The Building and Construction Authority (BCA) of Singapore has issued the Building Control (Amendment) Regulations 2026, which introduce a formal definition of "lightning protection system" into the Building Control Regulations 2003. The amendment defines the system as comprising air-termination, down-conductor, and earth-termination components that intercept, conduct, and disperse lightning currents to earth. Most provisions take effect 1 April 2026, with select regulations effective 31 March 2026.

What changed

Regulation 2 of the Building Control Regulations 2003 is amended to add a new definition of "lightning protection system" which specifically describes the system as comprising three components: an air-termination system, a down-conductor system, and an earth-termination system. The definition clarifies that these components must be installed on or within a building and must collectively intercept, conduct, and disperse lightning currents to earth. The amendment is published as S 134 under the Building Control Act 1989.

Building owners, developers, architects, and contractors should review the Building Control Regulations 2026 to understand how the new lightning protection system definition may affect building design and construction requirements. The definition may trigger obligations for buildings to incorporate compliant lightning protection measures. Most amendments come into force on 1 April 2026, with regulations 7, 8, 9, and 11 effective 31 March 2026. Parties should consult with BCA or qualified professionals to ensure compliance with any new or updated technical requirements.

What to do next

  1. Review the new definition of lightning protection system added to Regulation 2 of the Building Control Regulations 2003
  2. Assess whether existing or planned buildings require compliant lightning protection systems under the updated regulations
  3. Consult with BCA or qualified engineers regarding any new obligations for building designs incorporating lightning protection measures

Source document (simplified)

Building Control (Amendment) Regulations 2026 Status:
Published in Subsidiary Legislation Supplement
on 30 Mar 2026
-
-
-
No. S 134
| Building Control Act 1989 |

| Building Control
(Amendment) Regulations 2026 |

| | In exercise of the powers conferred by section 49 of the Building Control Act 1989, the Minister for National Development makes the following Regulations: | | In exercise of the powers conferred by section 49 of the Building Control Act 1989, the Minister for National Development makes the following Regulations: |
| In exercise of the powers conferred by section 49 of the Building Control Act 1989, the Minister for National Development makes the following Regulations: | |

| Citation and commencement |

| 1. —(1)  These Regulations are the Building Control (Amendment) Regulations 2026 and, except for regulations 7, 8, 9 and 11, come into operation on 1 April 2026.
| (2)  Regulations 7, 8, 9 and 11 come into operation on 31 March 2026. | | (2)  Regulations 7, 8, 9 and 11 come into operation on 31 March 2026. |
| (2)  Regulations 7, 8, 9 and 11 come into operation on 31 March 2026. | |

| Amendment of regulation 2 |

| 2. In the Building Control Regulations 2003 (G.N. No. S 666/2003) (called in these Regulations the principal Regulations), in regulation 2, after the definition of “imposed load” or “imposed loading”, insert —
| \| “ “lightning protection system” means a system comprising an air‑termination system, a down‑conductor system and an earth‑termination system, which is installed on or within a building and collectively intercepts, conducts and disperses lightning currents to earth; ”. \| | “ “lightning protection system” means a system comprising an air‑termination system, a down‑conductor system and an earth‑termination system, which is installed on or within a building and collectively intercepts, conducts and disperses lightning currents to earth; ”. |
| “ “lightning protection system” means a system comprising an air‑termination system, a down‑conductor system and an earth‑termination system, which is installed on or within a building and collectively intercepts, conducts and disperses lightning currents to earth; ”. | | | | “ “lightning protection system” means a system comprising an air‑termination system, a down‑conductor system and an earth‑termination system, which is installed on or within a building and collectively intercepts, conducts and disperses lightning currents to earth; ”. | | “ “lightning protection system” means a system comprising an air‑termination system, a down‑conductor system and an earth‑termination system, which is installed on or within a building and collectively intercepts, conducts and disperses lightning currents to earth; ”. |
| | “ “lightning protection system” means a system comprising an air‑termination system, a down‑conductor system and an earth‑termination system, which is installed on or within a building and collectively intercepts, conducts and disperses lightning currents to earth; ”. | | “ “lightning protection system” means a system comprising an air‑termination system, a down‑conductor system and an earth‑termination system, which is installed on or within a building and collectively intercepts, conducts and disperses lightning currents to earth; ”. | |
| “ “lightning protection system” means a system comprising an air‑termination system, a down‑conductor system and an earth‑termination system, which is installed on or within a building and collectively intercepts, conducts and disperses lightning currents to earth; ”. | | |

| Amendment of regulation 4 |

| 3. In the principal Regulations, in regulation 4(1)(a) —
| (a) | in sub‑paragraph (v), delete “and” at the end; and | | | |
| (b) | after sub‑paragraph (vi), insert —
\| \| “ (vii) \| where applicable, lightning protection system plans; ”. \| \| “ (vii) \| where applicable, lightning protection system plans; ”. \|
\| “ (vii) \| where applicable, lightning protection system plans; ”. \| \| | \| “ (vii) \| where applicable, lightning protection system plans; ”. \| | “ (vii) | where applicable, lightning protection system plans; ”. |
| \| “ (vii) \| where applicable, lightning protection system plans; ”. \| | “ (vii) | where applicable, lightning protection system plans; ”. | | |
| “ (vii) | where applicable, lightning protection system plans; ”. | | | | | (a) | in sub‑paragraph (v), delete “and” at the end; and | (b) | after sub‑paragraph (vi), insert —
| \| “ (vii) \| where applicable, lightning protection system plans; ”. \| | “ (vii) | where applicable, lightning protection system plans; ”. |
| “ (vii) | where applicable, lightning protection system plans; ”. | | | | “ (vii) | where applicable, lightning protection system plans; ”. | | “ (vii) | where applicable, lightning protection system plans; ”. |
| (a) | in sub‑paragraph (v), delete “and” at the end; and | | | | | | |
| (b) | after sub‑paragraph (vi), insert —
| \| “ (vii) \| where applicable, lightning protection system plans; ”. \| | “ (vii) | where applicable, lightning protection system plans; ”. |
| “ (vii) | where applicable, lightning protection system plans; ”. | | | | “ (vii) | where applicable, lightning protection system plans; ”. | | “ (vii) | where applicable, lightning protection system plans; ”. | | | |
| | “ (vii) | where applicable, lightning protection system plans; ”. | | “ (vii) | where applicable, lightning protection system plans; ”. | | | | | |
| “ (vii) | where applicable, lightning protection system plans; ”. | | | | | | |

| Amendment of regulation 4A |

| 4. In the principal Regulations, in regulation 4A(1) —
| (a) | in paragraph (a), after sub‑paragraph (v), insert —
\| \| “ (vi) \| where applicable, lightning protection system plans; ”; and \| \| “ (vi) \| where applicable, lightning protection system plans; ”; and \|
\| “ (vi) \| where applicable, lightning protection system plans; ”; and \| \| | \| “ (vi) \| where applicable, lightning protection system plans; ”; and \| | “ (vi) | where applicable, lightning protection system plans; ”; and |
| \| “ (vi) \| where applicable, lightning protection system plans; ”; and \| | “ (vi) | where applicable, lightning protection system plans; ”; and | | |
| “ (vi) | where applicable, lightning protection system plans; ”; and | | | |
| (b) | in paragraph (b), replace “11” with “11A”. | | | | | (a) | in paragraph (a), after sub‑paragraph (v), insert —
| \| “ (vi) \| where applicable, lightning protection system plans; ”; and \| | “ (vi) | where applicable, lightning protection system plans; ”; and |
| “ (vi) | where applicable, lightning protection system plans; ”; and | | | | “ (vi) | where applicable, lightning protection system plans; ”; and | | “ (vi) | where applicable, lightning protection system plans; ”; and | (b) | in paragraph (b), replace “11” with “11A”. |
| (a) | in paragraph (a), after sub‑paragraph (v), insert —
| \| “ (vi) \| where applicable, lightning protection system plans; ”; and \| | “ (vi) | where applicable, lightning protection system plans; ”; and |
| “ (vi) | where applicable, lightning protection system plans; ”; and | | | | “ (vi) | where applicable, lightning protection system plans; ”; and | | “ (vi) | where applicable, lightning protection system plans; ”; and | | | |
| | “ (vi) | where applicable, lightning protection system plans; ”; and | | “ (vi) | where applicable, lightning protection system plans; ”; and | | | | | |
| “ (vi) | where applicable, lightning protection system plans; ”; and | | | | | | |
| (b) | in paragraph (b), replace “11” with “11A”. | | | | | | |

| New regulation 11A |

| 5. In the principal Regulations, after regulation 11, insert —
| \| “ Particulars to be shown on lightning protection system plans \|

\| 11A. —(1)  The lightning protection system plans mentioned in regulations 4(1)(a)(vii) and 4A(1)(a)(vi) must specify the class of lightning protection system and where applicable, consist of or contain the following:
\| (a) \| a site plan containing or showing —
\\| (i) \\| the location and layout of the site with boundary lines clearly verged; \\|
\\| (ii) \\| the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; \\|
\\| (iii) \\| the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; \\|
\\| (iv) \\| the distance between the new building to be erected or the building works to be carried out and the lot boundary; \\|
\\| (v) \\| any retaining wall on the lot; \\|
\\| (vi) \\| any existing and proposed platform level and slope; and \\|
\\| (vii) \\| the ingress and egress to the site; \\| \| (i) \| the location and layout of the site with boundary lines clearly verged; \| (ii) \| the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; \| (iii) \| the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; \| (iv) \| the distance between the new building to be erected or the building works to be carried out and the lot boundary; \| (v) \| any retaining wall on the lot; \| (vi) \| any existing and proposed platform level and slope; and \| (vii) \| the ingress and egress to the site; \|
\| (i) \| the location and layout of the site with boundary lines clearly verged; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (ii) \| the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (iii) \| the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (iv) \| the distance between the new building to be erected or the building works to be carried out and the lot boundary; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (v) \| any retaining wall on the lot; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (vi) \| any existing and proposed platform level and slope; and \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (vii) \| the ingress and egress to the site; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (b) \| the roof plan of the building containing or showing —
\\| (i) \\| the air-termination system; and \\|
\\| (ii) \\| the location of the down conductors; \\| \| (i) \| the air-termination system; and \| (ii) \| the location of the down conductors; \| \| \| \| \| \| \| \| \| \| \|
\| (i) \| the air-termination system; and \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (ii) \| the location of the down conductors; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (c) \| one or more elevation plans containing or showing —
\\| (i) \\| the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and \\|
\\| (ii) \\| the location of the down conductors; \\| \| (i) \| the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and \| (ii) \| the location of the down conductors; \| \| \| \| \| \| \| \| \| \| \|
\| (i) \| the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (ii) \| the location of the down conductors; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (d) \| the floor plan of each storey where the earth electrodes are located; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (e) \| one or more plans containing or showing —
\\| (i) \\| the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and \\|
\\| (ii) \\| the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); \\| \| (i) \| the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and \| (ii) \| the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); \| \| \| \| \| \| \| \| \| \| \|
\| (i) \| the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (ii) \| the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (f) \| such other details or plans as the Commissioner of Building Control may require. \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|

\| (2)  Without affecting regulations 6 and 7, all lightning protection system plans must —
\\| (a) \\| be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; \\|
\\| (b) \\| be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and \\|
\\| (c) \\| bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. \\| \| (a) \| be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; \| (b) \| be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and \| (c) \| bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. \|
\| (a) \| be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; \| \| \| \| \| \|
\| (b) \| be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and \| \| \| \| \| \|
\| (c) \| bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. \| \| \| \| \| \| \| (a) \| a site plan containing or showing —
\| (i) \| the location and layout of the site with boundary lines clearly verged; \|
\| (ii) \| the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; \|
\| (iii) \| the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; \|
\| (iv) \| the distance between the new building to be erected or the building works to be carried out and the lot boundary; \|
\| (v) \| any retaining wall on the lot; \|
\| (vi) \| any existing and proposed platform level and slope; and \|
\| (vii) \| the ingress and egress to the site; \| \| (i) \| the location and layout of the site with boundary lines clearly verged; \| (ii) \| the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; \| (iii) \| the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; \| (iv) \| the distance between the new building to be erected or the building works to be carried out and the lot boundary; \| (v) \| any retaining wall on the lot; \| (vi) \| any existing and proposed platform level and slope; and \| (vii) \| the ingress and egress to the site; \| (b) \| the roof plan of the building containing or showing —
\| (i) \| the air-termination system; and \|
\| (ii) \| the location of the down conductors; \| \| (i) \| the air-termination system; and \| (ii) \| the location of the down conductors; \| (c) \| one or more elevation plans containing or showing —
\| (i) \| the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and \|
\| (ii) \| the location of the down conductors; \| \| (i) \| the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and \| (ii) \| the location of the down conductors; \| (d) \| the floor plan of each storey where the earth electrodes are located; \| (e) \| one or more plans containing or showing —
\| (i) \| the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and \|
\| (ii) \| the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); \| \| (i) \| the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and \| (ii) \| the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); \| (f) \| such other details or plans as the Commissioner of Building Control may require. \| (2)  Without affecting regulations 6 and 7, all lightning protection system plans must —
\| (a) \| be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; \|
\| (b) \| be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and \|
\| (c) \| bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. \| \| (a) \| be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; \| (b) \| be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and \| (c) \| bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. \|
\| (a) \| a site plan containing or showing —
\| (i) \| the location and layout of the site with boundary lines clearly verged; \|
\| (ii) \| the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; \|
\| (iii) \| the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; \|
\| (iv) \| the distance between the new building to be erected or the building works to be carried out and the lot boundary; \|
\| (v) \| any retaining wall on the lot; \|
\| (vi) \| any existing and proposed platform level and slope; and \|
\| (vii) \| the ingress and egress to the site; \| \| (i) \| the location and layout of the site with boundary lines clearly verged; \| (ii) \| the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; \| (iii) \| the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; \| (iv) \| the distance between the new building to be erected or the building works to be carried out and the lot boundary; \| (v) \| any retaining wall on the lot; \| (vi) \| any existing and proposed platform level and slope; and \| (vii) \| the ingress and egress to the site; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (i) \| the location and layout of the site with boundary lines clearly verged; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (ii) \| the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (iii) \| the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (iv) \| the distance between the new building to be erected or the building works to be carried out and the lot boundary; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (v) \| any retaining wall on the lot; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (vi) \| any existing and proposed platform level and slope; and \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (vii) \| the ingress and egress to the site; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (b) \| the roof plan of the building containing or showing —
\| (i) \| the air-termination system; and \|
\| (ii) \| the location of the down conductors; \| \| (i) \| the air-termination system; and \| (ii) \| the location of the down conductors; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (i) \| the air-termination system; and \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (ii) \| the location of the down conductors; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (c) \| one or more elevation plans containing or showing —
\| (i) \| the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and \|
\| (ii) \| the location of the down conductors; \| \| (i) \| the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and \| (ii) \| the location of the down conductors; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (i) \| the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (ii) \| the location of the down conductors; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (d) \| the floor plan of each storey where the earth electrodes are located; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (e) \| one or more plans containing or showing —
\| (i) \| the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and \|
\| (ii) \| the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); \| \| (i) \| the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and \| (ii) \| the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (i) \| the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (ii) \| the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (f) \| such other details or plans as the Commissioner of Building Control may require. \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (2)  Without affecting regulations 6 and 7, all lightning protection system plans must —
\| (a) \| be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; \|
\| (b) \| be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and \|
\| (c) \| bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. \| \| (a) \| be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; \| (b) \| be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and \| (c) \| bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (a) \| be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (b) \| be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (c) \| bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| \| | “ Particulars to be shown on lightning protection system plans | 11A. —(1)  The lightning protection system plans mentioned in regulations 4(1)(a)(vii) and 4A(1)(a)(vi) must specify the class of lightning protection system and where applicable, consist of or contain the following:
\| (a) \| a site plan containing or showing —
\| (i) \| the location and layout of the site with boundary lines clearly verged; \|
\| (ii) \| the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; \|
\| (iii) \| the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; \|
\| (iv) \| the distance between the new building to be erected or the building works to be carried out and the lot boundary; \|
\| (v) \| any retaining wall on the lot; \|
\| (vi) \| any existing and proposed platform level and slope; and \|
\| (vii) \| the ingress and egress to the site; \| \| (i) \| the location and layout of the site with boundary lines clearly verged; \| (ii) \| the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; \| (iii) \| the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; \| (iv) \| the distance between the new building to be erected or the building works to be carried out and the lot boundary; \| (v) \| any retaining wall on the lot; \| (vi) \| any existing and proposed platform level and slope; and \| (vii) \| the ingress and egress to the site; \|
\| (i) \| the location and layout of the site with boundary lines clearly verged; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (ii) \| the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (iii) \| the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (iv) \| the distance between the new building to be erected or the building works to be carried out and the lot boundary; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (v) \| any retaining wall on the lot; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (vi) \| any existing and proposed platform level and slope; and \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (vii) \| the ingress and egress to the site; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (b) \| the roof plan of the building containing or showing —
\| (i) \| the air-termination system; and \|
\| (ii) \| the location of the down conductors; \| \| (i) \| the air-termination system; and \| (ii) \| the location of the down conductors; \| \| \| \| \| \| \| \| \| \| \|
\| (i) \| the air-termination system; and \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (ii) \| the location of the down conductors; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (c) \| one or more elevation plans containing or showing —
\| (i) \| the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and \|
\| (ii) \| the location of the down conductors; \| \| (i) \| the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and \| (ii) \| the location of the down conductors; \| \| \| \| \| \| \| \| \| \| \|
\| (i) \| the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (ii) \| the location of the down conductors; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (d) \| the floor plan of each storey where the earth electrodes are located; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (e) \| one or more plans containing or showing —
\| (i) \| the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and \|
\| (ii) \| the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); \| \| (i) \| the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and \| (ii) \| the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); \| \| \| \| \| \| \| \| \| \| \|
\| (i) \| the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (ii) \| the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (f) \| such other details or plans as the Commissioner of Building Control may require. \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|

