Force Majeure Analysis for Middle East Conflict Under English Law
Summary
Pinsent Masons published a legal guide analysing force majeure clauses under English law in the context of Middle East conflict disruption to global supply chains. The guide examines whether force majeure provisions excuse parties from contractual obligations when hostilities disrupt oil production, transport, and pricing. It is intended to help businesses navigate supply chain disruption and understand their contractual rights.
What changed
This guidance analyses force majeure provisions in English-law-governed supply contracts affected by Middle East conflict disruption. The guide addresses how force majeure clauses operate to alter parties' contractual obligations when extraordinary events—such as armed conflict disrupting shipping routes, crude oil production, and broader supply chains—prevent timely performance. It covers the legal framework for invoking force majeure and the requirements parties must satisfy.
Businesses with English-law-governed supply contracts impacted by the Middle East conflict should review their force majeure clauses for qualifying trigger events, assess whether their performance difficulties fall within scope, comply with any notice requirements, and maintain documentation of disruptions. While this is non-binding legal analysis, it provides a framework for understanding contractual risk allocation during geopolitical disruptions.
What to do next
- Review supply contracts governed by English law for force majeure provisions and qualifying trigger events
- Assess whether current performance difficulties fall within the scope of applicable force majeure clauses
- Ensure compliance with contractual notice requirements and maintain documentation of supply chain disruptions
Source document (simplified)
Out-Law / Your Daily Need-To-Know
OUT-LAW GUIDE 5 min. read
Middle East conflict: force majeure and commercial implications in English law
The war between the US, Israel and Iran is disrupting shipping, crude oil and other major supply chains. Photo: David McNew/Getty Images
27 Mar 2026, 3:34 pm
Follow What the Middle East conflict means for businesses
As the Middle East conflict continues, severe disruption to global supply chains is putting businesses’ contractual rights and obligations under intense scrutiny.
The ongoing hostilities in the Middle East, set against a volatile global energy market and the resulting disruption to oil production, transport and pricing, have brought into sharp focus a number of complex legal issues relevant to English law governed by international supply contracts.
- Read more: what the Middle East conflict means for businesses We consider below some legal and practical consequences for businesses navigating supply chain disruption.
Force majeure
In times of conflict, a question that frequently arises is whether a force majeure clause in a supply contract excuses parties from performing their obligations or from doing so on time. Force majeure clauses are contractual clauses which alter parties' obligations or liabilities under a contract when an extraordinary event or circumstances beyond their control prevent one or all of them from fulfilling those obligations.
Such clauses may give a list of specific events or circumstances, including fire, flood and even war, sometimes alongside wider, general wording, such as "or any other causes beyond our control".
Whether a particular clause relieves a party of contractual liability and the full consequences of this will depend on: the precise wording used in the clause; the allocation of risk between the parties provided for by the contract as a whole; the circumstances in which the parties entered into the contract; as well as the situation that has arisen. It is for the party relying on a force majeure clause – excusing its non-performance or late performance – to satisfy a court or other tribunal that this is the effect of the clause.
Commonly, force majeure clauses will specify the particular impact that the event or circumstances in question must have for the clause to be operative. Reference may be made, for example, to the event or circumstances having "prevented", "hindered" or "delayed" performance. These terms require different levels of impact on performance before a party may be relieved from liability.
For example, a shortage of raw materials caused by a legitimate force majeure event may hinder the performance of a manufacturing contract. However, if those materials can be obtained at a higher cost, the fact that performing would simply be less profitable – or even cause a loss – due to higher costs is generally unlikely to be sufficient grounds to absolve the party in question of liability to perform.
A party seeking to rely on a force majeure clause must usually also show that: the force majeure event was the cause of the inability to perform or delayed performance; their non-performance was due to circumstances beyond their control; and there were no reasonable steps that they could have taken to avoid or mitigate the event or its consequences.
Consequently, for suppliers navigating force majeure events it is crucial to explore whether alternatives are reasonably available – including at higher cost, unless this involves breaching existing contracts.
Within the force majeure clause, there may also be formal contractual requirements to comply with, such as a requirement to give notice within a particular time and in a particular form.
Frustration
Since force majeure is a creature of contract rather than a rule imposed by the general law, if there is no force majeure clause, or it doesn’t cover the type of event which has arisen, an affected party may be able to rely on the doctrine of frustration.
However, it is very difficult to demonstrate that a contract has been frustrated. Frustration requires that an unforeseen subsequent event outside the control of the parties has made the contract impossible to perform or has transformed performance of the obligations under the contract into something so radically different from that which the parties intended that it would be unfair to hold the parties to their obligations.
One situation where the courts have held that a contract was frustrated was when war broke out and the government banned the works and seized and sold the necessary equipment.
As with the test for "hindering" performance under force majeure clauses, the fact that performance has been made more difficult or costly is not enough.
A delay in contractual performance because of the conflict in the Middle East will likely be temporary and, one would hope, relatively short term. Temporary impossibility or delay is not by itself a ground for frustration. However, it may frustrate a contract in two circumstances; where time is 'of the essence'; or where the length or the extent of the delay is so extreme as to amount to frustration.
Arguing frustration may also be commercially undesirable in some circumstances, since its effect is to bring all parties' obligations under the contract to an end immediately, regardless of the wishes of the parties.
