FERC's New York Regional Office reviewed Brookfield Renewable's 12th Part 12D Periodic Inspection Report for the Cascade hydroelectric project (P-2327). The December 29, 2025 report was submitted for compliance with dam safety inspection requirements under the project license.
What changed
FERC's New York Regional Office issued correspondence to Brookfield Renewable reviewing the 12th Part 12D Periodic Inspection Report for the Cascade Project filed on December 29, 2025. The letter constitutes routine regulatory oversight under the project license P-2327.
Licensed hydroelectric project operators should maintain compliance with Part 12 dam safety inspection requirements and retain documentation of all FERC correspondence regarding inspection reports. Project operators should ensure timely submission and adequate documentation of periodic inspections to avoid regulatory inquiries.
What to do next
- Monitor for follow-up correspondence from FERC
Archived snapshot
Apr 8, 2026GovPing captured this document from the original source. If the source has since changed or been removed, this is the text as it existed at that time.
Document Info for Accession Number: 20260407-3013
Details Document: 04/07/2026
Filed: 04/07/2026
Posted: 04/07/2026 09:49:38 AM
First Received Date: 04/07/2026 09:23:22 AM
Security Level: Public
Official: Yes
E-filing: No
Non-decisional: No
Category: Issuance
Library: Hydro
Aperture: 0
File Type:
Description* :** Letter to Brookfield Renewable reviewing the 12/29/2025 12th Part 12D Report for the Periodic Inspection for the Cascade Project under P-2327.
Document Components File List
| Docket | Sub-Docket | Type |
| --- | --- | --- |
| P-2327 | 000 | On Document |
| Document Class | Document Type |
| --- | --- |
| FERC Correspondence With Applicant | Compliance Directives |
| FERC Correspondence With Applicant | General Correspondence |
| Order/Opinion | Delegated Order |
| Correspondent | Last Name | First Name | MI | Role/Org |
| --- | --- | --- | --- | --- |
| RECIPIENT | DORMAN | R | | BROOKFIELD RENEWABLE |
| AUTHOR | SPAIN | J | | NEW YORK REGIONAL OFFICE |
Related changes
Get daily alerts for FERC eLibrary: Hydropower Orders
Daily digest delivered to your inbox.
Free. Unsubscribe anytime.
Source
About this page
Every important government, regulator, and court update from around the world. One place. Real-time. Free. Our mission
Source document text, dates, docket IDs, and authority are extracted directly from FERC.
The plain-English summary, classification, and "what to do next" steps are AI-generated from the original text. Cite the source document, not the AI analysis.
Classification
Who this affects
Taxonomy
Browse Categories
Get alerts for this source
We'll email you when FERC eLibrary: Hydropower Orders publishes new changes.