Summary

FERC issued a Notice of Availability for a Draft Environmental Impact Statement concerning Sabine Pass Liquefaction, LLC's proposed Stage 5 Expansion Project. The Draft EIS evaluates potential environmental impacts from expanding LNG liquefaction capacity at the existing Sabine Pass facility in Cameron Parish, Louisiana. Comments on the Draft EIS will be accepted through the process established in the document.

What changed

FERC announced the availability of a Draft Environmental Impact Statement for the Sabine Pass Stage 5 Expansion Project (CP24-75, CP25-505, CP25-506). The Draft EIS analyzes environmental effects of proposed LNG liquefaction capacity additions at the Sabine Pass terminal, which currently operates under FERC authorization for LNG import and export activities. The document was prepared in accordance with the National Environmental Policy Act requirements.

Affected parties should review the Draft EIS and submit comments through the FERC eLibrary system. While no specific comment deadline is stated in this notice, stakeholders should locate the comment procedures within the Draft EIS document itself. This notice initiates the public review period for environmental review, which must be completed before FERC can issue any authorization decisions on the project applications.

What to do next

  1. Review the Draft EIS for the Sabine Pass Stage 5 Expansion Project via FERC eLibrary
  2. Submit comments on the Draft EIS according to procedures specified in the document
  3. Monitor related dockets CP24-75, CP25-505, and CP25-506 for updates and the final EIS

Source document (simplified)

Document Info for Accession Number: 20260403-3025

Details Document: 04/03/2026
Filed: 04/03/2026
Posted: 04/03/2026 10:47:05 AM
First Received Date: 04/03/2026 10:17:08 AM
Security Level: Public
Official: Yes
E-filing: No
Non-decisional: No
Category: Issuance
Library: Gas
Aperture: 0
File Type:
Description* :** Notice of Availability of The Draft Environmental Impact Statement for the Proposed Sabine Pass Stage 5 Expansion Project re Sabine Pass Liquefaction, LLC et al. under CP24-75 et al.
File List

| Docket | Sub-Docket | Type |
| --- | --- | --- |
| CP24-75 | 001 | On Document |
| CP25-505 | 000 | On Document |
| CP25-506 | 000 | On Document |

| Document Class | Document Type |
| --- | --- |
| Notice | Formal Notice |

| Correspondent | Last Name | First Name | MI | Role/Org |
| --- | --- | --- | --- | --- |
| AUTHOR | REESE | D | A | SECRETARY OF THE COMMISSION, FERC |

Source

Analysis generated by AI. Source diff and links are from the original.

Classification

Agency
FERC
Published
April 3rd, 2026
Instrument
Notice
Legal weight
Non-binding
Stage
Draft
Change scope
Minor
Docket
CP24-75 CP25-505 CP25-506

Who this affects

Applies to
Energy companies Government agencies
Industry sector
4831 Maritime & Shipping
Activity scope
LNG Export Terminal Approval Pipeline Infrastructure Review
Geographic scope
United States US

Taxonomy

Primary area
Energy
Operational domain
Compliance
Topics
Environmental Protection International Trade

Get Government General alerts

Weekly digest. AI-summarized, no noise.

Free. Unsubscribe anytime.

Get alerts for this source

We'll email you when FERC eLibrary: All Notices - ChangeBridge publishes new changes.

Optional. Personalizes your daily digest.

Free. Unsubscribe anytime.