\| (2)  Without affecting regulations 6 and 7, all lightning protection system plans must —
\| (a) \| be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; \|
\| (b) \| be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and \|
\| (c) \| bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. \| \| (a) \| be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; \| (b) \| be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and \| (c) \| bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. \|
\| (a) \| be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; \| \| \| \| \| \|
\| (b) \| be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and \| \| \| \| \| \|
\| (c) \| bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. \| \| \| \| \| \| | (a) | a site plan containing or showing —
\| (i) \| the location and layout of the site with boundary lines clearly verged; \|
\| (ii) \| the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; \|
\| (iii) \| the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; \|
\| (iv) \| the distance between the new building to be erected or the building works to be carried out and the lot boundary; \|
\| (v) \| any retaining wall on the lot; \|
\| (vi) \| any existing and proposed platform level and slope; and \|
\| (vii) \| the ingress and egress to the site; \| | (i) | the location and layout of the site with boundary lines clearly verged; | (ii) | the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; | (iii) | the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; | (iv) | the distance between the new building to be erected or the building works to be carried out and the lot boundary; | (v) | any retaining wall on the lot; | (vi) | any existing and proposed platform level and slope; and | (vii) | the ingress and egress to the site; | (b) | the roof plan of the building containing or showing —
\| (i) \| the air-termination system; and \|
\| (ii) \| the location of the down conductors; \| | (i) | the air-termination system; and | (ii) | the location of the down conductors; | (c) | one or more elevation plans containing or showing —
\| (i) \| the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and \|
\| (ii) \| the location of the down conductors; \| | (i) | the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and | (ii) | the location of the down conductors; | (d) | the floor plan of each storey where the earth electrodes are located; | (e) | one or more plans containing or showing —
\| (i) \| the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and \|
\| (ii) \| the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); \| | (i) | the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and | (ii) | the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); | (f) | such other details or plans as the Commissioner of Building Control may require. | (2)  Without affecting regulations 6 and 7, all lightning protection system plans must —
\| (a) \| be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; \|
\| (b) \| be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and \|
\| (c) \| bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. \| | (a) | be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; | (b) | be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and | (c) | bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. |
| “ Particulars to be shown on lightning protection system plans | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| 11A. —(1)  The lightning protection system plans mentioned in regulations 4(1)(a)(vii) and 4A(1)(a)(vi) must specify the class of lightning protection system and where applicable, consist of or contain the following:
\| (a) \| a site plan containing or showing —
\| (i) \| the location and layout of the site with boundary lines clearly verged; \|
\| (ii) \| the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; \|
\| (iii) \| the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; \|
\| (iv) \| the distance between the new building to be erected or the building works to be carried out and the lot boundary; \|
\| (v) \| any retaining wall on the lot; \|
\| (vi) \| any existing and proposed platform level and slope; and \|
\| (vii) \| the ingress and egress to the site; \| \| (i) \| the location and layout of the site with boundary lines clearly verged; \| (ii) \| the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; \| (iii) \| the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; \| (iv) \| the distance between the new building to be erected or the building works to be carried out and the lot boundary; \| (v) \| any retaining wall on the lot; \| (vi) \| any existing and proposed platform level and slope; and \| (vii) \| the ingress and egress to the site; \|
\| (i) \| the location and layout of the site with boundary lines clearly verged; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (ii) \| the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (iii) \| the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (iv) \| the distance between the new building to be erected or the building works to be carried out and the lot boundary; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (v) \| any retaining wall on the lot; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (vi) \| any existing and proposed platform level and slope; and \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (vii) \| the ingress and egress to the site; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (b) \| the roof plan of the building containing or showing —
\| (i) \| the air-termination system; and \|
\| (ii) \| the location of the down conductors; \| \| (i) \| the air-termination system; and \| (ii) \| the location of the down conductors; \| \| \| \| \| \| \| \| \| \| \|
\| (i) \| the air-termination system; and \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (ii) \| the location of the down conductors; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (c) \| one or more elevation plans containing or showing —
\| (i) \| the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and \|
\| (ii) \| the location of the down conductors; \| \| (i) \| the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and \| (ii) \| the location of the down conductors; \| \| \| \| \| \| \| \| \| \| \|
\| (i) \| the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (ii) \| the location of the down conductors; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (d) \| the floor plan of each storey where the earth electrodes are located; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (e) \| one or more plans containing or showing —
\| (i) \| the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and \|
\| (ii) \| the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); \| \| (i) \| the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and \| (ii) \| the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); \| \| \| \| \| \| \| \| \| \| \|
\| (i) \| the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (ii) \| the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (f) \| such other details or plans as the Commissioner of Building Control may require. \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|

\| (2)  Without affecting regulations 6 and 7, all lightning protection system plans must —
\| (a) \| be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; \|
\| (b) \| be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and \|
\| (c) \| bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. \| \| (a) \| be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; \| (b) \| be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and \| (c) \| bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. \|
\| (a) \| be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; \| \| \| \| \| \|
\| (b) \| be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and \| \| \| \| \| \|
\| (c) \| bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. \| \| \| \| \| \| | (a) | a site plan containing or showing —
\| (i) \| the location and layout of the site with boundary lines clearly verged; \|
\| (ii) \| the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; \|
\| (iii) \| the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; \|
\| (iv) \| the distance between the new building to be erected or the building works to be carried out and the lot boundary; \|
\| (v) \| any retaining wall on the lot; \|
\| (vi) \| any existing and proposed platform level and slope; and \|
\| (vii) \| the ingress and egress to the site; \| | (i) | the location and layout of the site with boundary lines clearly verged; | (ii) | the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; | (iii) | the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; | (iv) | the distance between the new building to be erected or the building works to be carried out and the lot boundary; | (v) | any retaining wall on the lot; | (vi) | any existing and proposed platform level and slope; and | (vii) | the ingress and egress to the site; | (b) | the roof plan of the building containing or showing —
\| (i) \| the air-termination system; and \|
\| (ii) \| the location of the down conductors; \| | (i) | the air-termination system; and | (ii) | the location of the down conductors; | (c) | one or more elevation plans containing or showing —
\| (i) \| the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and \|
\| (ii) \| the location of the down conductors; \| | (i) | the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and | (ii) | the location of the down conductors; | (d) | the floor plan of each storey where the earth electrodes are located; | (e) | one or more plans containing or showing —
\| (i) \| the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and \|
\| (ii) \| the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); \| | (i) | the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and | (ii) | the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); | (f) | such other details or plans as the Commissioner of Building Control may require. | (2)  Without affecting regulations 6 and 7, all lightning protection system plans must —
\| (a) \| be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; \|
\| (b) \| be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and \|
\| (c) \| bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. \| | (a) | be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; | (b) | be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and | (c) | bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. | | |
| (a) | a site plan containing or showing —
\| (i) \| the location and layout of the site with boundary lines clearly verged; \|
\| (ii) \| the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; \|
\| (iii) \| the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; \|
\| (iv) \| the distance between the new building to be erected or the building works to be carried out and the lot boundary; \|
\| (v) \| any retaining wall on the lot; \|
\| (vi) \| any existing and proposed platform level and slope; and \|
\| (vii) \| the ingress and egress to the site; \| | (i) | the location and layout of the site with boundary lines clearly verged; | (ii) | the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; | (iii) | the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; | (iv) | the distance between the new building to be erected or the building works to be carried out and the lot boundary; | (v) | any retaining wall on the lot; | (vi) | any existing and proposed platform level and slope; and | (vii) | the ingress and egress to the site; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (i) | the location and layout of the site with boundary lines clearly verged; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (ii) | the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (iii) | the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (iv) | the distance between the new building to be erected or the building works to be carried out and the lot boundary; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (v) | any retaining wall on the lot; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (vi) | any existing and proposed platform level and slope; and | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (vii) | the ingress and egress to the site; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (b) | the roof plan of the building containing or showing —
\| (i) \| the air-termination system; and \|
\| (ii) \| the location of the down conductors; \| | (i) | the air-termination system; and | (ii) | the location of the down conductors; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (i) | the air-termination system; and | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (ii) | the location of the down conductors; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (c) | one or more elevation plans containing or showing —
\| (i) \| the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and \|
\| (ii) \| the location of the down conductors; \| | (i) | the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and | (ii) | the location of the down conductors; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (i) | the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (ii) | the location of the down conductors; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (d) | the floor plan of each storey where the earth electrodes are located; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (e) | one or more plans containing or showing —
\| (i) \| the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and \|
\| (ii) \| the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); \| | (i) | the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and | (ii) | the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (i) | the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (ii) | the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (f) | such other details or plans as the Commissioner of Building Control may require. | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (2)  Without affecting regulations 6 and 7, all lightning protection system plans must —
\| (a) \| be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; \|
\| (b) \| be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and \|
\| (c) \| bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. \| | (a) | be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; | (b) | be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and | (c) | bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (a) | be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (b) | be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (c) | bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | “ Particulars to be shown on lightning protection system plans |

| 11A. —(1)  The lightning protection system plans mentioned in regulations 4(1)(a)(vii) and 4A(1)(a)(vi) must specify the class of lightning protection system and where applicable, consist of or contain the following:
\| (a) \| a site plan containing or showing —
\| (i) \| the location and layout of the site with boundary lines clearly verged; \|
\| (ii) \| the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; \|
\| (iii) \| the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; \|
\| (iv) \| the distance between the new building to be erected or the building works to be carried out and the lot boundary; \|
\| (v) \| any retaining wall on the lot; \|
\| (vi) \| any existing and proposed platform level and slope; and \|
\| (vii) \| the ingress and egress to the site; \| \| (i) \| the location and layout of the site with boundary lines clearly verged; \| (ii) \| the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; \| (iii) \| the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; \| (iv) \| the distance between the new building to be erected or the building works to be carried out and the lot boundary; \| (v) \| any retaining wall on the lot; \| (vi) \| any existing and proposed platform level and slope; and \| (vii) \| the ingress and egress to the site; \|
\| (i) \| the location and layout of the site with boundary lines clearly verged; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (ii) \| the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (iii) \| the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (iv) \| the distance between the new building to be erected or the building works to be carried out and the lot boundary; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (v) \| any retaining wall on the lot; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (vi) \| any existing and proposed platform level and slope; and \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (vii) \| the ingress and egress to the site; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (b) \| the roof plan of the building containing or showing —
\| (i) \| the air-termination system; and \|
\| (ii) \| the location of the down conductors; \| \| (i) \| the air-termination system; and \| (ii) \| the location of the down conductors; \| \| \| \| \| \| \| \| \| \| \|
\| (i) \| the air-termination system; and \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (ii) \| the location of the down conductors; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (c) \| one or more elevation plans containing or showing —
\| (i) \| the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and \|
\| (ii) \| the location of the down conductors; \| \| (i) \| the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and \| (ii) \| the location of the down conductors; \| \| \| \| \| \| \| \| \| \| \|
\| (i) \| the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (ii) \| the location of the down conductors; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (d) \| the floor plan of each storey where the earth electrodes are located; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (e) \| one or more plans containing or showing —
\| (i) \| the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and \|
\| (ii) \| the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); \| \| (i) \| the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and \| (ii) \| the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); \| \| \| \| \| \| \| \| \| \| \|
\| (i) \| the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (ii) \| the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (f) \| such other details or plans as the Commissioner of Building Control may require. \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|

\| (2)  Without affecting regulations 6 and 7, all lightning protection system plans must —
\| (a) \| be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; \|
\| (b) \| be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and \|
\| (c) \| bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. \| \| (a) \| be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; \| (b) \| be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and \| (c) \| bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. \|
\| (a) \| be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; \| \| \| \| \| \|
\| (b) \| be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and \| \| \| \| \| \|
\| (c) \| bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. \| \| \| \| \| \| | (a) | a site plan containing or showing —
\| (i) \| the location and layout of the site with boundary lines clearly verged; \|
\| (ii) \| the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; \|
\| (iii) \| the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; \|
\| (iv) \| the distance between the new building to be erected or the building works to be carried out and the lot boundary; \|
\| (v) \| any retaining wall on the lot; \|
\| (vi) \| any existing and proposed platform level and slope; and \|
\| (vii) \| the ingress and egress to the site; \| | (i) | the location and layout of the site with boundary lines clearly verged; | (ii) | the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; | (iii) | the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; | (iv) | the distance between the new building to be erected or the building works to be carried out and the lot boundary; | (v) | any retaining wall on the lot; | (vi) | any existing and proposed platform level and slope; and | (vii) | the ingress and egress to the site; | (b) | the roof plan of the building containing or showing —
\| (i) \| the air-termination system; and \|
\| (ii) \| the location of the down conductors; \| | (i) | the air-termination system; and | (ii) | the location of the down conductors; | (c) | one or more elevation plans containing or showing —
\| (i) \| the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and \|
\| (ii) \| the location of the down conductors; \| | (i) | the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and | (ii) | the location of the down conductors; | (d) | the floor plan of each storey where the earth electrodes are located; | (e) | one or more plans containing or showing —
\| (i) \| the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and \|
\| (ii) \| the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); \| | (i) | the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and | (ii) | the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); | (f) | such other details or plans as the Commissioner of Building Control may require. | (2)  Without affecting regulations 6 and 7, all lightning protection system plans must —
\| (a) \| be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; \|
\| (b) \| be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and \|
\| (c) \| bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. \| | (a) | be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; | (b) | be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and | (c) | bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. |
| (a) | a site plan containing or showing —
\| (i) \| the location and layout of the site with boundary lines clearly verged; \|
\| (ii) \| the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; \|
\| (iii) \| the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; \|
\| (iv) \| the distance between the new building to be erected or the building works to be carried out and the lot boundary; \|
\| (v) \| any retaining wall on the lot; \|
\| (vi) \| any existing and proposed platform level and slope; and \|
\| (vii) \| the ingress and egress to the site; \| | (i) | the location and layout of the site with boundary lines clearly verged; | (ii) | the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; | (iii) | the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; | (iv) | the distance between the new building to be erected or the building works to be carried out and the lot boundary; | (v) | any retaining wall on the lot; | (vi) | any existing and proposed platform level and slope; and | (vii) | the ingress and egress to the site; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (i) | the location and layout of the site with boundary lines clearly verged; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (ii) | the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (iii) | the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (iv) | the distance between the new building to be erected or the building works to be carried out and the lot boundary; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (v) | any retaining wall on the lot; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (vi) | any existing and proposed platform level and slope; and | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (vii) | the ingress and egress to the site; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (b) | the roof plan of the building containing or showing —
\| (i) \| the air-termination system; and \|
\| (ii) \| the location of the down conductors; \| | (i) | the air-termination system; and | (ii) | the location of the down conductors; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (i) | the air-termination system; and | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (ii) | the location of the down conductors; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (c) | one or more elevation plans containing or showing —
\| (i) \| the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and \|
\| (ii) \| the location of the down conductors; \| | (i) | the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and | (ii) | the location of the down conductors; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (i) | the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (ii) | the location of the down conductors; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (d) | the floor plan of each storey where the earth electrodes are located; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (e) | one or more plans containing or showing —
\| (i) \| the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and \|
\| (ii) \| the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); \| | (i) | the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and | (ii) | the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (i) | the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (ii) | the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (f) | such other details or plans as the Commissioner of Building Control may require. | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (2)  Without affecting regulations 6 and 7, all lightning protection system plans must —
\| (a) \| be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; \|
\| (b) \| be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and \|
\| (c) \| bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. \| | (a) | be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; | (b) | be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and | (c) | bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (a) | be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (b) | be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (c) | bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | “ Particulars to be shown on lightning protection system plans | 11A. —(1)  The lightning protection system plans mentioned in regulations 4(1)(a)(vii) and 4A(1)(a)(vi) must specify the class of lightning protection system and where applicable, consist of or contain the following:
| (a) | a site plan containing or showing —
\| (i) \| the location and layout of the site with boundary lines clearly verged; \|
\| (ii) \| the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; \|
\| (iii) \| the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; \|
\| (iv) \| the distance between the new building to be erected or the building works to be carried out and the lot boundary; \|
\| (v) \| any retaining wall on the lot; \|
\| (vi) \| any existing and proposed platform level and slope; and \|
\| (vii) \| the ingress and egress to the site; \| | (i) | the location and layout of the site with boundary lines clearly verged; | (ii) | the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; | (iii) | the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; | (iv) | the distance between the new building to be erected or the building works to be carried out and the lot boundary; | (v) | any retaining wall on the lot; | (vi) | any existing and proposed platform level and slope; and | (vii) | the ingress and egress to the site; |
| (i) | the location and layout of the site with boundary lines clearly verged; | | | | | | | | | | | | | | |
| (ii) | the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; | | | | | | | | | | | | | | |
| (iii) | the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; | | | | | | | | | | | | | | |
| (iv) | the distance between the new building to be erected or the building works to be carried out and the lot boundary; | | | | | | | | | | | | | | |
| (v) | any retaining wall on the lot; | | | | | | | | | | | | | | |
| (vi) | any existing and proposed platform level and slope; and | | | | | | | | | | | | | | |
| (vii) | the ingress and egress to the site; | | | | | | | | | | | | | | |
| (b) | the roof plan of the building containing or showing —
\| (i) \| the air-termination system; and \|
\| (ii) \| the location of the down conductors; \| | (i) | the air-termination system; and | (ii) | the location of the down conductors; | | | | | | | | | | |
| (i) | the air-termination system; and | | | | | | | | | | | | | | |
| (ii) | the location of the down conductors; | | | | | | | | | | | | | | |
| (c) | one or more elevation plans containing or showing —
\| (i) \| the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and \|
\| (ii) \| the location of the down conductors; \| | (i) | the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and | (ii) | the location of the down conductors; | | | | | | | | | | |
| (i) | the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and | | | | | | | | | | | | | | |
| (ii) | the location of the down conductors; | | | | | | | | | | | | | | |
| (d) | the floor plan of each storey where the earth electrodes are located; | | | | | | | | | | | | | | |
| (e) | one or more plans containing or showing —
\| (i) \| the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and \|
\| (ii) \| the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); \| | (i) | the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and | (ii) | the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); | | | | | | | | | | |
| (i) | the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and | | | | | | | | | | | | | | |
| (ii) | the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); | | | | | | | | | | | | | | |
| (f) | such other details or plans as the Commissioner of Building Control may require. | | | | | | | | | | | | | | |

