Changeflow GovPing Government General Rio Grande LNG Granted Overnight Weekend Constr...
Routine Rule Added Final

Rio Grande LNG Granted Overnight Weekend Construction Work Hours

Favicon for changeflow.com FERC eLibrary: All Orders
Published
Detected
Email

Summary

FERC Office of Energy Projects issued a delegated order granting Rio Grande LNG, LLC and affiliated entities permission to modify workforce configuration and expand construction work hours to include overnight and weekend operations. The approval applies to the LNG facility project under dockets CP16-454 and CP24-70. This administrative authorization allows continuous construction activity at the project site.

What changed

FERC's Office of Energy Projects issued a delegated order on April 10, 2026 approving Rio Grande LNG's request to implement overnight and weekend construction work hours at its Texas LNG facility. The order modifies the existing workforce configuration authorization under Certificate Proceedings CP16-454 and CP24-70, allowing round-the-clock construction activity.

Energy project developers and LNG facility operators should note that FERC regularly grants similar work hours modifications for large infrastructure projects. This approval is specific to Rio Grande LNG but establishes a precedent for operational flexibility requests. Companies managing FERC-regulated energy projects should review their certificate conditions and consider whether extended work hours could accelerate project timelines.

What to do next

  1. Monitor for any additional FERC conditions attached to the work hours authorization
  2. Ensure compliance with environmental mitigation requirements during extended hours
  3. Review similar certificate modifications if your project requires schedule changes

Archived snapshot

Apr 10, 2026

GovPing captured this document from the original source. If the source has since changed or been removed, this is the text as it existed at that time.

Document Info for Accession Number: 20260410-3006

Details Document: 04/10/2026
Filed: 04/10/2026
Posted: 04/10/2026 09:45:07 AM
First Received Date: 04/10/2026 08:32:18 AM
Security Level: Public
Official: Yes
E-filing: No
Non-decisional: No
Category: Issuance
Library: Gas
Aperture: 0
File Type:
Description* :** Letter to Rio Grande LNG, LLC et al. granting the 04/03/2026 request to modify the workforce configuration and expand the construction work hours to include overnight and weekend work under CP16-454 et al.
File List

Docket Sub-Docket Type
CP16-454 000 On Document
CP24-70 000 On Document
Document Class Document Type
Order/Opinion Delegated Order
Correspondent Last Name First Name MI Role/Org
RECIPIENT Woods E RIO GRANDE LNG LLC
RECIPIENT Woods E RIO GRANDE LNG TRAIN 4, LLC
RECIPIENT Woods E RIO GRANDE LNG TRAIN 5, LLC
AUTHOR Swearingen D OFFICE OF ENERGY PROJECTS

Named provisions

Workforce Configuration Modification Extended Construction Hours Authorization

Get daily alerts for FERC eLibrary: All Orders

Daily digest delivered to your inbox.

Free. Unsubscribe anytime.

About this page

What is GovPing?

Every important government, regulator, and court update from around the world. One place. Real-time. Free. Our mission

What's from the agency?

Source document text, dates, docket IDs, and authority are extracted directly from FERC.

What's AI-generated?

The summary, classification, recommended actions, deadlines, and penalty information are AI-generated from the original text and may contain errors. Always verify against the source document.

Last updated

Classification

Agency
FERC
Published
April 10th, 2026
Instrument
Rule
Legal weight
Binding
Stage
Final
Change scope
Minor
Document ID
Accession No. 20260410-3006
Docket
CP16-454 CP24-70

Who this affects

Applies to
Energy companies Construction firms Importers and exporters
Industry sector
2111 Oil & Gas Extraction
Activity scope
LNG facility construction Infrastructure certificate compliance Energy project operations
Geographic scope
United States US

Taxonomy

Primary area
Energy
Operational domain
Regulatory Affairs
Topics
Environmental Protection Infrastructure Maritime

Get alerts for this source

We'll email you when FERC eLibrary: All Orders publishes new changes.

Free. Unsubscribe anytime.

You're subscribed!