Cheyenne Light Standard Large Generator Interconnection Agreement With Black Hills Electric Generation Accepted
Summary
FERC's Office of Energy Market Regulation issued a delegated order accepting Cheyenne Light, Fuel and Power Company's executed Standard Large Generator Interconnection Agreement with Black Hills Electric Generation, LLC. The acceptance was filed under docket ER26-1475 and dated April 10, 2026. This routine administrative action approves the interconnection arrangement between the two parties, allowing them to proceed with their planned generator interconnection.
What changed
FERC issued a letter order accepting Cheyenne Light, Fuel and Power Company's executed Standard Large Generator Interconnection Agreement with Black Hills Electric Generation, LLC under the ER26-1475 docket. The order, issued by the Office of Energy Market Regulation, approves the interconnection agreement as filed on February 23, 2026.\n\nAffected parties—Cheyenne Light and Black Hills Electric Generation—may proceed with implementing their interconnection arrangement now that FERC has accepted the agreement. Other market participants seeking similar interconnection agreements should note this as a routine acceptance of a standard large generator interconnection filing.
What to do next
- Monitor for any subsequent FERC filings or modifications to the interconnection agreement
Archived snapshot
Apr 11, 2026GovPing captured this document from the original source. If the source has since changed or been removed, this is the text as it existed at that time.
Document Info for Accession Number: 20260410-3054
Details Document: 04/10/2026
Filed: 04/10/2026
Posted: 04/10/2026 03:31:08 PM
First Received Date: 04/10/2026 02:54:35 PM
Security Level: Public
Official: Yes
E-filing: No
Non-decisional: No
Category: Issuance
Library: Electric
Aperture: 0
File Type:
Description* :** Letter order accepting Cheyenne Light, Fuel and Power Company's 02/23/2026 filing of an executed Standard Large Generator Interconnection Agreement with Black Hills Electric Generation, LLC under ER26-1475.
File List
| Docket | Sub-Docket | Type |
|---|---|---|
| ER26-1475 | 000 | On Document |
| Document Class | Document Type |
|---|---|
| Order/Opinion | Delegated Order |
| Correspondent | Last Name | First Name | MI | Role/Org |
|---|---|---|---|---|
| RECIPIENT | * | * | CHEYENNE LIGHT, FUEL AND POWER COMPANY | |
| AUTHOR | Poré | A | S | OFFICE OF ENERGY MARKET REGULATION |
Related changes
Get daily alerts for FERC eLibrary: All Orders
Daily digest delivered to your inbox.
Free. Unsubscribe anytime.
Source
About this page
Every important government, regulator, and court update from around the world. One place. Real-time. Free. Our mission
Source document text, dates, docket IDs, and authority are extracted directly from FERC.
The summary, classification, recommended actions, deadlines, and penalty information are AI-generated from the original text and may contain errors. Always verify against the source document.
Classification
Who this affects
Taxonomy
Browse Categories
Get alerts for this source
We'll email you when FERC eLibrary: All Orders publishes new changes.
Subscribed!
Optional. Filters your digest to exactly the updates that matter to you.