| (2)  Without affecting regulations 6 and 7, all lightning protection system plans must —
\| (a) \| be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; \|
\| (b) \| be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and \|
\| (c) \| bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. \| | (a) | be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; | (b) | be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and | (c) | bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. |
| (a) | be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; | | | | | |
| (b) | be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and | | | | | |
| (c) | bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. | | | | | | | (a) | a site plan containing or showing —
| (i) | the location and layout of the site with boundary lines clearly verged; |
| (ii) | the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; |
| (iii) | the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; |
| (iv) | the distance between the new building to be erected or the building works to be carried out and the lot boundary; |
| (v) | any retaining wall on the lot; |
| (vi) | any existing and proposed platform level and slope; and |
| (vii) | the ingress and egress to the site; | | (i) | the location and layout of the site with boundary lines clearly verged; | (ii) | the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; | (iii) | the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; | (iv) | the distance between the new building to be erected or the building works to be carried out and the lot boundary; | (v) | any retaining wall on the lot; | (vi) | any existing and proposed platform level and slope; and | (vii) | the ingress and egress to the site; | (b) | the roof plan of the building containing or showing —
| (i) | the air-termination system; and |
| (ii) | the location of the down conductors; | | (i) | the air-termination system; and | (ii) | the location of the down conductors; | (c) | one or more elevation plans containing or showing —
| (i) | the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and |
| (ii) | the location of the down conductors; | | (i) | the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and | (ii) | the location of the down conductors; | (d) | the floor plan of each storey where the earth electrodes are located; | (e) | one or more plans containing or showing —
| (i) | the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and |
| (ii) | the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); | | (i) | the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and | (ii) | the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); | (f) | such other details or plans as the Commissioner of Building Control may require. | (2)  Without affecting regulations 6 and 7, all lightning protection system plans must —
| (a) | be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; |
| (b) | be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and |
| (c) | bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. | | (a) | be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; | (b) | be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and | (c) | bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. |
| | “ Particulars to be shown on lightning protection system plans |

| 11A. —(1)  The lightning protection system plans mentioned in regulations 4(1)(a)(vii) and 4A(1)(a)(vi) must specify the class of lightning protection system and where applicable, consist of or contain the following:
\| (a) \| a site plan containing or showing —
\| (i) \| the location and layout of the site with boundary lines clearly verged; \|
\| (ii) \| the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; \|
\| (iii) \| the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; \|
\| (iv) \| the distance between the new building to be erected or the building works to be carried out and the lot boundary; \|
\| (v) \| any retaining wall on the lot; \|
\| (vi) \| any existing and proposed platform level and slope; and \|
\| (vii) \| the ingress and egress to the site; \| \| (i) \| the location and layout of the site with boundary lines clearly verged; \| (ii) \| the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; \| (iii) \| the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; \| (iv) \| the distance between the new building to be erected or the building works to be carried out and the lot boundary; \| (v) \| any retaining wall on the lot; \| (vi) \| any existing and proposed platform level and slope; and \| (vii) \| the ingress and egress to the site; \|
\| (i) \| the location and layout of the site with boundary lines clearly verged; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (ii) \| the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (iii) \| the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (iv) \| the distance between the new building to be erected or the building works to be carried out and the lot boundary; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (v) \| any retaining wall on the lot; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (vi) \| any existing and proposed platform level and slope; and \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (vii) \| the ingress and egress to the site; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (b) \| the roof plan of the building containing or showing —
\| (i) \| the air-termination system; and \|
\| (ii) \| the location of the down conductors; \| \| (i) \| the air-termination system; and \| (ii) \| the location of the down conductors; \| \| \| \| \| \| \| \| \| \| \|
\| (i) \| the air-termination system; and \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (ii) \| the location of the down conductors; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (c) \| one or more elevation plans containing or showing —
\| (i) \| the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and \|
\| (ii) \| the location of the down conductors; \| \| (i) \| the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and \| (ii) \| the location of the down conductors; \| \| \| \| \| \| \| \| \| \| \|
\| (i) \| the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (ii) \| the location of the down conductors; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (d) \| the floor plan of each storey where the earth electrodes are located; \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (e) \| one or more plans containing or showing —
\| (i) \| the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and \|
\| (ii) \| the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); \| \| (i) \| the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and \| (ii) \| the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); \| \| \| \| \| \| \| \| \| \| \|
\| (i) \| the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (ii) \| the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (f) \| such other details or plans as the Commissioner of Building Control may require. \| \| \| \| \| \| \| \| \| \| \| \| \| \| \|

\| (2)  Without affecting regulations 6 and 7, all lightning protection system plans must —
\| (a) \| be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; \|
\| (b) \| be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and \|
\| (c) \| bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. \| \| (a) \| be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; \| (b) \| be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and \| (c) \| bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. \|
\| (a) \| be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; \| \| \| \| \| \|
\| (b) \| be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and \| \| \| \| \| \|
\| (c) \| bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. \| \| \| \| \| \| | (a) | a site plan containing or showing —
\| (i) \| the location and layout of the site with boundary lines clearly verged; \|
\| (ii) \| the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; \|
\| (iii) \| the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; \|
\| (iv) \| the distance between the new building to be erected or the building works to be carried out and the lot boundary; \|
\| (v) \| any retaining wall on the lot; \|
\| (vi) \| any existing and proposed platform level and slope; and \|
\| (vii) \| the ingress and egress to the site; \| | (i) | the location and layout of the site with boundary lines clearly verged; | (ii) | the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; | (iii) | the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; | (iv) | the distance between the new building to be erected or the building works to be carried out and the lot boundary; | (v) | any retaining wall on the lot; | (vi) | any existing and proposed platform level and slope; and | (vii) | the ingress and egress to the site; | (b) | the roof plan of the building containing or showing —
\| (i) \| the air-termination system; and \|
\| (ii) \| the location of the down conductors; \| | (i) | the air-termination system; and | (ii) | the location of the down conductors; | (c) | one or more elevation plans containing or showing —
\| (i) \| the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and \|
\| (ii) \| the location of the down conductors; \| | (i) | the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and | (ii) | the location of the down conductors; | (d) | the floor plan of each storey where the earth electrodes are located; | (e) | one or more plans containing or showing —
\| (i) \| the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and \|
\| (ii) \| the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); \| | (i) | the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and | (ii) | the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); | (f) | such other details or plans as the Commissioner of Building Control may require. | (2)  Without affecting regulations 6 and 7, all lightning protection system plans must —
\| (a) \| be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; \|
\| (b) \| be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and \|
\| (c) \| bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. \| | (a) | be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; | (b) | be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and | (c) | bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. |
| (a) | a site plan containing or showing —
\| (i) \| the location and layout of the site with boundary lines clearly verged; \|
\| (ii) \| the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; \|
\| (iii) \| the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; \|
\| (iv) \| the distance between the new building to be erected or the building works to be carried out and the lot boundary; \|
\| (v) \| any retaining wall on the lot; \|
\| (vi) \| any existing and proposed platform level and slope; and \|
\| (vii) \| the ingress and egress to the site; \| | (i) | the location and layout of the site with boundary lines clearly verged; | (ii) | the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; | (iii) | the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; | (iv) | the distance between the new building to be erected or the building works to be carried out and the lot boundary; | (v) | any retaining wall on the lot; | (vi) | any existing and proposed platform level and slope; and | (vii) | the ingress and egress to the site; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (i) | the location and layout of the site with boundary lines clearly verged; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (ii) | the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (iii) | the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (iv) | the distance between the new building to be erected or the building works to be carried out and the lot boundary; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (v) | any retaining wall on the lot; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (vi) | any existing and proposed platform level and slope; and | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (vii) | the ingress and egress to the site; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (b) | the roof plan of the building containing or showing —
\| (i) \| the air-termination system; and \|
\| (ii) \| the location of the down conductors; \| | (i) | the air-termination system; and | (ii) | the location of the down conductors; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (i) | the air-termination system; and | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (ii) | the location of the down conductors; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (c) | one or more elevation plans containing or showing —
\| (i) \| the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and \|
\| (ii) \| the location of the down conductors; \| | (i) | the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and | (ii) | the location of the down conductors; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (i) | the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (ii) | the location of the down conductors; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (d) | the floor plan of each storey where the earth electrodes are located; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (e) | one or more plans containing or showing —
\| (i) \| the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and \|
\| (ii) \| the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); \| | (i) | the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and | (ii) | the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (i) | the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (ii) | the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (f) | such other details or plans as the Commissioner of Building Control may require. | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (2)  Without affecting regulations 6 and 7, all lightning protection system plans must —
\| (a) \| be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; \|
\| (b) \| be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and \|
\| (c) \| bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. \| | (a) | be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; | (b) | be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and | (c) | bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (a) | be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (b) | be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (c) | bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | “ Particulars to be shown on lightning protection system plans | 11A. —(1)  The lightning protection system plans mentioned in regulations 4(1)(a)(vii) and 4A(1)(a)(vi) must specify the class of lightning protection system and where applicable, consist of or contain the following:
| (a) | a site plan containing or showing —
\| (i) \| the location and layout of the site with boundary lines clearly verged; \|
\| (ii) \| the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; \|
\| (iii) \| the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; \|
\| (iv) \| the distance between the new building to be erected or the building works to be carried out and the lot boundary; \|
\| (v) \| any retaining wall on the lot; \|
\| (vi) \| any existing and proposed platform level and slope; and \|
\| (vii) \| the ingress and egress to the site; \| | (i) | the location and layout of the site with boundary lines clearly verged; | (ii) | the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; | (iii) | the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; | (iv) | the distance between the new building to be erected or the building works to be carried out and the lot boundary; | (v) | any retaining wall on the lot; | (vi) | any existing and proposed platform level and slope; and | (vii) | the ingress and egress to the site; |
| (i) | the location and layout of the site with boundary lines clearly verged; | | | | | | | | | | | | | | |
| (ii) | the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; | | | | | | | | | | | | | | |
| (iii) | the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; | | | | | | | | | | | | | | |
| (iv) | the distance between the new building to be erected or the building works to be carried out and the lot boundary; | | | | | | | | | | | | | | |
| (v) | any retaining wall on the lot; | | | | | | | | | | | | | | |
| (vi) | any existing and proposed platform level and slope; and | | | | | | | | | | | | | | |
| (vii) | the ingress and egress to the site; | | | | | | | | | | | | | | |
| (b) | the roof plan of the building containing or showing —
\| (i) \| the air-termination system; and \|
\| (ii) \| the location of the down conductors; \| | (i) | the air-termination system; and | (ii) | the location of the down conductors; | | | | | | | | | | |
| (i) | the air-termination system; and | | | | | | | | | | | | | | |
| (ii) | the location of the down conductors; | | | | | | | | | | | | | | |
| (c) | one or more elevation plans containing or showing —
\| (i) \| the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and \|
\| (ii) \| the location of the down conductors; \| | (i) | the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and | (ii) | the location of the down conductors; | | | | | | | | | | |
| (i) | the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and | | | | | | | | | | | | | | |
| (ii) | the location of the down conductors; | | | | | | | | | | | | | | |
| (d) | the floor plan of each storey where the earth electrodes are located; | | | | | | | | | | | | | | |
| (e) | one or more plans containing or showing —
\| (i) \| the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and \|
\| (ii) \| the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); \| | (i) | the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and | (ii) | the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); | | | | | | | | | | |
| (i) | the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and | | | | | | | | | | | | | | |
| (ii) | the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); | | | | | | | | | | | | | | |
| (f) | such other details or plans as the Commissioner of Building Control may require. | | | | | | | | | | | | | | |

| (2)  Without affecting regulations 6 and 7, all lightning protection system plans must —
\| (a) \| be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; \|
\| (b) \| be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and \|
\| (c) \| bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. \| | (a) | be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; | (b) | be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and | (c) | bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. |
| (a) | be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; | | | | | |
| (b) | be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and | | | | | |
| (c) | bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. | | | | | | | (a) | a site plan containing or showing —
| (i) | the location and layout of the site with boundary lines clearly verged; |
| (ii) | the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; |
| (iii) | the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; |
| (iv) | the distance between the new building to be erected or the building works to be carried out and the lot boundary; |
| (v) | any retaining wall on the lot; |
| (vi) | any existing and proposed platform level and slope; and |
| (vii) | the ingress and egress to the site; | | (i) | the location and layout of the site with boundary lines clearly verged; | (ii) | the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; | (iii) | the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; | (iv) | the distance between the new building to be erected or the building works to be carried out and the lot boundary; | (v) | any retaining wall on the lot; | (vi) | any existing and proposed platform level and slope; and | (vii) | the ingress and egress to the site; | (b) | the roof plan of the building containing or showing —
| (i) | the air-termination system; and |
| (ii) | the location of the down conductors; | | (i) | the air-termination system; and | (ii) | the location of the down conductors; | (c) | one or more elevation plans containing or showing —
| (i) | the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and |
| (ii) | the location of the down conductors; | | (i) | the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and | (ii) | the location of the down conductors; | (d) | the floor plan of each storey where the earth electrodes are located; | (e) | one or more plans containing or showing —
| (i) | the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and |
| (ii) | the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); | | (i) | the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and | (ii) | the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); | (f) | such other details or plans as the Commissioner of Building Control may require. | (2)  Without affecting regulations 6 and 7, all lightning protection system plans must —
| (a) | be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; |
| (b) | be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and |
| (c) | bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. | | (a) | be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; | (b) | be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and | (c) | bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. | |
| “ Particulars to be shown on lightning protection system plans | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| 11A. —(1)  The lightning protection system plans mentioned in regulations 4(1)(a)(vii) and 4A(1)(a)(vi) must specify the class of lightning protection system and where applicable, consist of or contain the following:
| (a) | a site plan containing or showing —
\| (i) \| the location and layout of the site with boundary lines clearly verged; \|
\| (ii) \| the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; \|
\| (iii) \| the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; \|
\| (iv) \| the distance between the new building to be erected or the building works to be carried out and the lot boundary; \|
\| (v) \| any retaining wall on the lot; \|
\| (vi) \| any existing and proposed platform level and slope; and \|
\| (vii) \| the ingress and egress to the site; \| | (i) | the location and layout of the site with boundary lines clearly verged; | (ii) | the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; | (iii) | the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; | (iv) | the distance between the new building to be erected or the building works to be carried out and the lot boundary; | (v) | any retaining wall on the lot; | (vi) | any existing and proposed platform level and slope; and | (vii) | the ingress and egress to the site; |
| (i) | the location and layout of the site with boundary lines clearly verged; | | | | | | | | | | | | | | |
| (ii) | the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; | | | | | | | | | | | | | | |
| (iii) | the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; | | | | | | | | | | | | | | |
| (iv) | the distance between the new building to be erected or the building works to be carried out and the lot boundary; | | | | | | | | | | | | | | |
| (v) | any retaining wall on the lot; | | | | | | | | | | | | | | |
| (vi) | any existing and proposed platform level and slope; and | | | | | | | | | | | | | | |
| (vii) | the ingress and egress to the site; | | | | | | | | | | | | | | |
| (b) | the roof plan of the building containing or showing —
\| (i) \| the air-termination system; and \|
\| (ii) \| the location of the down conductors; \| | (i) | the air-termination system; and | (ii) | the location of the down conductors; | | | | | | | | | | |
| (i) | the air-termination system; and | | | | | | | | | | | | | | |
| (ii) | the location of the down conductors; | | | | | | | | | | | | | | |
| (c) | one or more elevation plans containing or showing —
\| (i) \| the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and \|
\| (ii) \| the location of the down conductors; \| | (i) | the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and | (ii) | the location of the down conductors; | | | | | | | | | | |
| (i) | the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and | | | | | | | | | | | | | | |
| (ii) | the location of the down conductors; | | | | | | | | | | | | | | |
| (d) | the floor plan of each storey where the earth electrodes are located; | | | | | | | | | | | | | | |
| (e) | one or more plans containing or showing —
\| (i) \| the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and \|
\| (ii) \| the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); \| | (i) | the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and | (ii) | the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); | | | | | | | | | | |
| (i) | the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and | | | | | | | | | | | | | | |
| (ii) | the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); | | | | | | | | | | | | | | |
| (f) | such other details or plans as the Commissioner of Building Control may require. | | | | | | | | | | | | | | |

| (2)  Without affecting regulations 6 and 7, all lightning protection system plans must —
\| (a) \| be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; \|
\| (b) \| be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and \|
\| (c) \| bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. \| | (a) | be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; | (b) | be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and | (c) | bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. |
| (a) | be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; | | | | | |
| (b) | be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and | | | | | |
| (c) | bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. | | | | | | | (a) | a site plan containing or showing —
| (i) | the location and layout of the site with boundary lines clearly verged; |
| (ii) | the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; |
| (iii) | the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; |
| (iv) | the distance between the new building to be erected or the building works to be carried out and the lot boundary; |
| (v) | any retaining wall on the lot; |
| (vi) | any existing and proposed platform level and slope; and |
| (vii) | the ingress and egress to the site; | | (i) | the location and layout of the site with boundary lines clearly verged; | (ii) | the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; | (iii) | the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; | (iv) | the distance between the new building to be erected or the building works to be carried out and the lot boundary; | (v) | any retaining wall on the lot; | (vi) | any existing and proposed platform level and slope; and | (vii) | the ingress and egress to the site; | (b) | the roof plan of the building containing or showing —
| (i) | the air-termination system; and |
| (ii) | the location of the down conductors; | | (i) | the air-termination system; and | (ii) | the location of the down conductors; | (c) | one or more elevation plans containing or showing —
| (i) | the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and |
| (ii) | the location of the down conductors; | | (i) | the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and | (ii) | the location of the down conductors; | (d) | the floor plan of each storey where the earth electrodes are located; | (e) | one or more plans containing or showing —
| (i) | the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and |
| (ii) | the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); | | (i) | the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and | (ii) | the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); | (f) | such other details or plans as the Commissioner of Building Control may require. | (2)  Without affecting regulations 6 and 7, all lightning protection system plans must —
| (a) | be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; |
| (b) | be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and |
| (c) | bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. | | (a) | be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; | (b) | be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and | (c) | bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. | | | |
| (a) | a site plan containing or showing —
| (i) | the location and layout of the site with boundary lines clearly verged; |
| (ii) | the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; |
| (iii) | the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; |
| (iv) | the distance between the new building to be erected or the building works to be carried out and the lot boundary; |
| (v) | any retaining wall on the lot; |
| (vi) | any existing and proposed platform level and slope; and |
| (vii) | the ingress and egress to the site; | | (i) | the location and layout of the site with boundary lines clearly verged; | (ii) | the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; | (iii) | the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; | (iv) | the distance between the new building to be erected or the building works to be carried out and the lot boundary; | (v) | any retaining wall on the lot; | (vi) | any existing and proposed platform level and slope; and | (vii) | the ingress and egress to the site; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (i) | the location and layout of the site with boundary lines clearly verged; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (ii) | the outline of the building to be erected or building in which building works are to be carried out marked in colour or otherwise; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (iii) | the north point, or the georeference, and the number of the lot and adjoining lots and the Mukim (MK) or Town Subdivision (TS) number of the lot; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (iv) | the distance between the new building to be erected or the building works to be carried out and the lot boundary; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (v) | any retaining wall on the lot; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (vi) | any existing and proposed platform level and slope; and | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (vii) | the ingress and egress to the site; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (b) | the roof plan of the building containing or showing —
| (i) | the air-termination system; and |
| (ii) | the location of the down conductors; | | (i) | the air-termination system; and | (ii) | the location of the down conductors; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (i) | the air-termination system; and | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (ii) | the location of the down conductors; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (c) | one or more elevation plans containing or showing —
| (i) | the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and |
| (ii) | the location of the down conductors; | | (i) | the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and | (ii) | the location of the down conductors; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (i) | the zones of lightning protection provided by the air‑termination network for the open roof spaces and the sides of the building; and | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (ii) | the location of the down conductors; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (d) | the floor plan of each storey where the earth electrodes are located; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (e) | one or more plans containing or showing —
| (i) | the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and |
| (ii) | the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); | | (i) | the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and | (ii) | the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (i) | the details and the location of the points where there is equipotential bonding between the air‑termination system, down‑conductor system and earth‑termination system; and | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (ii) | the details and the location of the points where there is equipotential bonding of the lightning protection system to electrically conductive parts of the building (except mechanical and electrical services); | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (f) | such other details or plans as the Commissioner of Building Control may require. | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (2)  Without affecting regulations 6 and 7, all lightning protection system plans must —
| (a) | be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; |
| (b) | be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and |
| (c) | bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. | | (a) | be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; | (b) | be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and | (c) | bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (a) | be in accordance with the provisions of the Act and these Regulations and any other requirement of the Commissioner of Building Control; | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (b) | be signed, or be accompanied by an endorsement signed, by the qualified person who prepared the lightning protection system plans; and | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| (c) | bear a certificate from the qualified person who prepared the lightning protection system plans stating that the plans have been prepared in accordance with the Act and these Regulations, or be accompanied by such certificate. ”. | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |

| Amendment of regulation 22 |

| 6. In the principal Regulations, in regulation 22 —
| (a) | in paragraph (x), delete “and” at the end; | | | | | |
| (b) | in paragraph (y), replace the full‑stop at the end with a semi‑colon; and | | | | | |
| (c) | after paragraph (y), insert —
\| \| “ (z) \| a record of inspection and of the test results relating to the electrical continuity of the lightning protection system installed at any building on the premises at which building works are carried out; \|
\| (za) \| a record of inspection and of the measurement of earth electrodes and overall earth-termination system resistance. ”. \| \| “ (z) \| a record of inspection and of the test results relating to the electrical continuity of the lightning protection system installed at any building on the premises at which building works are carried out; \| (za) \| a record of inspection and of the measurement of earth electrodes and overall earth-termination system resistance. ”. \|
\| “ (z) \| a record of inspection and of the test results relating to the electrical continuity of the lightning protection system installed at any building on the premises at which building works are carried out; \| \| \| \|
\| (za) \| a record of inspection and of the measurement of earth electrodes and overall earth-termination system resistance. ”. \| \| \| \| | \| “ (z) \| a record of inspection and of the test results relating to the electrical continuity of the lightning protection system installed at any building on the premises at which building works are carried out; \|
\| (za) \| a record of inspection and of the measurement of earth electrodes and overall earth-termination system resistance. ”. \| | “ (z) | a record of inspection and of the test results relating to the electrical continuity of the lightning protection system installed at any building on the premises at which building works are carried out; | (za) | a record of inspection and of the measurement of earth electrodes and overall earth-termination system resistance. ”. |
| \| “ (z) \| a record of inspection and of the test results relating to the electrical continuity of the lightning protection system installed at any building on the premises at which building works are carried out; \|
\| (za) \| a record of inspection and of the measurement of earth electrodes and overall earth-termination system resistance. ”. \| | “ (z) | a record of inspection and of the test results relating to the electrical continuity of the lightning protection system installed at any building on the premises at which building works are carried out; | (za) | a record of inspection and of the measurement of earth electrodes and overall earth-termination system resistance. ”. | | |
| “ (z) | a record of inspection and of the test results relating to the electrical continuity of the lightning protection system installed at any building on the premises at which building works are carried out; | | | | | |
| (za) | a record of inspection and of the measurement of earth electrodes and overall earth-termination system resistance. ”. | | | | | | | (a) | in paragraph (x), delete “and” at the end; | (b) | in paragraph (y), replace the full‑stop at the end with a semi‑colon; and | (c) | after paragraph (y), insert —
| \| “ (z) \| a record of inspection and of the test results relating to the electrical continuity of the lightning protection system installed at any building on the premises at which building works are carried out; \|
\| (za) \| a record of inspection and of the measurement of earth electrodes and overall earth-termination system resistance. ”. \| | “ (z) | a record of inspection and of the test results relating to the electrical continuity of the lightning protection system installed at any building on the premises at which building works are carried out; | (za) | a record of inspection and of the measurement of earth electrodes and overall earth-termination system resistance. ”. |
| “ (z) | a record of inspection and of the test results relating to the electrical continuity of the lightning protection system installed at any building on the premises at which building works are carried out; | | | |
| (za) | a record of inspection and of the measurement of earth electrodes and overall earth-termination system resistance. ”. | | | | | | “ (z) | a record of inspection and of the test results relating to the electrical continuity of the lightning protection system installed at any building on the premises at which building works are carried out; |
| (za) | a record of inspection and of the measurement of earth electrodes and overall earth-termination system resistance. ”. | | “ (z) | a record of inspection and of the test results relating to the electrical continuity of the lightning protection system installed at any building on the premises at which building works are carried out; | (za) | a record of inspection and of the measurement of earth electrodes and overall earth-termination system resistance. ”. |
| (a) | in paragraph (x), delete “and” at the end; | | | | | | | | | | |
| (b) | in paragraph (y), replace the full‑stop at the end with a semi‑colon; and | | | | | | | | | | |
| (c) | after paragraph (y), insert —
| \| “ (z) \| a record of inspection and of the test results relating to the electrical continuity of the lightning protection system installed at any building on the premises at which building works are carried out; \|
\| (za) \| a record of inspection and of the measurement of earth electrodes and overall earth-termination system resistance. ”. \| | “ (z) | a record of inspection and of the test results relating to the electrical continuity of the lightning protection system installed at any building on the premises at which building works are carried out; | (za) | a record of inspection and of the measurement of earth electrodes and overall earth-termination system resistance. ”. |
| “ (z) | a record of inspection and of the test results relating to the electrical continuity of the lightning protection system installed at any building on the premises at which building works are carried out; | | | |
| (za) | a record of inspection and of the measurement of earth electrodes and overall earth-termination system resistance. ”. | | | | | | “ (z) | a record of inspection and of the test results relating to the electrical continuity of the lightning protection system installed at any building on the premises at which building works are carried out; |
| (za) | a record of inspection and of the measurement of earth electrodes and overall earth-termination system resistance. ”. | | “ (z) | a record of inspection and of the test results relating to the electrical continuity of the lightning protection system installed at any building on the premises at which building works are carried out; | (za) | a record of inspection and of the measurement of earth electrodes and overall earth-termination system resistance. ”. | | | | | |
| | “ (z) | a record of inspection and of the test results relating to the electrical continuity of the lightning protection system installed at any building on the premises at which building works are carried out; |
| (za) | a record of inspection and of the measurement of earth electrodes and overall earth-termination system resistance. ”. | | “ (z) | a record of inspection and of the test results relating to the electrical continuity of the lightning protection system installed at any building on the premises at which building works are carried out; | (za) | a record of inspection and of the measurement of earth electrodes and overall earth-termination system resistance. ”. | | | | | | | |
| “ (z) | a record of inspection and of the test results relating to the electrical continuity of the lightning protection system installed at any building on the premises at which building works are carried out; | | | | | | | | | | |
| (za) | a record of inspection and of the measurement of earth electrodes and overall earth-termination system resistance. ”. | | | | | | | | | | |

| Amendment of regulation 24 |

| 7. In the principal Regulations, in regulation 24(4), in the definition of “resident engineer”, in paragraph (e)(ii), replace “http://www.bca.gov.sg” with “https://www1.bca.gov.sg”. |

| Amendment of regulation 42 |

| 8. In the principal Regulations, in regulation 42 —
| (a) | after paragraph (1), insert —
\|
\| “ (1A)  An application to the Commissioner of Building Control for the expedited processing of an application under paragraph (1)(b) must be accompanied by a fee of —
\\| (a) \\| $500, if the building works are up to 3,000 m 2 in area; or \\|
\\| (b) \\| $1,000, if the building works exceed 3,000 m 2 in area. \\| \| (a) \| $500, if the building works are up to 3,000 m 2 in area; or \| (b) \| $1,000, if the building works exceed 3,000 m 2 in area. \|
\| (a) \| $500, if the building works are up to 3,000 m 2 in area; or \| \| \| \|
\| (b) \| $1,000, if the building works exceed 3,000 m 2 in area. \| \| \| \|

\| (1B) An application to the Commissioner of Building Control (in connection with an application under paragraph (1)(b)) to conduct an expedited inspection of the building or any part of the building in respect of which the building works have been carried out must be accompanied by a fee of $3,000. \|

\| (1C) To avoid doubt, the fees mentioned in paragraphs (1A) and (1B) are in addition to the fees payable under Parts 2, 3 and 3A of the Second Schedule. ”; and \| \| “ (1A)  An application to the Commissioner of Building Control for the expedited processing of an application under paragraph (1)(b) must be accompanied by a fee of —
\| (a) \| $500, if the building works are up to 3,000 m 2 in area; or \|
\| (b) \| $1,000, if the building works exceed 3,000 m 2 in area. \| \| (a) \| $500, if the building works are up to 3,000 m 2 in area; or \| (b) \| $1,000, if the building works exceed 3,000 m 2 in area. \| (1B) An application to the Commissioner of Building Control (in connection with an application under paragraph (1)(b)) to conduct an expedited inspection of the building or any part of the building in respect of which the building works have been carried out must be accompanied by a fee of $3,000. \| (1C) To avoid doubt, the fees mentioned in paragraphs (1A) and (1B) are in addition to the fees payable under Parts 2, 3 and 3A of the Second Schedule. ”; and \|
\| “ (1A)  An application to the Commissioner of Building Control for the expedited processing of an application under paragraph (1)(b) must be accompanied by a fee of —
\| (a) \| $500, if the building works are up to 3,000 m 2 in area; or \|
\| (b) \| $1,000, if the building works exceed 3,000 m 2 in area. \| \| (a) \| $500, if the building works are up to 3,000 m 2 in area; or \| (b) \| $1,000, if the building works exceed 3,000 m 2 in area. \| \| \| \|
\| (a) \| $500, if the building works are up to 3,000 m 2 in area; or \| \| \| \| \| \| \|
\| (b) \| $1,000, if the building works exceed 3,000 m 2 in area. \| \| \| \| \| \| \|
\| (1B) An application to the Commissioner of Building Control (in connection with an application under paragraph (1)(b)) to conduct an expedited inspection of the building or any part of the building in respect of which the building works have been carried out must be accompanied by a fee of $3,000. \| \| \| \| \| \| \| \|
\| (1C) To avoid doubt, the fees mentioned in paragraphs (1A) and (1B) are in addition to the fees payable under Parts 2, 3 and 3A of the Second Schedule. ”; and \| \| \| \| \| \| \| \| |
\| “ (1A)  An application to the Commissioner of Building Control for the expedited processing of an application under paragraph (1)(b) must be accompanied by a fee of —
\| (a) \| $500, if the building works are up to 3,000 m 2 in area; or \|
\| (b) \| $1,000, if the building works exceed 3,000 m 2 in area. \| \| (a) \| $500, if the building works are up to 3,000 m 2 in area; or \| (b) \| $1,000, if the building works exceed 3,000 m 2 in area. \|
\| (a) \| $500, if the building works are up to 3,000 m 2 in area; or \| \| \| \|
\| (b) \| $1,000, if the building works exceed 3,000 m 2 in area. \| \| \| \|

\| (1B) An application to the Commissioner of Building Control (in connection with an application under paragraph (1)(b)) to conduct an expedited inspection of the building or any part of the building in respect of which the building works have been carried out must be accompanied by a fee of $3,000. \|

\| (1C) To avoid doubt, the fees mentioned in paragraphs (1A) and (1B) are in addition to the fees payable under Parts 2, 3 and 3A of the Second Schedule. ”; and \| | “ (1A)  An application to the Commissioner of Building Control for the expedited processing of an application under paragraph (1)(b) must be accompanied by a fee of —
\| (a) \| $500, if the building works are up to 3,000 m 2 in area; or \|
\| (b) \| $1,000, if the building works exceed 3,000 m 2 in area. \| | (a) | $500, if the building works are up to 3,000 m 2 in area; or | (b) | $1,000, if the building works exceed 3,000 m 2 in area. | (1B) An application to the Commissioner of Building Control (in connection with an application under paragraph (1)(b)) to conduct an expedited inspection of the building or any part of the building in respect of which the building works have been carried out must be accompanied by a fee of $3,000. | (1C) To avoid doubt, the fees mentioned in paragraphs (1A) and (1B) are in addition to the fees payable under Parts 2, 3 and 3A of the Second Schedule. ”; and | | | | |
|
\| “ (1A)  An application to the Commissioner of Building Control for the expedited processing of an application under paragraph (1)(b) must be accompanied by a fee of —
\| (a) \| $500, if the building works are up to 3,000 m 2 in area; or \|
\| (b) \| $1,000, if the building works exceed 3,000 m 2 in area. \| \| (a) \| $500, if the building works are up to 3,000 m 2 in area; or \| (b) \| $1,000, if the building works exceed 3,000 m 2 in area. \|
\| (a) \| $500, if the building works are up to 3,000 m 2 in area; or \| \| \| \|
\| (b) \| $1,000, if the building works exceed 3,000 m 2 in area. \| \| \| \|

\| (1B) An application to the Commissioner of Building Control (in connection with an application under paragraph (1)(b)) to conduct an expedited inspection of the building or any part of the building in respect of which the building works have been carried out must be accompanied by a fee of $3,000. \|

\| (1C) To avoid doubt, the fees mentioned in paragraphs (1A) and (1B) are in addition to the fees payable under Parts 2, 3 and 3A of the Second Schedule. ”; and \| | “ (1A)  An application to the Commissioner of Building Control for the expedited processing of an application under paragraph (1)(b) must be accompanied by a fee of —
\| (a) \| $500, if the building works are up to 3,000 m 2 in area; or \|
\| (b) \| $1,000, if the building works exceed 3,000 m 2 in area. \| | (a) | $500, if the building works are up to 3,000 m 2 in area; or | (b) | $1,000, if the building works exceed 3,000 m 2 in area. | (1B) An application to the Commissioner of Building Control (in connection with an application under paragraph (1)(b)) to conduct an expedited inspection of the building or any part of the building in respect of which the building works have been carried out must be accompanied by a fee of $3,000. | (1C) To avoid doubt, the fees mentioned in paragraphs (1A) and (1B) are in addition to the fees payable under Parts 2, 3 and 3A of the Second Schedule. ”; and | | | | | | |
| “ (1A)  An application to the Commissioner of Building Control for the expedited processing of an application under paragraph (1)(b) must be accompanied by a fee of —
\| (a) \| $500, if the building works are up to 3,000 m 2 in area; or \|
\| (b) \| $1,000, if the building works exceed 3,000 m 2 in area. \| | (a) | $500, if the building works are up to 3,000 m 2 in area; or | (b) | $1,000, if the building works exceed 3,000 m 2 in area. | | | | | | | | | |
| (a) | $500, if the building works are up to 3,000 m 2 in area; or | | | | | | | | | | | | |
| (b) | $1,000, if the building works exceed 3,000 m 2 in area. | | | | | | | | | | | | |
| (1B) An application to the Commissioner of Building Control (in connection with an application under paragraph (1)(b)) to conduct an expedited inspection of the building or any part of the building in respect of which the building works have been carried out must be accompanied by a fee of $3,000. | | | | | | | | | | | | | |
| (1C) To avoid doubt, the fees mentioned in paragraphs (1A) and (1B) are in addition to the fees payable under Parts 2, 3 and 3A of the Second Schedule. ”; and | | | | | | | | | | | | | |
| (b) | after paragraph (2), insert —
\|
\| “ (3)  In this regulation —
\\| “area”, in relation to building works, means —
\\| (a) \\| the area of the storey or storeys in respect of the general building; or \\|
\\| (b) \\| the area of the plan view of the specified building, \\|

\\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \\| \\| (a) \\| the area of the storey or storeys in respect of the general building; or \\| (b) \\| the area of the plan view of the specified building, \\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \\|
\\| (a) \\| the area of the storey or storeys in respect of the general building; or \\| \\| \\| \\| \\|
\\| (b) \\| the area of the plan view of the specified building, \\| \\| \\| \\| \\|
\\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \\| \\| \\| \\| \\| \\|

\\| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; \\|

\\| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; \\|

\\| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; \\|

\\| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. \\| \| “area”, in relation to building works, means —
\\| (a) \\| the area of the storey or storeys in respect of the general building; or \\|
\\| (b) \\| the area of the plan view of the specified building, \\|

\\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \\| \| (a) \| the area of the storey or storeys in respect of the general building; or \| (b) \| the area of the plan view of the specified building, \| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; \| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; \| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; \| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. \|
\| “area”, in relation to building works, means —
\\| (a) \\| the area of the storey or storeys in respect of the general building; or \\|
\\| (b) \\| the area of the plan view of the specified building, \\|

\\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \\| \| (a) \| the area of the storey or storeys in respect of the general building; or \| (b) \| the area of the plan view of the specified building, \| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| \| \| \| \|
\| (a) \| the area of the storey or storeys in respect of the general building; or \| \| \| \| \| \| \| \| \| \|
\| (b) \| the area of the plan view of the specified building, \| \| \| \| \| \| \| \| \| \|
\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| \| \| \| \| \| \| \| \| \|
\| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; \| \| \| \| \| \| \| \| \| \| \|
\| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; \| \| \| \| \| \| \| \| \| \| \|
\| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; \| \| \| \| \| \| \| \| \| \| \|
\| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. \| \| \| \| \| \| \| \| \| \| \| \| “ (3)  In this regulation —
\| “area”, in relation to building works, means —
\\| (a) \\| the area of the storey or storeys in respect of the general building; or \\|
\\| (b) \\| the area of the plan view of the specified building, \\|

