London Luton Airport Expansion Correction Order 2026

Favicon for www.legislation.gov.uk UK New Legislation
Published March 21st, 2026
Detected March 21st, 2026
Email

Summary

The UK Secretary of State for Transport has issued the London Luton Airport Expansion Development Consent (Correction) Order 2026 to correct minor errors in the original 2025 Order. These corrections address specific wording and typographical errors within various articles and schedules of the development consent order.

What changed

This Correction Order amends the London Luton Airport Expansion Development Consent Order 2025 (the '2025 Order') to rectify several correctable errors identified within the original document. The corrections, made under Schedule 4 of the Planning Act 2008, include changes to definitions (e.g., 'bridleway', 'groundwater'), substitutions of incorrect terms (e.g., 'stoppclosed' to 'stopped', 'report' to 'reported'), and minor omissions or insertions of text to ensure accuracy and consistency. These are administrative corrections to the existing development consent.

Compliance officers should note that this is a correction of an existing order and does not introduce new obligations or change the fundamental scope of the development consent. The corrections are effective from March 21, 2026. No specific actions are required from regulated entities beyond ensuring their understanding of the corrected text, particularly concerning definitions and specific provisions within the 2025 Order as amended by this Correction Order.

What to do next

  1. Review the schedule of corrections to the London Luton Airport Expansion Development Consent Order 2025.

Source document (simplified)

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

Statutory Instruments

2026 No. 328

Infrastructure Planning

The London Luton Airport Expansion Development Consent (Correction) Order 2026

Made

20th March 2026

Coming into force

21st March 2026

The London Luton Airport Expansion Development Consent Order 2025(1) (“ the 2025 Order ”) which granted development consent within the meaning of the Planning Act 2008(2) (“ the Act ”), contained correctable errors within the meaning of paragraph 1(3) of Schedule 4 to the Act.

In accordance with paragraph 1(5)(a) of Schedule 4 to the Act, before the end of the relevant period as defined in paragraph 1(6)(a) of Schedule 4 to the Act, the Secretary of State received a written request from the applicant(3) for the correction of errors or omissions in the 2025 Order.

In accordance with paragraph 1(7) of Schedule 4 to the Act, the Secretary of State informed the relevant local planning authority for the area in which the land to which the 2025 Order relates is situated, that the requests had been received.

The Secretary of State, in exercise of the powers conferred by section 119 of, and paragraph 1(4) and (8) of Schedule 4 to, the Act, makes the following Order.

Citation and commencement

  1. This Order may be cited as the London Luton Airport Expansion Development Consent (Correction) Order 2026 and comes into force on 21st March 2026.

Corrections to the London Luton Airport Expansion Development Consent Order 2025

  1. The London Luton Airport Expansion Development Consent Order is corrected as set out in the table in the Schedule to this Order, where—

(a) column 1 sets out where the correction is to be made;

(b) column 2 sets out how the correction is to be made; and

(c) column 3 sets out the text to be substituted, inserted or omitted.

Signed by authority of the Secretary of State for Transport

Natasha Kopala

Head of the Transport and Works Act Orders Unit

Department for Transport

20th March 2026

Article 2

SCHEDULE CORRECTABLE ERRORS

| (1)

Where the correction is to be made | (2)

How the correction is to be made | (3)

Text to be substituted, inserted or omitted |
| --- | --- | --- |
| Article 2 (interpretation), definition of “bridleway” | After “interpretation” insert | “)” |
| Article 2(10) | For “report” substitute | “reported” |
| Article 13(2) (temporary stopping up and restriction of use of streets) | For “stoppclosed” substitute | “stopped” |
| Article 21(1)(b) (authority to survey and investigate the land) | For “ground water” substitute | “groundwater” |
| Article 33(10) (temporary use of land for carrying out the authorised development) | After “section 125(c)” delete | “of the 2008 Act” |
| Article 50(3) (certification of documents, etc.) | For “GCG Framework” substitute | “green controlled growth framework” |
| Article 50(3)(a) | For “consistent” substitute | “consistently” |
| Article 50(3)(b) | For “paragragh” substitute | “paragraph” |
| Schedule 1 (authorised development), Work No. 5(e) | For “Off-site” substitute | “Offsite” |
| Schedule 2 (requirements), Part 1, paragraph 1, definition of “substantially in accordance with” | After “should not give rise to” omit | “any new or” |
| Schedule 2, Part 1, paragraph 2(2) | After “sewage undertakers and in relation to” omit | “t” |
| Schedule 2, Part 1, paragraph 6(3)(c) | After “of this Schedule” omit | “, subject to paragraph 2(1)(g)” |
| Schedule 2, Part 2, paragraph 14 | For sub-paragraphs (1) and (2) substitute | “ (1) Prior to commencement of construction, the undertaker is required to carry out an assessment of the latest version of the Flood and Coastal Erosion Risk Data published by the Environment Agency to determine whether it changes the level of risk assessed within the flood risk assessment (Environmental Statement Appendix 20.1, as listed in Schedule 9 to, and certified under article 50 of, this Order).

