Bucks Lake Dam Safety Monitoring Plan Accepted for Bucks Creek Project

Favicon for changeflow.com FERC eLibrary: All Orders
Published
Detected
Email

Summary

FERC's San Francisco Regional Office accepted Pacific Gas and Electric Company's updated Dam Safety Surveillance and Monitoring Plan for the Bucks Lake Dam, part of the Bucks Creek Project under license P-619. The plan and schedule, submitted on 02/23/2026, were accepted to address FERC's prior comments on the dam's safety monitoring requirements. PG&E must now implement the accepted plan according to the approved schedule.

What changed

FERC's San Francisco Regional Office issued a delegated order accepting Pacific Gas and Electric Company's Dam Safety Surveillance and Monitoring Plan for the Bucks Lake Dam, located within the Bucks Creek Project (P-619). The acceptance follows FERC's review of the plan submitted on 02/23/2026, which was revised to address agency comments on dam safety monitoring requirements.

Owners and operators of FERC-jurisdictional hydroelectric projects, particularly Pacific Gas and Electric Company, should ensure the accepted plan is implemented per the approved schedule and maintain documentation demonstrating compliance with the surveillance and monitoring requirements for dam safety.

What to do next

  1. Implement the accepted Dam Safety Surveillance and Monitoring Plan according to the approved schedule

Archived snapshot

Apr 11, 2026

GovPing captured this document from the original source. If the source has since changed or been removed, this is the text as it existed at that time.

Document Info for Accession Number: 20260410-3043

Details Document: 04/10/2026
Filed: 04/10/2026
Posted: 04/10/2026 02:57:06 PM
First Received Date: 04/10/2026 02:42:28 PM
Security Level: Public
Official: Yes
E-filing: No
Non-decisional: No
Category: Issuance
Library: Hydro
Aperture: 0
File Type:
Description* :** Letter to Pacific Gas and Electric Company accepting the 02/23/2026 plan and schedule to update the Dam Safety Surveillance and Monitoring Plan to address FERC's comment for the Bucks Lake Dam, part of the Bucks Creek Project under P-619.
File List

Docket Sub-Docket Type
P-619 000 On Document
Document Class Document Type
Order/Opinion Delegated Order
Correspondent Last Name First Name MI Role/Org
RECIPIENT Cruzen R PACIFIC GAS AND ELECTRIC COMPANY
AUTHOR BLACKETT F L SAN FRANCISCO REGIONAL OFFICE

Get daily alerts for FERC eLibrary: All Orders

Daily digest delivered to your inbox.

Free. Unsubscribe anytime.

About this page

What is GovPing?

Every important government, regulator, and court update from around the world. One place. Real-time. Free. Our mission

What's from the agency?

Source document text, dates, docket IDs, and authority are extracted directly from FERC.

What's AI-generated?

The summary, classification, recommended actions, deadlines, and penalty information are AI-generated from the original text and may contain errors. Always verify against the source document.

Last updated

Classification

Agency
FERC
Published
April 10th, 2026
Instrument
Rule
Legal weight
Binding
Stage
Final
Change scope
Minor
Document ID
P-619
Docket
P-619

Who this affects

Applies to
Energy companies
Industry sector
2210 Electric Utilities
Activity scope
Hydroelectric project compliance Dam safety monitoring
Geographic scope
United States US

Taxonomy

Primary area
Energy
Operational domain
Compliance
Topics
Environmental Protection Infrastructure