\\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \\| \| (a) \| the area of the storey or storeys in respect of the general building; or \| (b) \| the area of the plan view of the specified building, \| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \|
\| (a) \| the area of the storey or storeys in respect of the general building; or \| \| \| \| \|
\| (b) \| the area of the plan view of the specified building, \| \| \| \| \|
\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| \| \| \| \|

\| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; \|

\| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; \|

\| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; \|

\| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. \| \| “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| (a) \| the area of the storey or storeys in respect of the general building; or \| (b) \| the area of the plan view of the specified building, \| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; \| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; \| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; \| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. \|
\| “ (3)  In this regulation —
\| “area”, in relation to building works, means —
\\| (a) \\| the area of the storey or storeys in respect of the general building; or \\|
\\| (b) \\| the area of the plan view of the specified building, \\|

\\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \\| \| (a) \| the area of the storey or storeys in respect of the general building; or \| (b) \| the area of the plan view of the specified building, \| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \|
\| (a) \| the area of the storey or storeys in respect of the general building; or \| \| \| \| \|
\| (b) \| the area of the plan view of the specified building, \| \| \| \| \|
\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| \| \| \| \|

\| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; \|

\| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; \|

\| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; \|

\| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. \| \| “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| (a) \| the area of the storey or storeys in respect of the general building; or \| (b) \| the area of the plan view of the specified building, \| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; \| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; \| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; \| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. \| \|
\| “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| (a) \| the area of the storey or storeys in respect of the general building; or \| (b) \| the area of the plan view of the specified building, \| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| \| \| \| \| \|
\| (a) \| the area of the storey or storeys in respect of the general building; or \| \| \| \| \| \| \| \| \| \| \|
\| (b) \| the area of the plan view of the specified building, \| \| \| \| \| \| \| \| \| \| \|
\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| \| \| \| \| \| \| \| \| \| \|
\| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; \| \| \| \| \| \| \| \| \| \| \| \|
\| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; \| \| \| \| \| \| \| \| \| \| \| \|
\| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; \| \| \| \| \| \| \| \| \| \| \| \|
\| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. \| \| \| \| \| \| \| \| \| \| \| \| |
\| “ (3)  In this regulation —
\| “area”, in relation to building works, means —
\\| (a) \\| the area of the storey or storeys in respect of the general building; or \\|
\\| (b) \\| the area of the plan view of the specified building, \\|

\\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \\| \| (a) \| the area of the storey or storeys in respect of the general building; or \| (b) \| the area of the plan view of the specified building, \| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \|
\| (a) \| the area of the storey or storeys in respect of the general building; or \| \| \| \| \|
\| (b) \| the area of the plan view of the specified building, \| \| \| \| \|
\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| \| \| \| \|

\| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; \|

\| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; \|

\| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; \|

\| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. \| \| “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| (a) \| the area of the storey or storeys in respect of the general building; or \| (b) \| the area of the plan view of the specified building, \| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; \| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; \| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; \| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. \|
\| “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| (a) \| the area of the storey or storeys in respect of the general building; or \| (b) \| the area of the plan view of the specified building, \| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| \| \| \| \|
\| (a) \| the area of the storey or storeys in respect of the general building; or \| \| \| \| \| \| \| \| \| \|
\| (b) \| the area of the plan view of the specified building, \| \| \| \| \| \| \| \| \| \|
\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| \| \| \| \| \| \| \| \| \|
\| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; \| \| \| \| \| \| \| \| \| \| \|
\| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; \| \| \| \| \| \| \| \| \| \| \|
\| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; \| \| \| \| \| \| \| \| \| \| \|
\| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. \| \| \| \| \| \| \| \| \| \| \| | “ (3)  In this regulation —
\| “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| (a) \| the area of the storey or storeys in respect of the general building; or \| (b) \| the area of the plan view of the specified building, \| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \|
\| (a) \| the area of the storey or storeys in respect of the general building; or \| \| \| \| \|
\| (b) \| the area of the plan view of the specified building, \| \| \| \| \|
\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| \| \| \| \|

\| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; \|

\| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; \|

\| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; \|

\| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. \| | “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| | (a) | the area of the storey or storeys in respect of the general building; or | (b) | the area of the plan view of the specified building, | or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; | “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; | “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; | “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; | “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. |
|
\| “ (3)  In this regulation —
\| “area”, in relation to building works, means —
\\| (a) \\| the area of the storey or storeys in respect of the general building; or \\|
\\| (b) \\| the area of the plan view of the specified building, \\|

\\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \\| \| (a) \| the area of the storey or storeys in respect of the general building; or \| (b) \| the area of the plan view of the specified building, \| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \|
\| (a) \| the area of the storey or storeys in respect of the general building; or \| \| \| \| \|
\| (b) \| the area of the plan view of the specified building, \| \| \| \| \|
\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| \| \| \| \|

\| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; \|

\| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; \|

\| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; \|

\| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. \| \| “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| (a) \| the area of the storey or storeys in respect of the general building; or \| (b) \| the area of the plan view of the specified building, \| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; \| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; \| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; \| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. \|
\| “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| (a) \| the area of the storey or storeys in respect of the general building; or \| (b) \| the area of the plan view of the specified building, \| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| \| \| \| \|
\| (a) \| the area of the storey or storeys in respect of the general building; or \| \| \| \| \| \| \| \| \| \|
\| (b) \| the area of the plan view of the specified building, \| \| \| \| \| \| \| \| \| \|
\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| \| \| \| \| \| \| \| \| \|
\| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; \| \| \| \| \| \| \| \| \| \| \|
\| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; \| \| \| \| \| \| \| \| \| \| \|
\| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; \| \| \| \| \| \| \| \| \| \| \|
\| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. \| \| \| \| \| \| \| \| \| \| \| | “ (3)  In this regulation —
\| “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| (a) \| the area of the storey or storeys in respect of the general building; or \| (b) \| the area of the plan view of the specified building, \| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \|
\| (a) \| the area of the storey or storeys in respect of the general building; or \| \| \| \| \|
\| (b) \| the area of the plan view of the specified building, \| \| \| \| \|
\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| \| \| \| \|

\| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; \|

\| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; \|

\| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; \|

\| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. \| | “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| | (a) | the area of the storey or storeys in respect of the general building; or | (b) | the area of the plan view of the specified building, | or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; | “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; | “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; | “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; | “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. | | |
| “ (3)  In this regulation —
\| “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| (a) \| the area of the storey or storeys in respect of the general building; or \| (b) \| the area of the plan view of the specified building, \| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \|
\| (a) \| the area of the storey or storeys in respect of the general building; or \| \| \| \| \|
\| (b) \| the area of the plan view of the specified building, \| \| \| \| \|
\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| \| \| \| \|

\| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; \|

\| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; \|

\| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; \|

\| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. \| | “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| | (a) | the area of the storey or storeys in respect of the general building; or | (b) | the area of the plan view of the specified building, | or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; | “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; | “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; | “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; | “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. | | | |
| “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| | (a) | the area of the storey or storeys in respect of the general building; or | (b) | the area of the plan view of the specified building, | or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; | | | | | | | | |
| (a) | the area of the storey or storeys in respect of the general building; or | | | | | | | | | | | | |
| (b) | the area of the plan view of the specified building, | | | | | | | | | | | | |
| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; | | | | | | | | | | | | | |
| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; | | | | | | | | | | | | | |
| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; | | | | | | | | | | | | | |
| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; | | | | | | | | | | | | | |
| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. | | | | | | | | | | | | | | | (a) | after paragraph (1), insert —
|
\| “ (1A)  An application to the Commissioner of Building Control for the expedited processing of an application under paragraph (1)(b) must be accompanied by a fee of —
\| (a) \| $500, if the building works are up to 3,000 m 2 in area; or \|
\| (b) \| $1,000, if the building works exceed 3,000 m 2 in area. \| \| (a) \| $500, if the building works are up to 3,000 m 2 in area; or \| (b) \| $1,000, if the building works exceed 3,000 m 2 in area. \|
\| (a) \| $500, if the building works are up to 3,000 m 2 in area; or \| \| \| \|
\| (b) \| $1,000, if the building works exceed 3,000 m 2 in area. \| \| \| \|

\| (1B) An application to the Commissioner of Building Control (in connection with an application under paragraph (1)(b)) to conduct an expedited inspection of the building or any part of the building in respect of which the building works have been carried out must be accompanied by a fee of $3,000. \|

\| (1C) To avoid doubt, the fees mentioned in paragraphs (1A) and (1B) are in addition to the fees payable under Parts 2, 3 and 3A of the Second Schedule. ”; and \| | “ (1A)  An application to the Commissioner of Building Control for the expedited processing of an application under paragraph (1)(b) must be accompanied by a fee of —
\| (a) \| $500, if the building works are up to 3,000 m 2 in area; or \|
\| (b) \| $1,000, if the building works exceed 3,000 m 2 in area. \| | (a) | $500, if the building works are up to 3,000 m 2 in area; or | (b) | $1,000, if the building works exceed 3,000 m 2 in area. | (1B) An application to the Commissioner of Building Control (in connection with an application under paragraph (1)(b)) to conduct an expedited inspection of the building or any part of the building in respect of which the building works have been carried out must be accompanied by a fee of $3,000. | (1C) To avoid doubt, the fees mentioned in paragraphs (1A) and (1B) are in addition to the fees payable under Parts 2, 3 and 3A of the Second Schedule. ”; and |
| “ (1A)  An application to the Commissioner of Building Control for the expedited processing of an application under paragraph (1)(b) must be accompanied by a fee of —
\| (a) \| $500, if the building works are up to 3,000 m 2 in area; or \|
\| (b) \| $1,000, if the building works exceed 3,000 m 2 in area. \| | (a) | $500, if the building works are up to 3,000 m 2 in area; or | (b) | $1,000, if the building works exceed 3,000 m 2 in area. | | | |
| (a) | $500, if the building works are up to 3,000 m 2 in area; or | | | | | | |
| (b) | $1,000, if the building works exceed 3,000 m 2 in area. | | | | | | |
| (1B) An application to the Commissioner of Building Control (in connection with an application under paragraph (1)(b)) to conduct an expedited inspection of the building or any part of the building in respect of which the building works have been carried out must be accompanied by a fee of $3,000. | | | | | | | |
| (1C) To avoid doubt, the fees mentioned in paragraphs (1A) and (1B) are in addition to the fees payable under Parts 2, 3 and 3A of the Second Schedule. ”; and | | | | | | | | |
| “ (1A)  An application to the Commissioner of Building Control for the expedited processing of an application under paragraph (1)(b) must be accompanied by a fee of —
\| (a) \| $500, if the building works are up to 3,000 m 2 in area; or \|
\| (b) \| $1,000, if the building works exceed 3,000 m 2 in area. \| | (a) | $500, if the building works are up to 3,000 m 2 in area; or | (b) | $1,000, if the building works exceed 3,000 m 2 in area. |
| (a) | $500, if the building works are up to 3,000 m 2 in area; or | | | |
| (b) | $1,000, if the building works exceed 3,000 m 2 in area. | | | |

| (1B) An application to the Commissioner of Building Control (in connection with an application under paragraph (1)(b)) to conduct an expedited inspection of the building or any part of the building in respect of which the building works have been carried out must be accompanied by a fee of $3,000. |

| (1C) To avoid doubt, the fees mentioned in paragraphs (1A) and (1B) are in addition to the fees payable under Parts 2, 3 and 3A of the Second Schedule. ”; and | | “ (1A)  An application to the Commissioner of Building Control for the expedited processing of an application under paragraph (1)(b) must be accompanied by a fee of —
| (a) | $500, if the building works are up to 3,000 m 2 in area; or |
| (b) | $1,000, if the building works exceed 3,000 m 2 in area. | | (a) | $500, if the building works are up to 3,000 m 2 in area; or | (b) | $1,000, if the building works exceed 3,000 m 2 in area. | (1B) An application to the Commissioner of Building Control (in connection with an application under paragraph (1)(b)) to conduct an expedited inspection of the building or any part of the building in respect of which the building works have been carried out must be accompanied by a fee of $3,000. | (1C) To avoid doubt, the fees mentioned in paragraphs (1A) and (1B) are in addition to the fees payable under Parts 2, 3 and 3A of the Second Schedule. ”; and | (b) | after paragraph (2), insert —
|
\| “ (3)  In this regulation —
\| “area”, in relation to building works, means —
\\| (a) \\| the area of the storey or storeys in respect of the general building; or \\|
\\| (b) \\| the area of the plan view of the specified building, \\|

\\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \\| \| (a) \| the area of the storey or storeys in respect of the general building; or \| (b) \| the area of the plan view of the specified building, \| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \|
\| (a) \| the area of the storey or storeys in respect of the general building; or \| \| \| \| \|
\| (b) \| the area of the plan view of the specified building, \| \| \| \| \|
\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| \| \| \| \|

\| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; \|

\| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; \|

\| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; \|

\| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. \| \| “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| (a) \| the area of the storey or storeys in respect of the general building; or \| (b) \| the area of the plan view of the specified building, \| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; \| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; \| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; \| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. \|
\| “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| (a) \| the area of the storey or storeys in respect of the general building; or \| (b) \| the area of the plan view of the specified building, \| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| \| \| \| \|
\| (a) \| the area of the storey or storeys in respect of the general building; or \| \| \| \| \| \| \| \| \| \|
\| (b) \| the area of the plan view of the specified building, \| \| \| \| \| \| \| \| \| \|
\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| \| \| \| \| \| \| \| \| \|
\| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; \| \| \| \| \| \| \| \| \| \| \|
\| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; \| \| \| \| \| \| \| \| \| \| \|
\| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; \| \| \| \| \| \| \| \| \| \| \|
\| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. \| \| \| \| \| \| \| \| \| \| \| | “ (3)  In this regulation —
\| “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| (a) \| the area of the storey or storeys in respect of the general building; or \| (b) \| the area of the plan view of the specified building, \| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \|
\| (a) \| the area of the storey or storeys in respect of the general building; or \| \| \| \| \|
\| (b) \| the area of the plan view of the specified building, \| \| \| \| \|
\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| \| \| \| \|

\| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; \|

\| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; \|

\| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; \|

\| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. \| | “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| | (a) | the area of the storey or storeys in respect of the general building; or | (b) | the area of the plan view of the specified building, | or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; | “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; | “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; | “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; | “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. |
| “ (3)  In this regulation —
\| “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| (a) \| the area of the storey or storeys in respect of the general building; or \| (b) \| the area of the plan view of the specified building, \| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \|
\| (a) \| the area of the storey or storeys in respect of the general building; or \| \| \| \| \|
\| (b) \| the area of the plan view of the specified building, \| \| \| \| \|
\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| \| \| \| \|

\| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; \|

\| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; \|

\| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; \|

\| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. \| | “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| | (a) | the area of the storey or storeys in respect of the general building; or | (b) | the area of the plan view of the specified building, | or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; | “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; | “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; | “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; | “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. | |
| “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| | (a) | the area of the storey or storeys in respect of the general building; or | (b) | the area of the plan view of the specified building, | or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; | | | | | | |
| (a) | the area of the storey or storeys in respect of the general building; or | | | | | | | | | | |
| (b) | the area of the plan view of the specified building, | | | | | | | | | | |
| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; | | | | | | | | | | | |
| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; | | | | | | | | | | | |
| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; | | | | | | | | | | | |
| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; | | | | | | | | | | | |
| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. | | | | | | | | | | | | |
| “ (3)  In this regulation —
\| “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| (a) \| the area of the storey or storeys in respect of the general building; or \| (b) \| the area of the plan view of the specified building, \| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \|
\| (a) \| the area of the storey or storeys in respect of the general building; or \| \| \| \| \|
\| (b) \| the area of the plan view of the specified building, \| \| \| \| \|
\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| \| \| \| \|

\| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; \|

\| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; \|

\| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; \|

\| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. \| | “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| | (a) | the area of the storey or storeys in respect of the general building; or | (b) | the area of the plan view of the specified building, | or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; | “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; | “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; | “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; | “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. |
| “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| | (a) | the area of the storey or storeys in respect of the general building; or | (b) | the area of the plan view of the specified building, | or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; | | | | | |
| (a) | the area of the storey or storeys in respect of the general building; or | | | | | | | | | |
| (b) | the area of the plan view of the specified building, | | | | | | | | | |
| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; | | | | | | | | | | |
| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; | | | | | | | | | | |
| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; | | | | | | | | | | |
| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; | | | | | | | | | | |
| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. | | | | | | | | | | | | “ (3)  In this regulation —
| “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| | (a) | the area of the storey or storeys in respect of the general building; or | (b) | the area of the plan view of the specified building, | or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; |
| (a) | the area of the storey or storeys in respect of the general building; or | | | | |
| (b) | the area of the plan view of the specified building, | | | | |
| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; | | | | | |

| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; |

| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; |

| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; |

| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. | | “area”, in relation to building works, means —
| (a) | the area of the storey or storeys in respect of the general building; or |
| (b) | the area of the plan view of the specified building, |

| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; | | (a) | the area of the storey or storeys in respect of the general building; or | (b) | the area of the plan view of the specified building, | or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; | “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; | “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; | “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; | “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. |
| (a) | after paragraph (1), insert —
|
\| “ (1A)  An application to the Commissioner of Building Control for the expedited processing of an application under paragraph (1)(b) must be accompanied by a fee of —
\| (a) \| $500, if the building works are up to 3,000 m 2 in area; or \|
\| (b) \| $1,000, if the building works exceed 3,000 m 2 in area. \| \| (a) \| $500, if the building works are up to 3,000 m 2 in area; or \| (b) \| $1,000, if the building works exceed 3,000 m 2 in area. \|
\| (a) \| $500, if the building works are up to 3,000 m 2 in area; or \| \| \| \|
\| (b) \| $1,000, if the building works exceed 3,000 m 2 in area. \| \| \| \|

\| (1B) An application to the Commissioner of Building Control (in connection with an application under paragraph (1)(b)) to conduct an expedited inspection of the building or any part of the building in respect of which the building works have been carried out must be accompanied by a fee of $3,000. \|