(2) The undertaker must consult with the Environment Agency and the lead local flood authority on whether an updated flood risk assessment is required as a result of the assessment carried out under sub-paragraph (1).

(3) If any material change in risk is identified as a result of the process undertaken under sub-paragraphs (1) and (2), then the undertaker must prepare an updated flood risk assessment, which must be submitted to and approved in writing by Luton Borough Council, following consultation with the Environment Agency and the lead local flood authority.

(4) The undertaker is required to carry out the authorised development in accordance with any updated flood risk assessment produced by the undertaker as a result of the process under sub-paragraphs (1) to (3). ” |
| Schedule 2, Part 2, paragraph 18(5) | For “ground water” substitute | “groundwater” |
| Schedule 2, Part 3, paragraph 19, definition of “terms of reference” | In sub-paragraph (b), for “paragraph 21(9)” substitute | “paragraph 21(10)” |
| Schedule 2, Part 3, paragraph 21(1) | After “(“ ESG ”)” omit | “as soon as reasonably practicable following service of the notice under article 44(1) (interaction with LLAOL planning permission) and in any event” |
| Schedule 2, Part 3, paragraph 21(5) | For “(or a substitute agreed)” substitute | “(or an agreed substitute)” |
| Schedule 2, Part 3, paragraph 21(9) | For “sub-paragraph (7)” substitute | “sub-paragraph (8)” |
| Schedule 2, Part 3, paragraph 22(2) | For sub-paragraph (2) substitute | “ (2) The undertaker must prepare and submit to the ESG—

(a) the first Monitoring Report—

(i) on the date notice is served under article 44(1) (interaction with LLAOL planning permission); and

(ii) no later than 31 July in the calendar year in which that notice is served; and

(b) all subsequent Monitoring Reports on or before 31 July annually thereafter. ” |
| Schedule 2, Part 3, paragraph 22(6) | For “sub-paragraph (1)” substitute | “sub-paragraph (2)” |
| Schedule 2, Part 3, paragraph 24(2) | For “paragraph 21(6)(a), (b), (c) or (d)” substitute | “paragraph 21(7)(a), (b), (c) or (d)” |
| Schedule 2, Part 3, paragraph 24(9) | For “sub-paragraph (2)” substitute | “sub-paragraph (3)” |
| Schedule 2, Part 3, paragraph 24(10) | For “artricle” substitute | “article” |
| Schedule 2, Part 3, paragraph 24(10)(b) | For “sub-paragraph (5)(b)” substitute | “sub-paragraph (5)” |
| Schedule 2, Part 3, paragraph 24(11) | For “paragraph 24” substitute | “paragraph 25” |
| Schedule 2, Part 3, paragraph 24(11) | For “paragraph 21(6)(a), (b), (c) or (d)” substitute | “paragraph 21(7)(a), (b), (c) or (d)” |
| Schedule 2, Part 3, paragraph 24(11) | For “paragraph 26(10)” substitute | “paragraph 25(10)” |
| Schedule 2, Part 3, paragraph 25(7)(a) | For “lodge an appeal under paragraph 40 (appeals to the Secretary of State)” substitute | “resolve the disagreement under article 52 (arbitration)” |
| Schedule 2, Part 3, paragraph 25(15) | For “paragraph 21” substitute | “paragraph 22” |
| Schedule 2, Part 3, paragraph 25(15) | After “has been exceeded,” insert | “and except where sub-paragraph (3) applies,” |
| Schedule 2, Part 3, paragraph 25(16) | For “by the Secretary of State under paragraph 40 (appeals to the Secretary of State)” substitute | “by resolution under article 52 (arbitration)” |
| Schedule 2, Part 4, paragraph 27 | After “may operate” insert | “the airport” |
| Schedule 2, Part 4, paragraph 27 | After “under this Order” omit | “the airport” |
| Schedule 2, Part 4, paragraph 28(1) | After “must not operate” insert | “the airport” |
| Schedule 2, Part 4, paragraph 28(1) | After “under this Order” omit | “the airport” |
| Schedule 2, Part 4, paragraph 28(1) | After “23:30-06:00” insert | “local time” |
| Schedule 2, Part 4, paragraph 28(1) | After “12 month period,” insert | “in accordance with the air noise management plan,” |
| Schedule 2, Part 4, paragraph 29(1) | For “air traffic movement”, in both place where it occurs, substitute | “air traffic movements” |
| Schedule 2, Part 4, paragraph 29(1) | After “06:00-07:00” insert | “local time” |
| Schedule 2, Part 4, paragraph 29(2) | For “airport” substitute | “aircraft” |
| Schedule 2, Part 4, paragraph 29(2) | After “non-scheduled service” insert | “, excluding exempt flights” |
| Schedule 2, Part 4, paragraph 33(1), Table 1, heading of column (3) | For “2039–2033” substitute | “2029–2033” |
| Schedule 2, Part 4, paragraph 33(2) | For “GCG framework” substitute | “green controlled growth framework” |
| Schedule 2, Part 4, paragraph 33(3) | After “2008 Act” insert | “ —

