Forest Service Pre-Award Contracting Deficiencies ($48.2M unsupported costs)
Summary
The USDA Office of Inspector General issued Report No. 08801-0005-51 finding that the Forest Service did not fully comply with Federal laws and regulations when executing pre-award contracting processes from November 2021 to March 2025. The inspection identified $48,255,403 in unsupported costs across 13 sampled contracts, with recommendations to evaluate the affected contracts and implement stronger oversight controls.
What changed
The USDA OIG conducted an inspection/evaluation of Forest Service pre-award contracting activities under the Infrastructure Investment and Jobs Act (IIJA) and found that the agency failed to comply with Federal laws and regulations in executing the pre-award contracting process for 13 sampled contracts. The total questioned costs amount to $48,255,403 in unsupported costs for the period November 15, 2021 through March 31, 2025. The OIG issued two open recommendations: (1) to evaluate pre-award documents for the 13 contracts with missing documentation and document conclusions, and (2) to establish and implement oversight controls to ensure contract file documentation is complete and fully compliant.
Agencies receiving Federal funds for construction or contracting activities should review their pre-award documentation practices to ensure compliance with Federal procurement requirements. While the OIG report itself does not impose immediate penalties, questioned costs of $48.2 million are subject to disallowance by the awarding agency. Contracting officers and program managers should verify that all required pre-award documentation is complete, properly executed, and retained in contract files before award. Enhanced oversight controls for documentation completeness should be implemented as a priority.
What to do next
- Review pre-award contracting documentation practices for completeness and compliance with Federal procurement regulations
- Verify all required documentation exists in contract files before award execution
- Implement oversight controls to ensure ongoing compliance with pre-award contracting requirements
Penalties
Questioned costs of $48,255,403 may be subject to disallowance by the awarding agency if documentation is not provided to support the expenditures.
Source document (simplified)
IIJA – Forest Service Pre-Award Contracting Activities
Report Information
Date Issued
March 26, 2026
Report Number: 08801-0005-51 Report Type Inspection / Evaluation Component Forest Service Description We determined that the Forest Service did not fully comply with Federal laws and regulations when executing the pre-award contracting process for the sampled contracts from November 15, 2021, to March 31, 2025, resulting in more than $48.2 million in unsupported costs. Joint Report No Agency Wide Yes (agency-wide) Questioned Costs $48,255,403 Funds for Better Use $0 View report on Oversight.gov
Recommendations
1 - Open
Evaluate the pre-award documents for the 13 contracts that had missing documents, which have an overall award value of more than $48.2 million in unsupported costs, and document conclusions reached, as applicable.
2 - Open
Establish and implement oversight controls to ensure that contract file documentation is complete and fully complies with Federal laws and regulations.
Named provisions
Related changes
Source
Classification
Who this affects
Taxonomy
Browse Categories
Get Agriculture & Food Safety alerts
Weekly digest. AI-summarized, no noise.
Free. Unsubscribe anytime.
Get alerts for this source
We'll email you when USDA OIG Reports publishes new changes.