\| (1C) To avoid doubt, the fees mentioned in paragraphs (1A) and (1B) are in addition to the fees payable under Parts 2, 3 and 3A of the Second Schedule. ”; and \| | “ (1A)  An application to the Commissioner of Building Control for the expedited processing of an application under paragraph (1)(b) must be accompanied by a fee of —
\| (a) \| $500, if the building works are up to 3,000 m 2 in area; or \|
\| (b) \| $1,000, if the building works exceed 3,000 m 2 in area. \| | (a) | $500, if the building works are up to 3,000 m 2 in area; or | (b) | $1,000, if the building works exceed 3,000 m 2 in area. | (1B) An application to the Commissioner of Building Control (in connection with an application under paragraph (1)(b)) to conduct an expedited inspection of the building or any part of the building in respect of which the building works have been carried out must be accompanied by a fee of $3,000. | (1C) To avoid doubt, the fees mentioned in paragraphs (1A) and (1B) are in addition to the fees payable under Parts 2, 3 and 3A of the Second Schedule. ”; and |
| “ (1A)  An application to the Commissioner of Building Control for the expedited processing of an application under paragraph (1)(b) must be accompanied by a fee of —
\| (a) \| $500, if the building works are up to 3,000 m 2 in area; or \|
\| (b) \| $1,000, if the building works exceed 3,000 m 2 in area. \| | (a) | $500, if the building works are up to 3,000 m 2 in area; or | (b) | $1,000, if the building works exceed 3,000 m 2 in area. | | | |
| (a) | $500, if the building works are up to 3,000 m 2 in area; or | | | | | | |
| (b) | $1,000, if the building works exceed 3,000 m 2 in area. | | | | | | |
| (1B) An application to the Commissioner of Building Control (in connection with an application under paragraph (1)(b)) to conduct an expedited inspection of the building or any part of the building in respect of which the building works have been carried out must be accompanied by a fee of $3,000. | | | | | | | |
| (1C) To avoid doubt, the fees mentioned in paragraphs (1A) and (1B) are in addition to the fees payable under Parts 2, 3 and 3A of the Second Schedule. ”; and | | | | | | | | |
| “ (1A)  An application to the Commissioner of Building Control for the expedited processing of an application under paragraph (1)(b) must be accompanied by a fee of —
\| (a) \| $500, if the building works are up to 3,000 m 2 in area; or \|
\| (b) \| $1,000, if the building works exceed 3,000 m 2 in area. \| | (a) | $500, if the building works are up to 3,000 m 2 in area; or | (b) | $1,000, if the building works exceed 3,000 m 2 in area. |
| (a) | $500, if the building works are up to 3,000 m 2 in area; or | | | |
| (b) | $1,000, if the building works exceed 3,000 m 2 in area. | | | |

| (1B) An application to the Commissioner of Building Control (in connection with an application under paragraph (1)(b)) to conduct an expedited inspection of the building or any part of the building in respect of which the building works have been carried out must be accompanied by a fee of $3,000. |

| (1C) To avoid doubt, the fees mentioned in paragraphs (1A) and (1B) are in addition to the fees payable under Parts 2, 3 and 3A of the Second Schedule. ”; and | | “ (1A)  An application to the Commissioner of Building Control for the expedited processing of an application under paragraph (1)(b) must be accompanied by a fee of —
| (a) | $500, if the building works are up to 3,000 m 2 in area; or |
| (b) | $1,000, if the building works exceed 3,000 m 2 in area. | | (a) | $500, if the building works are up to 3,000 m 2 in area; or | (b) | $1,000, if the building works exceed 3,000 m 2 in area. | (1B) An application to the Commissioner of Building Control (in connection with an application under paragraph (1)(b)) to conduct an expedited inspection of the building or any part of the building in respect of which the building works have been carried out must be accompanied by a fee of $3,000. | (1C) To avoid doubt, the fees mentioned in paragraphs (1A) and (1B) are in addition to the fees payable under Parts 2, 3 and 3A of the Second Schedule. ”; and | | | | | | | | | | | | | | | |
|
| “ (1A)  An application to the Commissioner of Building Control for the expedited processing of an application under paragraph (1)(b) must be accompanied by a fee of —
\| (a) \| $500, if the building works are up to 3,000 m 2 in area; or \|
\| (b) \| $1,000, if the building works exceed 3,000 m 2 in area. \| | (a) | $500, if the building works are up to 3,000 m 2 in area; or | (b) | $1,000, if the building works exceed 3,000 m 2 in area. |
| (a) | $500, if the building works are up to 3,000 m 2 in area; or | | | |
| (b) | $1,000, if the building works exceed 3,000 m 2 in area. | | | |

| (1B) An application to the Commissioner of Building Control (in connection with an application under paragraph (1)(b)) to conduct an expedited inspection of the building or any part of the building in respect of which the building works have been carried out must be accompanied by a fee of $3,000. |

| (1C) To avoid doubt, the fees mentioned in paragraphs (1A) and (1B) are in addition to the fees payable under Parts 2, 3 and 3A of the Second Schedule. ”; and | | “ (1A)  An application to the Commissioner of Building Control for the expedited processing of an application under paragraph (1)(b) must be accompanied by a fee of —
| (a) | $500, if the building works are up to 3,000 m 2 in area; or |
| (b) | $1,000, if the building works exceed 3,000 m 2 in area. | | (a) | $500, if the building works are up to 3,000 m 2 in area; or | (b) | $1,000, if the building works exceed 3,000 m 2 in area. | (1B) An application to the Commissioner of Building Control (in connection with an application under paragraph (1)(b)) to conduct an expedited inspection of the building or any part of the building in respect of which the building works have been carried out must be accompanied by a fee of $3,000. | (1C) To avoid doubt, the fees mentioned in paragraphs (1A) and (1B) are in addition to the fees payable under Parts 2, 3 and 3A of the Second Schedule. ”; and | | | | | | | | | | | | | | | | | |
| “ (1A)  An application to the Commissioner of Building Control for the expedited processing of an application under paragraph (1)(b) must be accompanied by a fee of —
| (a) | $500, if the building works are up to 3,000 m 2 in area; or |
| (b) | $1,000, if the building works exceed 3,000 m 2 in area. | | (a) | $500, if the building works are up to 3,000 m 2 in area; or | (b) | $1,000, if the building works exceed 3,000 m 2 in area. | | | | | | | | | | | | | | | | | | | | |
| (a) | $500, if the building works are up to 3,000 m 2 in area; or | | | | | | | | | | | | | | | | | | | | | | | |
| (b) | $1,000, if the building works exceed 3,000 m 2 in area. | | | | | | | | | | | | | | | | | | | | | | | |
| (1B) An application to the Commissioner of Building Control (in connection with an application under paragraph (1)(b)) to conduct an expedited inspection of the building or any part of the building in respect of which the building works have been carried out must be accompanied by a fee of $3,000. | | | | | | | | | | | | | | | | | | | | | | | | |
| (1C) To avoid doubt, the fees mentioned in paragraphs (1A) and (1B) are in addition to the fees payable under Parts 2, 3 and 3A of the Second Schedule. ”; and | | | | | | | | | | | | | | | | | | | | | | | | |
| (b) | after paragraph (2), insert —
|
\| “ (3)  In this regulation —
\| “area”, in relation to building works, means —
\\| (a) \\| the area of the storey or storeys in respect of the general building; or \\|
\\| (b) \\| the area of the plan view of the specified building, \\|

\\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \\| \| (a) \| the area of the storey or storeys in respect of the general building; or \| (b) \| the area of the plan view of the specified building, \| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \|
\| (a) \| the area of the storey or storeys in respect of the general building; or \| \| \| \| \|
\| (b) \| the area of the plan view of the specified building, \| \| \| \| \|
\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| \| \| \| \|

\| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; \|

\| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; \|

\| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; \|

\| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. \| \| “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| (a) \| the area of the storey or storeys in respect of the general building; or \| (b) \| the area of the plan view of the specified building, \| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; \| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; \| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; \| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. \|
\| “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| (a) \| the area of the storey or storeys in respect of the general building; or \| (b) \| the area of the plan view of the specified building, \| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| \| \| \| \|
\| (a) \| the area of the storey or storeys in respect of the general building; or \| \| \| \| \| \| \| \| \| \|
\| (b) \| the area of the plan view of the specified building, \| \| \| \| \| \| \| \| \| \|
\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| \| \| \| \| \| \| \| \| \|
\| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; \| \| \| \| \| \| \| \| \| \| \|
\| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; \| \| \| \| \| \| \| \| \| \| \|
\| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; \| \| \| \| \| \| \| \| \| \| \|
\| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. \| \| \| \| \| \| \| \| \| \| \| | “ (3)  In this regulation —
\| “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| (a) \| the area of the storey or storeys in respect of the general building; or \| (b) \| the area of the plan view of the specified building, \| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \|
\| (a) \| the area of the storey or storeys in respect of the general building; or \| \| \| \| \|
\| (b) \| the area of the plan view of the specified building, \| \| \| \| \|
\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| \| \| \| \|

\| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; \|

\| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; \|

\| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; \|

\| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. \| | “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| | (a) | the area of the storey or storeys in respect of the general building; or | (b) | the area of the plan view of the specified building, | or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; | “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; | “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; | “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; | “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. |
| “ (3)  In this regulation —
\| “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| (a) \| the area of the storey or storeys in respect of the general building; or \| (b) \| the area of the plan view of the specified building, \| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \|
\| (a) \| the area of the storey or storeys in respect of the general building; or \| \| \| \| \|
\| (b) \| the area of the plan view of the specified building, \| \| \| \| \|
\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| \| \| \| \|

\| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; \|

\| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; \|

\| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; \|

\| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. \| | “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| | (a) | the area of the storey or storeys in respect of the general building; or | (b) | the area of the plan view of the specified building, | or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; | “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; | “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; | “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; | “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. | |
| “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| | (a) | the area of the storey or storeys in respect of the general building; or | (b) | the area of the plan view of the specified building, | or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; | | | | | | |
| (a) | the area of the storey or storeys in respect of the general building; or | | | | | | | | | | |
| (b) | the area of the plan view of the specified building, | | | | | | | | | | |
| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; | | | | | | | | | | | |
| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; | | | | | | | | | | | |
| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; | | | | | | | | | | | |
| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; | | | | | | | | | | | |
| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. | | | | | | | | | | | | |
| “ (3)  In this regulation —
\| “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| (a) \| the area of the storey or storeys in respect of the general building; or \| (b) \| the area of the plan view of the specified building, \| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \|
\| (a) \| the area of the storey or storeys in respect of the general building; or \| \| \| \| \|
\| (b) \| the area of the plan view of the specified building, \| \| \| \| \|
\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| \| \| \| \|

\| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; \|

\| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; \|

\| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; \|

\| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. \| | “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| | (a) | the area of the storey or storeys in respect of the general building; or | (b) | the area of the plan view of the specified building, | or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; | “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; | “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; | “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; | “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. |
| “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| | (a) | the area of the storey or storeys in respect of the general building; or | (b) | the area of the plan view of the specified building, | or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; | | | | | |
| (a) | the area of the storey or storeys in respect of the general building; or | | | | | | | | | |
| (b) | the area of the plan view of the specified building, | | | | | | | | | |
| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; | | | | | | | | | | |
| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; | | | | | | | | | | |
| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; | | | | | | | | | | |
| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; | | | | | | | | | | |
| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. | | | | | | | | | | | | “ (3)  In this regulation —
| “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| | (a) | the area of the storey or storeys in respect of the general building; or | (b) | the area of the plan view of the specified building, | or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; |
| (a) | the area of the storey or storeys in respect of the general building; or | | | | |
| (b) | the area of the plan view of the specified building, | | | | |
| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; | | | | | |

| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; |

| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; |

| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; |

| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. | | “area”, in relation to building works, means —
| (a) | the area of the storey or storeys in respect of the general building; or |
| (b) | the area of the plan view of the specified building, |

| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; | | (a) | the area of the storey or storeys in respect of the general building; or | (b) | the area of the plan view of the specified building, | or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; | “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; | “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; | “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; | “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. | | | | | | | | | | | |
|
| “ (3)  In this regulation —
\| “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| (a) \| the area of the storey or storeys in respect of the general building; or \| (b) \| the area of the plan view of the specified building, \| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \|
\| (a) \| the area of the storey or storeys in respect of the general building; or \| \| \| \| \|
\| (b) \| the area of the plan view of the specified building, \| \| \| \| \|
\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| \| \| \| \| \|

\| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; \|

\| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; \|

\| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; \|

\| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. \| | “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| | (a) | the area of the storey or storeys in respect of the general building; or | (b) | the area of the plan view of the specified building, | or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; | “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; | “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; | “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; | “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. |
| “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| | (a) | the area of the storey or storeys in respect of the general building; or | (b) | the area of the plan view of the specified building, | or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; | | | | | |
| (a) | the area of the storey or storeys in respect of the general building; or | | | | | | | | | |
| (b) | the area of the plan view of the specified building, | | | | | | | | | |
| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; | | | | | | | | | | |
| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; | | | | | | | | | | |
| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; | | | | | | | | | | |
| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; | | | | | | | | | | |
| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. | | | | | | | | | | | | “ (3)  In this regulation —
| “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| | (a) | the area of the storey or storeys in respect of the general building; or | (b) | the area of the plan view of the specified building, | or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; |
| (a) | the area of the storey or storeys in respect of the general building; or | | | | |
| (b) | the area of the plan view of the specified building, | | | | |
| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; | | | | | |

| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; |

| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; |

| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; |

| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. | | “area”, in relation to building works, means —
| (a) | the area of the storey or storeys in respect of the general building; or |
| (b) | the area of the plan view of the specified building, |

| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; | | (a) | the area of the storey or storeys in respect of the general building; or | (b) | the area of the plan view of the specified building, | or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; | “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; | “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; | “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; | “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. | | | | | | | | | | | | | |
| “ (3)  In this regulation —
| “area”, in relation to building works, means —
\| (a) \| the area of the storey or storeys in respect of the general building; or \|
\| (b) \| the area of the plan view of the specified building, \|

\| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; \| | (a) | the area of the storey or storeys in respect of the general building; or | (b) | the area of the plan view of the specified building, | or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; |
| (a) | the area of the storey or storeys in respect of the general building; or | | | | |
| (b) | the area of the plan view of the specified building, | | | | |
| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; | | | | | |

| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; |

| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; |

| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; |

| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. | | “area”, in relation to building works, means —
| (a) | the area of the storey or storeys in respect of the general building; or |
| (b) | the area of the plan view of the specified building, |

| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; | | (a) | the area of the storey or storeys in respect of the general building; or | (b) | the area of the plan view of the specified building, | or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; | “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; | “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; | “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; | “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. | | | | | | | | | | | | | | |
| “area”, in relation to building works, means —
| (a) | the area of the storey or storeys in respect of the general building; or |
| (b) | the area of the plan view of the specified building, |

| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; | | (a) | the area of the storey or storeys in respect of the general building; or | (b) | the area of the plan view of the specified building, | or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; | | | | | | | | | | | | | | | | | | | |
| (a) | the area of the storey or storeys in respect of the general building; or | | | | | | | | | | | | | | | | | | | | | | | |
| (b) | the area of the plan view of the specified building, | | | | | | | | | | | | | | | | | | | | | | | |
| or both (including, where applicable, any increase thereof) used for calculating the appropriate fee in Part 2, 3 or 3A of the Second Schedule (as the case may be) for the application for approval of the plans for the building works under section 5 or 5A of the Act, or for the lodgment of the plans under section 5AA of the Act; | | | | | | | | | | | | | | | | | | | | | | | | |
| “expedited inspection” means an inspection to be conducted within an expedited time after the receipt of an application for such inspection by the Commissioner of Building Control; | | | | | | | | | | | | | | | | | | | | | | | | |
| “expedited processing”, in relation to an application, means the provision of a decision on the application within an expedited time after the receipt of the application by the Commissioner of Building Control; | | | | | | | | | | | | | | | | | | | | | | | | |
| “expedited time” means such expedited timelines as the Commissioner of Building Control may specify on the Internet website of the Building and Construction Authority at https://www1.bca.gov.sg; | | | | | | | | | | | | | | | | | | | | | | | | |
| “general building” and “specified building” have the meanings given by paragraph 1(1) of the Second Schedule. ”. | | | | | | | | | | | | | | | | | | | | | | | | |

| Replacement of regulation 49 and new regulation 49A |

| 9. In the principal Regulations, replace regulation 49 with —
| \| “ Search, inspection and provision of copy of approved drawings \|

\| 49. —(1)  The Commissioner of Building Control may, on an application accompanied by a fee of $45, allow the owner of a building to which any building works relate, or the owner’s authorised agent, to search and inspect the approved or deemed approved drawings of the building works retained by the Commissioner of Building Control (called in this regulation the approved drawings) on such terms and conditions as the Commissioner of Building Control may decide.
\| (2)  The Commissioner of Building Control may, on payment of a further fee specified in paragraph (3), provide a copy of any of the approved drawings to the owner or the owner’s authorised agent mentioned in paragraph (1). \|

\| (3)  The fee in paragraph (2) is $65 for —
\\| (a) \\| each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or \\|
\\| (b) \\| any part of a set mentioned in sub‑paragraph (a). \\| \| (a) \| each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or \| (b) \| any part of a set mentioned in sub‑paragraph (a). \|
\| (a) \| each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or \| \| \| \|
\| (b) \| any part of a set mentioned in sub‑paragraph (a). \| \| \| \| \| (2)  The Commissioner of Building Control may, on payment of a further fee specified in paragraph (3), provide a copy of any of the approved drawings to the owner or the owner’s authorised agent mentioned in paragraph (1). \| (3)  The fee in paragraph (2) is $65 for —
\| (a) \| each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or \|
\| (b) \| any part of a set mentioned in sub‑paragraph (a). \| \| (a) \| each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or \| (b) \| any part of a set mentioned in sub‑paragraph (a). \|
\| (2)  The Commissioner of Building Control may, on payment of a further fee specified in paragraph (3), provide a copy of any of the approved drawings to the owner or the owner’s authorised agent mentioned in paragraph (1). \| \| \| \| \| \| \|
\| (3)  The fee in paragraph (2) is $65 for —
\| (a) \| each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or \|
\| (b) \| any part of a set mentioned in sub‑paragraph (a). \| \| (a) \| each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or \| (b) \| any part of a set mentioned in sub‑paragraph (a). \| \| \|
\| (a) \| each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or \| \| \| \| \| \|
\| (b) \| any part of a set mentioned in sub‑paragraph (a). \| \| \| \| \| \|

