Summary
The National Green Tribunal heard an execution application regarding environmental compliance by the Government of West Bengal. The Tribunal noted delays in sewage collection pit construction, attributing them partly to election processes, and scheduled the next hearing for August 3, 2026.
What changed
The National Green Tribunal (NGT) Eastern Zone Bench in Kolkata held a hearing on an execution application concerning environmental compliance by the Government of West Bengal. The applicant's counsel had not filed a rejoinder to the respondents' affidavits. The District Magistrate and Collector of Birbhum filed an affidavit stating that while the Sewerage Treatment Plant at Tarapith is functional, the sewage collection pit near the vegetable market outfall adjoining the Dwarka river is still not in place. The respondent cited election processes for the delay and suggested a timeline in August 2026 for its completion.
The Tribunal has directed the registry to list the matter for the next hearing on August 3, 2026, and to ensure the applicant's rejoinder is placed on record. The respondent's counsel is also directed to provide a copy of the reply affidavit to the applicant's counsel. This indicates ongoing scrutiny of environmental infrastructure projects and potential delays impacting compliance timelines, requiring close monitoring by the relevant government departments.
What to do next
- Ensure applicant's rejoinder is filed and placed on record.
- Provide a copy of the reply affidavit to the applicant's counsel via email.
- Prepare for the next hearing on August 3, 2026, with updated information on the sewage collection pit.
Source document (simplified)
## Unlock Advanced Research with PRISM AI
Integrated with over 4 crore judgments and laws — designed for legal practitioners, researchers, students and institutions
- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc -... Upgrade to Premium [Cites 0, Cited by 0 ] ### National Green Tribunal
Mr.Joydeep Mukherjee vs Chief Secretary Govt Of West Bengal on 23 March, 2026
Item No.05 Court No.1
BEFORE THE NATIONAL GREEN TRIBUNAL
EASTERN ZONE BENCH, KOLKATA
(THROUGH PHYSICAL HEARING WITH HYBRID MODE)
Execution Application No.06/2025/EZ
In
Original Application No.30/2014/EZ
Mr. Joydeep Mukherjee Applicant
Versus
Govt. of West Bengal Respondents
Date of hearing: 23.03.2026
CORAM: HON'BLE MR. JUSTICE DINESH KUMAR SINGH, JUDICIAL MEMBER
HON'BLE MR. ISHWAR SINGH, EXPERT MEMBER
Applicant: Mr. Joydeep Mukherjee, the applicant along with Mr. Aditya Jha,
Advocate for the applicant (through VC).
Respondents:Mr. Amitesh Banerjee, Senior Advocate and Mr. Sibojyoti
Chakrabarti Advocates for respondents no.1 to 3 (through VC).
ORDER 1. Learned counsel for the applicant has failed to file any rejoinder to
the affidavits filed from the side of respondents so far.
- The learned counsel for the respondent 2, District Magistrate and
Collector, Birbhum has filed an affidavit dated 20.03.2026 in compliance
of the previous order passed by this Tribunal wherein attention is drawn
to the averments made in para 4 sub Clause (II) wherein it is made clear
that Sewerage Treatment Plant at Tarapith has been made fully
functional since January 2023 but as regards the sewage collection pit
near vegetable market outfall adjoining Dwarka river for treatment of
sewage effluents generating therefrom, it is submitted by him that, that
pit is yet to be put in place for which when we enquired the learned
counsel as to what should be the outer time limit, he stated that because 1 of the Election process going on, all officials are busy and some date may
be fixed in the month of August 2026.
- Therefore, we direct the registry to list this matter for next hearing
on 03.08.2026.
- Learned counsel for the applicant said that he has already filed the
rejoinder through email but we have not found the same placed on
record. Therefore, we direct the registry to place it on record.
- Learned counsel for respondent 2 is further directed to provide a
copy of the reply affidavit to the learned counsel for the applicant through
email.
- Put up this matter for next consideration on 03.08.2026.
.........................................
Dinesh Kumar Singh, JM
..............................
Ishwar Singh, EM
March 23rd, 2026
Execution Application No.06/2025/EZ
In
Original Application No.30/2014/EZ
MN 2
Related changes
Source
Classification
Who this affects
Taxonomy
Browse Categories
Get Environment alerts
Weekly digest. AI-summarized, no noise.
Free. Unsubscribe anytime.
Get alerts for this source
We'll email you when India National Green Tribunal publishes new changes.