(a) ” |
| Schedule 2, Part 4, paragraph 33(3) | For “reasonably reasonably” substitute | “reasonable” |
| Schedule 2, Part 4, paragraph 33(3) | After “serious damage to property” insert | “; or

(b) if the exceedance results from circumstances which the ESG has certified are beyond the undertaker’s control. ” |
| Schedule 2, Part 4, paragraph 33 | After sub-paragraph (3) insert | “ (4) The undertaker may make a written request to the Secretary of State to change the contour limits, following consultation on such changes with Luton Borough Council and where appointed, the ESG. The Secretary of State may approve changes to contour limits where the undertaker has demonstrated that such changes would not result in materially new or materially different noise effects than those assessed in the environmental statement. ” |
| Schedule 2, Part 3, paragraph 34(4) | After “satisfactory level” insert | “or it is satisfied that the undertaker has taken all reasonable and practicable steps to insulate all eligible properties” |
| Schedule 2, Part 4, paragraph 34(5) | For “environment” substitute | “environmental” |
| Schedule 2, Part 4, paragraph 36(1) | For “Off-site Highway Works No.” substitute | “Offsite Highway Works, Work Nos.” |
| Schedule 2, Part 4, paragraph 36(2) | For “submitted to” substitute | “submitted for approval” |
| Schedule 2, Part 4, paragraph 42 | Omit sub-paragraphs (1), (2), (3) and (4) and substitute | “Not used” |
| Schedule 5 (land in which only new rights etc. may be acquired), Land Plans – Sheet 6 of 10, in the third row containing “6-04” in column (1) and “The rights and restrictive covenants to construct, operate, access, protect, and maintain a habitat mitigation area.” in column (2) | Omit the entire row | |
| Schedule 7 (land of which temporary possession may be taken), first row, column (2) | For “A505 Gispsy Lane” substitute | “A505 Gipsy Lane” |
| Schedule 8 (protective provisions), Part 1, paragraph 10(2) | For “subparagraph” substitute | “sub-paragraph” |
| Schedule 8, Part 5, paragraph 37(1) | For “subparagraph” substitute | “sub-paragraph” |

EXPLANATORY NOTE

(This note is not part of the Order)

This Order corrects errors and omissions in the London Luton Airport Expansion Development Consent (Correction) Order 2025 (S.I. 2025/463), a development consent order under the Planning Act 2008, following a request made under paragraph 1(5(a) of Schedule 4 to that Act.

(1) S.I. 2025/463.

(2) 2008 c. 29. Paragraph 1 of Schedule 4 was amended by paragraph 70 of Schedule 13, and Part 20 of Schedule 25, to the Localism Act 2011 (c. 20). There are other amendments to paragraph 1 of Schedule 4 that are not relevant to this Order.

(3) The term “applicant” is defined in paragraph 4 of Schedule 4 to the Planning Act 2008.

Named provisions

Citation and commencement Corrections to the London Luton Airport Expansion Development Consent Order 2025 SCHEDULE CORRECTABLE ERRORS

Source

Analysis generated by AI. Source diff and links are from the original.

Classification

Agency
UK Parliament
Published
March 21st, 2026
Instrument
Rule
Legal weight
Binding
Stage
Final
Change scope
Minor
Document ID
2026 No. 328
Supersedes
The London Luton Airport Expansion Development Consent Order 2025

Who this affects

Applies to
Government agencies
Industry sector
2361 Construction
Activity scope
Infrastructure Planning Airport Development
Geographic scope
United Kingdom GB

Taxonomy

Primary area
Transportation
Operational domain
Legal
Topics
Infrastructure Planning Development Consent

Get Government & Legislation alerts

Weekly digest. AI-summarized, no noise.

Free. Unsubscribe anytime.

Get alerts for this source

We'll email you when UK New Legislation publishes new changes.

Free. Unsubscribe anytime.