\| Provision of building information \|

\| 49A. The Commissioner of Building Control may, on an application accompanied by a fee of $45, provide the owner of a building or the owner’s authorised agent with —
\| (a) \| the date of issuance of the certificate of statutory completion or, where there are no records of such date, the date of issuance of the temporary occupation permit, in respect of that building; or \|
\| (b) \| the name of the qualified person appointed to prepare the plans of the building works for that building. ”. \| \| (a) \| the date of issuance of the certificate of statutory completion or, where there are no records of such date, the date of issuance of the temporary occupation permit, in respect of that building; or \| (b) \| the name of the qualified person appointed to prepare the plans of the building works for that building. ”. \|
\| (a) \| the date of issuance of the certificate of statutory completion or, where there are no records of such date, the date of issuance of the temporary occupation permit, in respect of that building; or \| \| \| \|
\| (b) \| the name of the qualified person appointed to prepare the plans of the building works for that building. ”. \| \| \| \| | “ Search, inspection and provision of copy of approved drawings | 49. —(1)  The Commissioner of Building Control may, on an application accompanied by a fee of $45, allow the owner of a building to which any building works relate, or the owner’s authorised agent, to search and inspect the approved or deemed approved drawings of the building works retained by the Commissioner of Building Control (called in this regulation the approved drawings) on such terms and conditions as the Commissioner of Building Control may decide.
\| (2)  The Commissioner of Building Control may, on payment of a further fee specified in paragraph (3), provide a copy of any of the approved drawings to the owner or the owner’s authorised agent mentioned in paragraph (1). \|

\| (3)  The fee in paragraph (2) is $65 for —
\| (a) \| each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or \|
\| (b) \| any part of a set mentioned in sub‑paragraph (a). \| \| (a) \| each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or \| (b) \| any part of a set mentioned in sub‑paragraph (a). \|
\| (a) \| each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or \| \| \| \|
\| (b) \| any part of a set mentioned in sub‑paragraph (a). \| \| \| \| | (2)  The Commissioner of Building Control may, on payment of a further fee specified in paragraph (3), provide a copy of any of the approved drawings to the owner or the owner’s authorised agent mentioned in paragraph (1). | (3)  The fee in paragraph (2) is $65 for —
\| (a) \| each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or \|
\| (b) \| any part of a set mentioned in sub‑paragraph (a). \| | (a) | each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or | (b) | any part of a set mentioned in sub‑paragraph (a). | Provision of building information | 49A. The Commissioner of Building Control may, on an application accompanied by a fee of $45, provide the owner of a building or the owner’s authorised agent with —
\| (a) \| the date of issuance of the certificate of statutory completion or, where there are no records of such date, the date of issuance of the temporary occupation permit, in respect of that building; or \|
\| (b) \| the name of the qualified person appointed to prepare the plans of the building works for that building. ”. \| | (a) | the date of issuance of the certificate of statutory completion or, where there are no records of such date, the date of issuance of the temporary occupation permit, in respect of that building; or | (b) | the name of the qualified person appointed to prepare the plans of the building works for that building. ”. |
| “ Search, inspection and provision of copy of approved drawings | | | | | | | | | | | | | | |
| 49. —(1)  The Commissioner of Building Control may, on an application accompanied by a fee of $45, allow the owner of a building to which any building works relate, or the owner’s authorised agent, to search and inspect the approved or deemed approved drawings of the building works retained by the Commissioner of Building Control (called in this regulation the approved drawings) on such terms and conditions as the Commissioner of Building Control may decide.
\| (2)  The Commissioner of Building Control may, on payment of a further fee specified in paragraph (3), provide a copy of any of the approved drawings to the owner or the owner’s authorised agent mentioned in paragraph (1). \|

\| (3)  The fee in paragraph (2) is $65 for —
\| (a) \| each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or \|
\| (b) \| any part of a set mentioned in sub‑paragraph (a). \| \| (a) \| each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or \| (b) \| any part of a set mentioned in sub‑paragraph (a). \|
\| (a) \| each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or \| \| \| \|
\| (b) \| any part of a set mentioned in sub‑paragraph (a). \| \| \| \| | (2)  The Commissioner of Building Control may, on payment of a further fee specified in paragraph (3), provide a copy of any of the approved drawings to the owner or the owner’s authorised agent mentioned in paragraph (1). | (3)  The fee in paragraph (2) is $65 for —
\| (a) \| each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or \|
\| (b) \| any part of a set mentioned in sub‑paragraph (a). \| | (a) | each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or | (b) | any part of a set mentioned in sub‑paragraph (a). | | | | | | | | |
| (2)  The Commissioner of Building Control may, on payment of a further fee specified in paragraph (3), provide a copy of any of the approved drawings to the owner or the owner’s authorised agent mentioned in paragraph (1). | | | | | | | | | | | | | | |
| (3)  The fee in paragraph (2) is $65 for —
\| (a) \| each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or \|
\| (b) \| any part of a set mentioned in sub‑paragraph (a). \| | (a) | each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or | (b) | any part of a set mentioned in sub‑paragraph (a). | | | | | | | | | | |
| (a) | each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or | | | | | | | | | | | | | |
| (b) | any part of a set mentioned in sub‑paragraph (a). | | | | | | | | | | | | | |
| Provision of building information | | | | | | | | | | | | | | |
| 49A. The Commissioner of Building Control may, on an application accompanied by a fee of $45, provide the owner of a building or the owner’s authorised agent with —
\| (a) \| the date of issuance of the certificate of statutory completion or, where there are no records of such date, the date of issuance of the temporary occupation permit, in respect of that building; or \|
\| (b) \| the name of the qualified person appointed to prepare the plans of the building works for that building. ”. \| | (a) | the date of issuance of the certificate of statutory completion or, where there are no records of such date, the date of issuance of the temporary occupation permit, in respect of that building; or | (b) | the name of the qualified person appointed to prepare the plans of the building works for that building. ”. | | | | | | | | | | |
| (a) | the date of issuance of the certificate of statutory completion or, where there are no records of such date, the date of issuance of the temporary occupation permit, in respect of that building; or | | | | | | | | | | | | | |
| (b) | the name of the qualified person appointed to prepare the plans of the building works for that building. ”. | | | | | | | | | | | | | | | | “ Search, inspection and provision of copy of approved drawings |

| 49. —(1)  The Commissioner of Building Control may, on an application accompanied by a fee of $45, allow the owner of a building to which any building works relate, or the owner’s authorised agent, to search and inspect the approved or deemed approved drawings of the building works retained by the Commissioner of Building Control (called in this regulation the approved drawings) on such terms and conditions as the Commissioner of Building Control may decide.
\| (2)  The Commissioner of Building Control may, on payment of a further fee specified in paragraph (3), provide a copy of any of the approved drawings to the owner or the owner’s authorised agent mentioned in paragraph (1). \|

\| (3)  The fee in paragraph (2) is $65 for —
\| (a) \| each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or \|
\| (b) \| any part of a set mentioned in sub‑paragraph (a). \| \| (a) \| each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or \| (b) \| any part of a set mentioned in sub‑paragraph (a). \|
\| (a) \| each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or \| \| \| \|
\| (b) \| any part of a set mentioned in sub‑paragraph (a). \| \| \| \| | (2)  The Commissioner of Building Control may, on payment of a further fee specified in paragraph (3), provide a copy of any of the approved drawings to the owner or the owner’s authorised agent mentioned in paragraph (1). | (3)  The fee in paragraph (2) is $65 for —
\| (a) \| each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or \|
\| (b) \| any part of a set mentioned in sub‑paragraph (a). \| | (a) | each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or | (b) | any part of a set mentioned in sub‑paragraph (a). |
| (2)  The Commissioner of Building Control may, on payment of a further fee specified in paragraph (3), provide a copy of any of the approved drawings to the owner or the owner’s authorised agent mentioned in paragraph (1). | | | | | | |
| (3)  The fee in paragraph (2) is $65 for —
\| (a) \| each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or \|
\| (b) \| any part of a set mentioned in sub‑paragraph (a). \| | (a) | each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or | (b) | any part of a set mentioned in sub‑paragraph (a). | | |
| (a) | each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or | | | | | |
| (b) | any part of a set mentioned in sub‑paragraph (a). | | | | | |

| Provision of building information |

| 49A. The Commissioner of Building Control may, on an application accompanied by a fee of $45, provide the owner of a building or the owner’s authorised agent with —
\| (a) \| the date of issuance of the certificate of statutory completion or, where there are no records of such date, the date of issuance of the temporary occupation permit, in respect of that building; or \|
\| (b) \| the name of the qualified person appointed to prepare the plans of the building works for that building. ”. \| | (a) | the date of issuance of the certificate of statutory completion or, where there are no records of such date, the date of issuance of the temporary occupation permit, in respect of that building; or | (b) | the name of the qualified person appointed to prepare the plans of the building works for that building. ”. |
| (a) | the date of issuance of the certificate of statutory completion or, where there are no records of such date, the date of issuance of the temporary occupation permit, in respect of that building; or | | | |
| (b) | the name of the qualified person appointed to prepare the plans of the building works for that building. ”. | | | | | “ Search, inspection and provision of copy of approved drawings | 49. —(1)  The Commissioner of Building Control may, on an application accompanied by a fee of $45, allow the owner of a building to which any building works relate, or the owner’s authorised agent, to search and inspect the approved or deemed approved drawings of the building works retained by the Commissioner of Building Control (called in this regulation the approved drawings) on such terms and conditions as the Commissioner of Building Control may decide.
| (2)  The Commissioner of Building Control may, on payment of a further fee specified in paragraph (3), provide a copy of any of the approved drawings to the owner or the owner’s authorised agent mentioned in paragraph (1). |

| (3)  The fee in paragraph (2) is $65 for —
\| (a) \| each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or \|
\| (b) \| any part of a set mentioned in sub‑paragraph (a). \| | (a) | each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or | (b) | any part of a set mentioned in sub‑paragraph (a). |
| (a) | each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or | | | |
| (b) | any part of a set mentioned in sub‑paragraph (a). | | | | | (2)  The Commissioner of Building Control may, on payment of a further fee specified in paragraph (3), provide a copy of any of the approved drawings to the owner or the owner’s authorised agent mentioned in paragraph (1). | (3)  The fee in paragraph (2) is $65 for —
| (a) | each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or |
| (b) | any part of a set mentioned in sub‑paragraph (a). | | (a) | each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or | (b) | any part of a set mentioned in sub‑paragraph (a). | Provision of building information | 49A. The Commissioner of Building Control may, on an application accompanied by a fee of $45, provide the owner of a building or the owner’s authorised agent with —
| (a) | the date of issuance of the certificate of statutory completion or, where there are no records of such date, the date of issuance of the temporary occupation permit, in respect of that building; or |
| (b) | the name of the qualified person appointed to prepare the plans of the building works for that building. ”. | | (a) | the date of issuance of the certificate of statutory completion or, where there are no records of such date, the date of issuance of the temporary occupation permit, in respect of that building; or | (b) | the name of the qualified person appointed to prepare the plans of the building works for that building. ”. |
| | “ Search, inspection and provision of copy of approved drawings |

| 49. —(1)  The Commissioner of Building Control may, on an application accompanied by a fee of $45, allow the owner of a building to which any building works relate, or the owner’s authorised agent, to search and inspect the approved or deemed approved drawings of the building works retained by the Commissioner of Building Control (called in this regulation the approved drawings) on such terms and conditions as the Commissioner of Building Control may decide.
\| (2)  The Commissioner of Building Control may, on payment of a further fee specified in paragraph (3), provide a copy of any of the approved drawings to the owner or the owner’s authorised agent mentioned in paragraph (1). \|

\| (3)  The fee in paragraph (2) is $65 for —
\| (a) \| each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or \|
\| (b) \| any part of a set mentioned in sub‑paragraph (a). \| \| (a) \| each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or \| (b) \| any part of a set mentioned in sub‑paragraph (a). \|
\| (a) \| each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or \| \| \| \|
\| (b) \| any part of a set mentioned in sub‑paragraph (a). \| \| \| \| | (2)  The Commissioner of Building Control may, on payment of a further fee specified in paragraph (3), provide a copy of any of the approved drawings to the owner or the owner’s authorised agent mentioned in paragraph (1). | (3)  The fee in paragraph (2) is $65 for —
\| (a) \| each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or \|
\| (b) \| any part of a set mentioned in sub‑paragraph (a). \| | (a) | each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or | (b) | any part of a set mentioned in sub‑paragraph (a). |
| (2)  The Commissioner of Building Control may, on payment of a further fee specified in paragraph (3), provide a copy of any of the approved drawings to the owner or the owner’s authorised agent mentioned in paragraph (1). | | | | | | |
| (3)  The fee in paragraph (2) is $65 for —
\| (a) \| each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or \|
\| (b) \| any part of a set mentioned in sub‑paragraph (a). \| | (a) | each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or | (b) | any part of a set mentioned in sub‑paragraph (a). | | |
| (a) | each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or | | | | | |
| (b) | any part of a set mentioned in sub‑paragraph (a). | | | | | |

| Provision of building information |

| 49A. The Commissioner of Building Control may, on an application accompanied by a fee of $45, provide the owner of a building or the owner’s authorised agent with —
\| (a) \| the date of issuance of the certificate of statutory completion or, where there are no records of such date, the date of issuance of the temporary occupation permit, in respect of that building; or \|
\| (b) \| the name of the qualified person appointed to prepare the plans of the building works for that building. ”. \| | (a) | the date of issuance of the certificate of statutory completion or, where there are no records of such date, the date of issuance of the temporary occupation permit, in respect of that building; or | (b) | the name of the qualified person appointed to prepare the plans of the building works for that building. ”. |
| (a) | the date of issuance of the certificate of statutory completion or, where there are no records of such date, the date of issuance of the temporary occupation permit, in respect of that building; or | | | |
| (b) | the name of the qualified person appointed to prepare the plans of the building works for that building. ”. | | | | | “ Search, inspection and provision of copy of approved drawings | 49. —(1)  The Commissioner of Building Control may, on an application accompanied by a fee of $45, allow the owner of a building to which any building works relate, or the owner’s authorised agent, to search and inspect the approved or deemed approved drawings of the building works retained by the Commissioner of Building Control (called in this regulation the approved drawings) on such terms and conditions as the Commissioner of Building Control may decide.
| (2)  The Commissioner of Building Control may, on payment of a further fee specified in paragraph (3), provide a copy of any of the approved drawings to the owner or the owner’s authorised agent mentioned in paragraph (1). |

| (3)  The fee in paragraph (2) is $65 for —
\| (a) \| each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or \|
\| (b) \| any part of a set mentioned in sub‑paragraph (a). \| | (a) | each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or | (b) | any part of a set mentioned in sub‑paragraph (a). |
| (a) | each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or | | | |
| (b) | any part of a set mentioned in sub‑paragraph (a). | | | | | (2)  The Commissioner of Building Control may, on payment of a further fee specified in paragraph (3), provide a copy of any of the approved drawings to the owner or the owner’s authorised agent mentioned in paragraph (1). | (3)  The fee in paragraph (2) is $65 for —
| (a) | each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or |
| (b) | any part of a set mentioned in sub‑paragraph (a). | | (a) | each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or | (b) | any part of a set mentioned in sub‑paragraph (a). | Provision of building information | 49A. The Commissioner of Building Control may, on an application accompanied by a fee of $45, provide the owner of a building or the owner’s authorised agent with —
| (a) | the date of issuance of the certificate of statutory completion or, where there are no records of such date, the date of issuance of the temporary occupation permit, in respect of that building; or |
| (b) | the name of the qualified person appointed to prepare the plans of the building works for that building. ”. | | (a) | the date of issuance of the certificate of statutory completion or, where there are no records of such date, the date of issuance of the temporary occupation permit, in respect of that building; or | (b) | the name of the qualified person appointed to prepare the plans of the building works for that building. ”. | |
| “ Search, inspection and provision of copy of approved drawings | | | | | | | | | | | | | | | |
| 49. —(1)  The Commissioner of Building Control may, on an application accompanied by a fee of $45, allow the owner of a building to which any building works relate, or the owner’s authorised agent, to search and inspect the approved or deemed approved drawings of the building works retained by the Commissioner of Building Control (called in this regulation the approved drawings) on such terms and conditions as the Commissioner of Building Control may decide.
| (2)  The Commissioner of Building Control may, on payment of a further fee specified in paragraph (3), provide a copy of any of the approved drawings to the owner or the owner’s authorised agent mentioned in paragraph (1). |

| (3)  The fee in paragraph (2) is $65 for —
\| (a) \| each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or \|
\| (b) \| any part of a set mentioned in sub‑paragraph (a). \| | (a) | each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or | (b) | any part of a set mentioned in sub‑paragraph (a). |
| (a) | each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or | | | |
| (b) | any part of a set mentioned in sub‑paragraph (a). | | | | | (2)  The Commissioner of Building Control may, on payment of a further fee specified in paragraph (3), provide a copy of any of the approved drawings to the owner or the owner’s authorised agent mentioned in paragraph (1). | (3)  The fee in paragraph (2) is $65 for —
| (a) | each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or |
| (b) | any part of a set mentioned in sub‑paragraph (a). | | (a) | each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or | (b) | any part of a set mentioned in sub‑paragraph (a). | | | | | | | | | |
| (2)  The Commissioner of Building Control may, on payment of a further fee specified in paragraph (3), provide a copy of any of the approved drawings to the owner or the owner’s authorised agent mentioned in paragraph (1). | | | | | | | | | | | | | | | |
| (3)  The fee in paragraph (2) is $65 for —
| (a) | each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or |
| (b) | any part of a set mentioned in sub‑paragraph (a). | | (a) | each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or | (b) | any part of a set mentioned in sub‑paragraph (a). | | | | | | | | | | | |
| (a) | each set of the approved drawings that is uniquely identified by a reference number in a format required by the Commissioner of Building Control; or | | | | | | | | | | | | | | |
| (b) | any part of a set mentioned in sub‑paragraph (a). | | | | | | | | | | | | | | |
| Provision of building information | | | | | | | | | | | | | | | |
| 49A. The Commissioner of Building Control may, on an application accompanied by a fee of $45, provide the owner of a building or the owner’s authorised agent with —
| (a) | the date of issuance of the certificate of statutory completion or, where there are no records of such date, the date of issuance of the temporary occupation permit, in respect of that building; or |
| (b) | the name of the qualified person appointed to prepare the plans of the building works for that building. ”. | | (a) | the date of issuance of the certificate of statutory completion or, where there are no records of such date, the date of issuance of the temporary occupation permit, in respect of that building; or | (b) | the name of the qualified person appointed to prepare the plans of the building works for that building. ”. | | | | | | | | | | | |
| (a) | the date of issuance of the certificate of statutory completion or, where there are no records of such date, the date of issuance of the temporary occupation permit, in respect of that building; or | | | | | | | | | | | | | | |
| (b) | the name of the qualified person appointed to prepare the plans of the building works for that building. ”. | | | | | | | | | | | | | | |

