 subsurface DMMUs). No COCs were detected above DMMP screening levels; three COCs (total chlordane, dieldrin, and heptachlor) were not detected with elevated reporting limits above their respective DMMP screening levels in all four DMMUs. All DMMUs samples were subsequently analyzed for the standard DMMP pesticide COCs using a high resolution method with lower reporting limits; using this method, all pesticides were non-detect with detection limits below the DMMP screening levels. Total dioxin Toxic Equivalencies (TEQs) were below the 15 pptr TEQ and 5 pptr 2,3,7,8-TCDD threshold concentrations for dispersive disposal in Willapa Bay. Total TEQs (U=1/2 reporting limit [RL]) ranged from 1.2 to 2.7 pptr. All material was found suitable for unconfined open-water disposal (DMMP 2015).
- 2020. Nine cores were collected in August 2020. Material from the cores were composited into three DMMUs to represent the entrance channel, marina, and marina area P1. All material was found suitable for unconfined open-water/flow-lane disposal (DMMP 2021).
- Bay Center
- 1998. Tier 1 no-test for 15,000 CY from Bay Center Entrance Channel, based on a 1993 grain size characterization that showed 99.7% sand from two samples (DMMP 1998b).
- 2001. Vibracore samples characterized 38,000 CY of proposed dredged material. Cores were composited into three DMMUs: two surface and one subsurface DMMUs. Analyses included all routine DMMP COCs (including tributyltin [TBT], but no dioxin) and included special analyses for pesticides carbaryl and glyphosate. All chemicals were either detected or not detected below DMMP screening levels (SLs), and TBT was quantitated at levels well below the screening limit in the porewater of the three DMMUs characterized. All sediments were found suitable for open-water disposal (DMMP 2001).
- 2011. Port of Willapa proposed 18,000 CY of dredging in shoals leading to the Bay Center Marina. Five individual grab samples were composited into one DMMU. Laboratory analysis was conducted for the standard DMMP COCs plus glyphosate and dioxins. There were no SL exceedances; dioxin TEQ (U=1/2 RL) was 1.36 pptr. All material was found suitable for open-water disposal (DMMP 2011).
- 2015. Eight cores were composited into two surface DMMUs. Porewater TBT was not detected at 0.005 mg/L. Diethyl phthalate initially exceeded the SL in DMMU 2, but further replicated extractions and reanalysis did not replicate this finding. Because diethyl phthalate is a common laboratory contaminant, the DMMP concluded that the original finding was anomalous. Dioxin TEQs (U=1/2 RL) were 1.33 and 0.62 pptr, well below the 15 pptr TEQ threshold for Willapa Bay. All material was found suitable for open-water disposal (DMMP 2015).
- 2020. To characterize approximately 72,000 CY, six cores were collected in the Inner Channel and composited into two DMMUs for laboratory analysis of the DMMP COC list. In the Palix River access lane, three grabs were composited for one DMMU analyzing total solids, total organic carbon, and grain size under the Tier 1 no-test exclusionary status. and all material was found suitable for open-water/flow-lane disposal (DMMP 2021).
- Nahcotta
- 2004. In September 2003, cores were collected from a total of 17 locations and composited into four composite DMMUs to represent 145,000 CY of proposed dredging. Only standard DMMP COCs were analyzed for, and there were no detected or undetected results above screening levels. All material was found suitable for unconfined open-water disposal (DMMP 2004).
- 2015. In September 2014, forty cores were collected and subsequently composited to represent eleven DMMUs, of which one was a subsurface DMMU. No COCs were detected above DMMP screening levels. Two COCs (total chlordane and heptachlor) were undetected with elevated reporting limits above their respective DMMP screening levels in two DMMUs. All DMMU samples were subsequently analyzed for the standard DMMP pesticide COCs using a high-resolution method with lower reporting limits; using this method, no pesticides were detected or not detected above the DMMP screening levels. TBT (porewater) was undetected at 0.005 mg/L. Total dioxin TEQs were below the 15 pptr TEQ and 5 pptr 2,3,7,8-TCDD threshold concentrations for dispersive disposal in Willapa Bay. Total TEQs (U=1/2 RL) ranged from 1.2 to 3.7 pptr. All material was found to be suitable for unconfined open-water disposal (DMMP 2015).
- 2020. Sixteen cores were collected in the entrance channel and boat basin to characterize three surface and two subsurface DMMUs. Sampling was conducted in August 2020. The standard DMMP COC list was analyzed and no COCs were detected above DMMP screening levels. All material was found suitable for open-water/flow-lane disposal (DMMP 2021)
OBJECTIVES
The objectives for this contract are as follows:to prepare a sampling and analysis plan (SAP) that shall be suitable for submission to the DMMP agencies for approval;
to sample and characterize the sediments in the proposed dredging area as described in the SAP; and
- to prepare a report to document characterization results that can then be used by DMMP to make a suitability determination. This PWS includes preparation of the SAP; sampling and testing of dredged material; data collection and analysis; and report preparation
- SCOPE Perform a sediment characterization in Willapa Bay. The services provided under this contract are detailed in Part 5 – Specific Tasks.
PLEASE SEE ATTACHED PWS, EVALUATION CRITERIA, & BID SCHEDULE for specific information and criteria for this acquisition.
Attachments/Links
Contact Information
Contracting Office Address
- KO CONTRACTING DIVISION 4735 EAST MARGINAL WAY SOUTH
- SEATTLE , WA 98134-2329
- USA
Primary Point of Contact
- Della S. Overton
- della.s.overton@usace.army.mil
- 2067646170
Secondary Point of Contact
- Shemekia McMillan
- Shemekia.R.Mcmillan@usace.army.mil
- 2067643730
History
- Mar 28, 2026 01:47 pm PDT Solicitation (Updated)
- Mar 20, 2026 12:17 pm PDT Solicitation (Original)
Named provisions
Related changes
Source
Classification
Who this affects
Taxonomy
Browse Categories
Get Trade & Sanctions alerts
Weekly digest. AI-summarized, no noise.
Free. Unsubscribe anytime.
Get alerts for this source
We'll email you when SAM.gov Environmental Compliance Services publishes new changes.