Material adverse changes and events
A ‘material adverse change’ (MAC) or ‘material adverse event’ (MAE) clause allows one party to avoid, suspend or renegotiate its obligations if a specified materially adverse event or change occurs. These clauses are designed to protect a party – often a buyer or lender – against unexpected and significant deterioration in the target business, the borrower, or the wider environment between signing and completion or during the life of the contract.
A MAC or MAE clause may be triggered by various events specified in the contract, such as macroeconomic or geopolitical events, including war, sanctions or oil supply disruption. The change must usually be substantial, durationally significant and not merely temporary.
These clauses tend to be heavily negotiated and whether a MAC or MAE has occurred depends on the precise wording and the factual context.
Practical considerations
There are a number of practical steps that businesses can take when navigating such extensive supply chain disruption:
- consider in detail the precise wording of any force majeure, MAC or MAE clause, including reference to specific events;
- explore alternative means of performing, reducing delay, or minimising any loss to the other party;
- serve any notices as required under the contract, as soon as possible and in accordance with the notice provisions;
- do not attempt to rely on increased costs to excuse non‑performance or delay, as this will not usually be sufficient;
keep a documentary record, particularly of why performance was impossible, hindered or delayed as the case may be; the steps taken to find alternatives and mitigate loss; and the service of any notices;
consider enhancing any contractual termination rights, such as an expressed right to terminate for any extended period of disruption or delay to performance or the use of a step‑in provision to allow for temporary use of alternative suppliers during a period of disruption.
If there is no force majeure clause, businesses can also consider frustration as a viable option. However, as mentioned above, they must be mindful of the high bar for establishing that a contract has been frustrated and that consequentially it will release both parties of their contractual obligations
As businesses attempt to navigate these challenging geopolitical headwinds, it is advisable to consider other routes and remedies under the existing contract, or through agreeing binding variations to contracts with other parties.
- What the Middle East conflict means for businesses
- Commercial
- Energy & Natural Resources
- Infrastructure
- Middle East
- Qatar
- Retail & Consumer
- Saudi Arabia
- Supply chain management
- Supply of goods & services
- United Arab Emirates
- United Kingdom Contact an adviser
Julian Diaz-Rainey Partner
+44 (0) 7876 542 797 [email protected] View Profile
Gabrielle Armstrong Senior Associate
+44 (0) 7920 288 455 [email protected] View Profile
Latest News
59 minutes ago
Australia tightens merger rules from April as ACCC thresholds expand
13 hours ago
Industry figures play down Middle East conflict impact on financial services
22 hours ago
WA wind farm agreements ‘major boost’ for state’s renewable energy industry
27 Mar 2026
Caveats to national security block on telecoms components, says CJEU Advocate General
27 Mar 2026
Future Homes and Buildings Standards set in England
Editor's Pick
OUT-LAW ANALYSIS
Middle East conflict will not necessarily trigger force majeure in Saudi contracts
11 Mar 2026
OUT-LAW NEWS
Middle East conflict: sanctions risk posed by re-routing of supply chains
19 Mar 2026
Know what’s coming, make better decisions
Stay ahead of events with our weekly digest of news and expert analysis, tailored for you
You might also like
OUT-LAW NEWS
New NHS England digital schemes are not ‘quick win’
Plans to launch a new digital NHS trust aimed at bringing down waiting lists and widening access to health services in England face significant safety and security concerns, an expert has warned.
6 Oct 2025
Health OUT-LAW NEWS
New British suicide prevention standard welcomed by construction sector
Jonathan Cowlan tells HRNews about the new suicide prevention standard BS 30480 and how HR professionals can make use of it.
2 Oct 2025
Employment OUT-LAW NEWS
Warning over knock-on effects ahead of first packaging scheme invoices
Fees for ‘obligated packaging producers’ under a UK ‘extended producer responsibility’ scheme must be managed carefully to avoid penalising specific sectors, an expert has warned.
9 Oct 2025
Trending topics across the site:
- Employment
- Construction Advisory & Disputes
- Artificial intelligence
- Implementing the Employment Rights Act
- Litigation and arbitration Left OUT-LAW NEWS
19 January 2023
UK government plans to revamp holiday pay calculation for part-year workers
Show me more OUT-LAW ANALYSIS
23 February 2021
Pensions disputes: managing member expectations paramount
Show me more OUT-LAW ANALYSIS
1 February 2021
UK subsidy control post-Brexit: access to effective judicial remedies
Show me more OUT-LAW NEWS
8 February 2016
'Steps of court' settlement was not negligent, court rules
Show me more OUT-LAW NEWS
27 August 2020
'Vast majority' of companies not seeking to avoid tax
Show me more OUT-LAW NEWS
19 March 2021
'World first' industrial decarbonisation strategy developed in the UK
Show me more OUT-LAW ANALYSIS
21 September 2020
3D printing: UK product safety issues
Show me more OUT-LAW NEWS
18 January 2021
5G potential for business highlighted in UK funding programme
Show me more Right
Named provisions
Related changes
Source
Classification
Who this affects
Taxonomy
Browse Categories
Get Courts & Legal alerts
Weekly digest. AI-summarized, no noise.
Free. Unsubscribe anytime.
Get alerts for this source
We'll email you when Inner Temple Library Current Awareness publishes new changes.