| Amendment of First Schedule |

| 10. In the principal Regulations, in the First Schedule, after paragraph 12, insert —
| \| “ 12A.  One to one replacement or reinstatement of any lightning protection system, or any repairs to any existing lightning protection system, except where those building works are located within the site of other building works that are not specified in this Schedule. ”. \| | “ 12A.  One to one replacement or reinstatement of any lightning protection system, or any repairs to any existing lightning protection system, except where those building works are located within the site of other building works that are not specified in this Schedule. ”. |
| “ 12A.  One to one replacement or reinstatement of any lightning protection system, or any repairs to any existing lightning protection system, except where those building works are located within the site of other building works that are not specified in this Schedule. ”. | | | | “ 12A.  One to one replacement or reinstatement of any lightning protection system, or any repairs to any existing lightning protection system, except where those building works are located within the site of other building works that are not specified in this Schedule. ”. | | “ 12A.  One to one replacement or reinstatement of any lightning protection system, or any repairs to any existing lightning protection system, except where those building works are located within the site of other building works that are not specified in this Schedule. ”. |
| | “ 12A.  One to one replacement or reinstatement of any lightning protection system, or any repairs to any existing lightning protection system, except where those building works are located within the site of other building works that are not specified in this Schedule. ”. | | “ 12A.  One to one replacement or reinstatement of any lightning protection system, or any repairs to any existing lightning protection system, except where those building works are located within the site of other building works that are not specified in this Schedule. ”. | |
| “ 12A.  One to one replacement or reinstatement of any lightning protection system, or any repairs to any existing lightning protection system, except where those building works are located within the site of other building works that are not specified in this Schedule. ”. | | |

| Amendment of Second Schedule |

| 11. In the principal Regulations, in the Second Schedule, in the schedule reference, replace “and 20(3)” with “, 20(3) and 42(1C) and (3)”. |

| Amendment of Third Schedule |

| 12. In the principal Regulations, in the Third Schedule, replace the first paragraph with —
| \| “ 1.  The plans of building works must be prepared and signed by the following qualified persons:
\| (a) \| for any of the projects listed in Part I, a professional engineer, except that for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; \| \| \| \| \|
\| (b) \| for any of the projects listed in Part II, a professional engineer or an architect, except that —
\\| (i) \\| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \\|
\\| (ii) \\| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; \\| \| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; \|
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \| \| \| \| \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; \| \| \| \| \|
\| (c) \| for any other project not listed in Parts I and II, an architect, except that —
\\| (i) \\| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \\|
\\| (ii) \\| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. \\| \| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. \|
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \| \| \| \| \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. \| \| \| \| \| \| (a) \| for any of the projects listed in Part I, a professional engineer, except that for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; \| (b) \| for any of the projects listed in Part II, a professional engineer or an architect, except that —
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; \| \| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; \| (c) \| for any other project not listed in Parts I and II, an architect, except that —
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. \| \| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. \|
\| (a) \| for any of the projects listed in Part I, a professional engineer, except that for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (b) \| for any of the projects listed in Part II, a professional engineer or an architect, except that —
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; \| \| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; \| \| \| \| \| \| \| \| \| \|
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (c) \| for any other project not listed in Parts I and II, an architect, except that —
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. \| \| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. \| \| \| \| \| \| \| \| \| \|
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \| \| \| \| \| \| \| \| \| \| \| \| \| \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. \| \| \| \| \| \| \| \| \| \| \| \| \| \| | “ 1.  The plans of building works must be prepared and signed by the following qualified persons:
\| (a) \| for any of the projects listed in Part I, a professional engineer, except that for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; \| \| \| \| \|
\| (b) \| for any of the projects listed in Part II, a professional engineer or an architect, except that —
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; \| \| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; \|
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \| \| \| \| \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; \| \| \| \| \|
\| (c) \| for any other project not listed in Parts I and II, an architect, except that —
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. \| \| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. \|
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \| \| \| \| \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. \| \| \| \| \| | (a) | for any of the projects listed in Part I, a professional engineer, except that for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; | (b) | for any of the projects listed in Part II, a professional engineer or an architect, except that —
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; \| | (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; | (c) | for any other project not listed in Parts I and II, an architect, except that —
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. \| | (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. |
| “ 1.  The plans of building works must be prepared and signed by the following qualified persons:
\| (a) \| for any of the projects listed in Part I, a professional engineer, except that for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; \| \| \| \| \|
\| (b) \| for any of the projects listed in Part II, a professional engineer or an architect, except that —
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; \| \| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; \|
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \| \| \| \| \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; \| \| \| \| \|
\| (c) \| for any other project not listed in Parts I and II, an architect, except that —
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. \| \| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. \|
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \| \| \| \| \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. \| \| \| \| \| | (a) | for any of the projects listed in Part I, a professional engineer, except that for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; | (b) | for any of the projects listed in Part II, a professional engineer or an architect, except that —
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; \| | (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; | (c) | for any other project not listed in Parts I and II, an architect, except that —
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. \| | (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. | |
| (a) | for any of the projects listed in Part I, a professional engineer, except that for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; | | | | | | | | | | | | | | |
| (b) | for any of the projects listed in Part II, a professional engineer or an architect, except that —
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; \| | (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; | | | | | | | | | | |
| (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | | | | | | | | | | | | | | |
| (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; | | | | | | | | | | | | | | |
| (c) | for any other project not listed in Parts I and II, an architect, except that —
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. \| | (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. | | | | | | | | | | |
| (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | | | | | | | | | | | | | | |
| (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. | | | | | | | | | | | | | | | | | “ 1.  The plans of building works must be prepared and signed by the following qualified persons:
\| (a) \| for any of the projects listed in Part I, a professional engineer, except that for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; \| \| \| \| \|
\| (b) \| for any of the projects listed in Part II, a professional engineer or an architect, except that —
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; \| \| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; \|
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \| \| \| \| \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; \| \| \| \| \|
\| (c) \| for any other project not listed in Parts I and II, an architect, except that —
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. \| \| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. \|
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \| \| \| \| \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. \| \| \| \| \| | (a) | for any of the projects listed in Part I, a professional engineer, except that for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; | (b) | for any of the projects listed in Part II, a professional engineer or an architect, except that —
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; \| | (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; | (c) | for any other project not listed in Parts I and II, an architect, except that —
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. \| | (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. |
| (a) | for any of the projects listed in Part I, a professional engineer, except that for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; | | | | | | | | | | | | | |
| (b) | for any of the projects listed in Part II, a professional engineer or an architect, except that —
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; \| | (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; | | | | | | | | | |
| (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | | | | | | | | | | | | | |
| (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; | | | | | | | | | | | | | |
| (c) | for any other project not listed in Parts I and II, an architect, except that —
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. \| | (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. | | | | | | | | | |
| (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | | | | | | | | | | | | | |
| (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. | | | | | | | | | | | | | | | “ 1.  The plans of building works must be prepared and signed by the following qualified persons:
| (a) | for any of the projects listed in Part I, a professional engineer, except that for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; | | | | |
| (b) | for any of the projects listed in Part II, a professional engineer or an architect, except that —
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; \| | (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; |
| (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | | | | |
| (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; | | | | |
| (c) | for any other project not listed in Parts I and II, an architect, except that —
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. \| | (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. |
| (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | | | | |
| (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. | | | | | | (a) | for any of the projects listed in Part I, a professional engineer, except that for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; | (b) | for any of the projects listed in Part II, a professional engineer or an architect, except that —
| (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and |
| (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; | | (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; | (c) | for any other project not listed in Parts I and II, an architect, except that —
| (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and |
| (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. | | (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. |
| | “ 1.  The plans of building works must be prepared and signed by the following qualified persons:
\| (a) \| for any of the projects listed in Part I, a professional engineer, except that for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; \| \| \| \| \|
\| (b) \| for any of the projects listed in Part II, a professional engineer or an architect, except that —
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; \| \| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; \|
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \| \| \| \| \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; \| \| \| \| \|
\| (c) \| for any other project not listed in Parts I and II, an architect, except that —
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. \| \| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. \|
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \| \| \| \| \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. \| \| \| \| \| | (a) | for any of the projects listed in Part I, a professional engineer, except that for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; | (b) | for any of the projects listed in Part II, a professional engineer or an architect, except that —
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; \| | (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; | (c) | for any other project not listed in Parts I and II, an architect, except that —
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. \| | (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. |
| (a) | for any of the projects listed in Part I, a professional engineer, except that for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; | | | | | | | | | | | | | |
| (b) | for any of the projects listed in Part II, a professional engineer or an architect, except that —
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; \| | (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; | | | | | | | | | |
| (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | | | | | | | | | | | | | |
| (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; | | | | | | | | | | | | | |
| (c) | for any other project not listed in Parts I and II, an architect, except that —
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. \| | (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. | | | | | | | | | |
| (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | | | | | | | | | | | | | |
| (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. | | | | | | | | | | | | | | | “ 1.  The plans of building works must be prepared and signed by the following qualified persons:
| (a) | for any of the projects listed in Part I, a professional engineer, except that for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; | | | | |
| (b) | for any of the projects listed in Part II, a professional engineer or an architect, except that —
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; \| | (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; |
| (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | | | | |
| (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; | | | | |
| (c) | for any other project not listed in Parts I and II, an architect, except that —
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. \| | (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. |
| (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | | | | |
| (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. | | | | | | (a) | for any of the projects listed in Part I, a professional engineer, except that for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; | (b) | for any of the projects listed in Part II, a professional engineer or an architect, except that —
| (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and |
| (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; | | (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; | (c) | for any other project not listed in Parts I and II, an architect, except that —
| (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and |
| (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. | | (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. | |
| “ 1.  The plans of building works must be prepared and signed by the following qualified persons:
| (a) | for any of the projects listed in Part I, a professional engineer, except that for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; | | | | |
| (b) | for any of the projects listed in Part II, a professional engineer or an architect, except that —
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; \| | (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; |
| (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | | | | |
| (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; | | | | |
| (c) | for any other project not listed in Parts I and II, an architect, except that —
\| (i) \| for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and \|
\| (ii) \| for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. \| | (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. |
| (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | | | | |
| (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. | | | | | | (a) | for any of the projects listed in Part I, a professional engineer, except that for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; | (b) | for any of the projects listed in Part II, a professional engineer or an architect, except that —
| (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and |
| (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; | | (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; | (c) | for any other project not listed in Parts I and II, an architect, except that —
| (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and |
| (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. | | (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. | | |
| (a) | for any of the projects listed in Part I, a professional engineer, except that for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; | | | | | | | | | | | | | | | |
| (b) | for any of the projects listed in Part II, a professional engineer or an architect, except that —
| (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and |
| (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; | | (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; | | | | | | | | | | | |
| (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | | | | | | | | | | | | | | | |
| (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering; | | | | | | | | | | | | | | | |
| (c) | for any other project not listed in Parts I and II, an architect, except that —
| (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and |
| (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. | | (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. | | | | | | | | | | | |
| (i) | for structural components and works relating to such projects, the structural plans must be prepared by a professional engineer; and | | | | | | | | | | | | | | | |
| (ii) | for works relating to any lightning protection system or any component of that system, the lightning protection system plans must be prepared by a professional engineer registered under the Professional Engineers Act 1991 in the branch of electrical engineering. ”. | | | | | | | | | | | | | | | |

| Amendment of Fifth Schedule |

| 13. In the principal Regulations, in the Fifth Schedule —
| (a) | in paragraph 37, replace “from the direct effects of” with “against physical damage caused by”; and | | |
| (b) | replace paragraph 38 with —
\| \| “ 38.  A lightning protection system must be capable of protecting the building against physical damage caused by lightning strike and protecting the occupants of that building from being exposed to any lightning current that is discharged through that building. ”. \| \| “ 38.  A lightning protection system must be capable of protecting the building against physical damage caused by lightning strike and protecting the occupants of that building from being exposed to any lightning current that is discharged through that building. ”. \|
\| “ 38.  A lightning protection system must be capable of protecting the building against physical damage caused by lightning strike and protecting the occupants of that building from being exposed to any lightning current that is discharged through that building. ”. \| \| | \| “ 38.  A lightning protection system must be capable of protecting the building against physical damage caused by lightning strike and protecting the occupants of that building from being exposed to any lightning current that is discharged through that building. ”. \| | “ 38.  A lightning protection system must be capable of protecting the building against physical damage caused by lightning strike and protecting the occupants of that building from being exposed to any lightning current that is discharged through that building. ”. |
| \| “ 38.  A lightning protection system must be capable of protecting the building against physical damage caused by lightning strike and protecting the occupants of that building from being exposed to any lightning current that is discharged through that building. ”. \| | “ 38.  A lightning protection system must be capable of protecting the building against physical damage caused by lightning strike and protecting the occupants of that building from being exposed to any lightning current that is discharged through that building. ”. | | |
| “ 38.  A lightning protection system must be capable of protecting the building against physical damage caused by lightning strike and protecting the occupants of that building from being exposed to any lightning current that is discharged through that building. ”. | | | | | (a) | in paragraph 37, replace “from the direct effects of” with “against physical damage caused by”; and | (b) | replace paragraph 38 with —
| \| “ 38.  A lightning protection system must be capable of protecting the building against physical damage caused by lightning strike and protecting the occupants of that building from being exposed to any lightning current that is discharged through that building. ”. \| | “ 38.  A lightning protection system must be capable of protecting the building against physical damage caused by lightning strike and protecting the occupants of that building from being exposed to any lightning current that is discharged through that building. ”. |
| “ 38.  A lightning protection system must be capable of protecting the building against physical damage caused by lightning strike and protecting the occupants of that building from being exposed to any lightning current that is discharged through that building. ”. | | | | “ 38.  A lightning protection system must be capable of protecting the building against physical damage caused by lightning strike and protecting the occupants of that building from being exposed to any lightning current that is discharged through that building. ”. | | “ 38.  A lightning protection system must be capable of protecting the building against physical damage caused by lightning strike and protecting the occupants of that building from being exposed to any lightning current that is discharged through that building. ”. |
| (a) | in paragraph 37, replace “from the direct effects of” with “against physical damage caused by”; and | | | | | |
| (b) | replace paragraph 38 with —
| \| “ 38.  A lightning protection system must be capable of protecting the building against physical damage caused by lightning strike and protecting the occupants of that building from being exposed to any lightning current that is discharged through that building. ”. \| | “ 38.  A lightning protection system must be capable of protecting the building against physical damage caused by lightning strike and protecting the occupants of that building from being exposed to any lightning current that is discharged through that building. ”. |
| “ 38.  A lightning protection system must be capable of protecting the building against physical damage caused by lightning strike and protecting the occupants of that building from being exposed to any lightning current that is discharged through that building. ”. | | | | “ 38.  A lightning protection system must be capable of protecting the building against physical damage caused by lightning strike and protecting the occupants of that building from being exposed to any lightning current that is discharged through that building. ”. | | “ 38.  A lightning protection system must be capable of protecting the building against physical damage caused by lightning strike and protecting the occupants of that building from being exposed to any lightning current that is discharged through that building. ”. | | | |
| | “ 38.  A lightning protection system must be capable of protecting the building against physical damage caused by lightning strike and protecting the occupants of that building from being exposed to any lightning current that is discharged through that building. ”. | | “ 38.  A lightning protection system must be capable of protecting the building against physical damage caused by lightning strike and protecting the occupants of that building from being exposed to any lightning current that is discharged through that building. ”. | | | | | |
| “ 38.  A lightning protection system must be capable of protecting the building against physical damage caused by lightning strike and protecting the occupants of that building from being exposed to any lightning current that is discharged through that building. ”. | | | | | | |
[G.N. Nos. S 598/2004; S 549/2005; S 478/2007; S 495/2007; S 54/2008; S 250/2008; S 643/2008; S 4/2011; S 591/2012; S 665/2013; S 287/2016; S 443/2017; S 709/2017; S 808/2018; S 101/2020; S 695/2020; S 579/2022; S 905/2022; S 302/2023; S 797/2023; S 854/2023; S 415/2024; S 1003/2024; S 218/2025; S 616/2025; S 631/2025]
| | Made on 30 March 2026. |

| LOH NGAI SENG |
Permanent Secretary,
Ministry of National Development,
Singapore. | Made on 30 March 2026. | LOH NGAI SENG |
| Made on 30 March 2026. | | |
| LOH NGAI SENG | | |

| [AG/LEGIS/SL/29/2025/4] |

| (To be presented to Parliament under section 52 of the Building Control Act 1989). |

| |

Named provisions

Regulation 2 - Amendment of regulation 2 (Definition of lightning protection system) Regulation 7 Regulation 8 Regulation 9 Regulation 11

Source

Analysis generated by AI. Source diff and links are from the original.

Classification

Agency
BCA
Published
March 30th, 2026
Instrument
Rule
Legal weight
Binding
Stage
Final
Change scope
Substantive
Document ID
S 134 - Building Control (Amendment) Regulations 2026

Who this affects

Applies to
Construction firms Manufacturers Government agencies
Industry sector
2361 Construction
Activity scope
Building Construction Electrical System Installation Building Safety Compliance
Geographic scope
Singapore SG

Taxonomy

Primary area
Construction
Operational domain
Compliance
Topics
Electrical Safety Environmental Protection

Get Government & Legislation alerts

Weekly digest. AI-summarized, no noise.

Free. Unsubscribe anytime.

Get alerts for this source

We'll email you when Singapore Legislation Updates publishes new changes.

Optional. Personalizes your daily digest.

Free. Unsubscribe anytime.