EPA Region 5 approved revisions to Ohio's air permit rules as part of the state's Clean Air Act implementation plan. The rule affects facilities operating under Ohio air permits and modifies the federally approved State Implementation Plan (SIP). The final rule is effective May 4, 2026.
What changed
EPA issued a final rule approving Ohio's revised air permit rules under the Clean Air Act Section 110 State Implementation Plan (SIP) process. The agency determined that Ohio's revisions meet federal requirements for air permit programs. The affected docket is EPA-R05-OAR-2025-0143, and the rule is codified under 40 CFR 52.
Ohio facilities holding air permits should verify that their existing permits remain compliant with the revised state rules. The effective date of May 4, 2026 provides approximately 30 days for affected parties to review the changes. No specific compliance reporting deadlines or penalties were identified beyond standard Clean Air Act enforcement provisions.
What to do next
- Review updated Ohio air permit rules to ensure facility permits remain compliant
- Verify that any pending permit applications align with new state requirements
- Maintain records documenting compliance with revised state air permit program
Source document (simplified)
Legal Status This site displays a prototype of a “Web 2.0” version of the daily
Federal Register. It is not an official legal edition of the Federal
Register, and does not replace the official print version or the official
electronic version on GPO’s govinfo.gov.
The documents posted on this site are XML renditions of published Federal
Register documents. Each document posted on the site includes a link to the
corresponding official PDF file on govinfo.gov. This prototype edition of the
daily Federal Register on FederalRegister.gov will remain an unofficial
informational resource until the Administrative Committee of the Federal
Register (ACFR) issues a regulation granting it official legal status.
For complete information about, and access to, our official publications
and services, go to About the Federal Register on NARA's archives.gov.
The OFR/GPO partnership is committed to presenting accurate and reliable
regulatory information on FederalRegister.gov with the objective of
establishing the XML-based Federal Register as an ACFR-sanctioned
publication in the future. While every effort has been made to ensure that
the material on FederalRegister.gov is accurately displayed, consistent with
the official SGML-based PDF version on govinfo.gov, those relying on it for
legal research should verify their results against an official edition of
the Federal Register. Until the ACFR grants it official status, the XML
rendition of the daily Federal Register on FederalRegister.gov does not
provide legal notice to the public or judicial notice to the courts.
Legal Status
Rule
You may be interested in this older document that published on 01/09/2026 with action 'Proposed rule.' View Document
Air Plan Approval; Ohio; Ohio Permit Rules Revisions
A Rule by the Environmental Protection Agency on 04/02/2026
- 1.
1.
Document Details Published Content - Document Details Agency Environmental Protection Agency Agency/Docket Numbers EPA-R05-OAR-2025-0143 FRL-13000-02-R5 CFR 40 CFR 52 Document Citation 91 FR 16550 Document Number 2026-06398 Document Type Rule Pages 16550-16553
(4 pages) Publication Date 04/02/2026 Published Content - Document DetailsPDF Official Content
- View printed version (PDF) Official Content
Document Details Published Content - Document Details Agency Environmental Protection Agency Agency/Docket Numbers EPA-R05-OAR-2025-0143 FRL-13000-02-R5 CFR 40 CFR 52 Document Citation 91 FR 16550 Document Number 2026-06398 Document Type Rule Pages 16550-16553
(4 pages) Publication Date 04/02/2026 Published Content - Document DetailsDocument Dates Published Content - Document Dates Effective Date 2026-05-04 Dates Text This final rule is effective on May 4, 2026. Published Content - Document Dates
Table of Contents Enhanced Content - Table of Contents This table of contents is a navigational tool, processed from the
headings within the legal text of Federal Register documents.
This repetition of headings to form internal navigation links
has no substantive legal effect.- AGENCY:
- ACTION:
- SUMMARY:
- DATES:
- ADDRESSES:
- FOR FURTHER INFORMATION CONTACT:
- SUPPLEMENTARY INFORMATION:
- I. Background Information
- II. Final Action
- III. Incorporation by Reference
- IV. Statutory and Executive Order Reviews
- List of Subjects in 40 CFR Part 52
- PART 52—APPROVAL AND PROMULGATION OF IMPLEMENTATION PLANS
- Footnotes Enhanced Content - Table of Contents
Related Documents Enhanced Content - Related Documents FederalRegister.gov uses the agency dockets published with the document to display related documents.
| EPA-R05-OAR-2025-0143
(2 Documents) | | | |
| --- | | | |
| Date | | Action | Title |
| | 2026-04-02 | Final rule. | Air Plan Approval; Ohio; Ohio Permit Rules Revisions |
| | 2026-01-09 | Proposed rule. | Air Plan Approval; Ohio; Ohio Permit Rules Revisions |
Enhanced Content - Related Documents
- Public Comments Enhanced Content - Public Comments This feature is not available for this document.
Enhanced Content - Public Comments
- Regulations.gov Data Enhanced Content - Regulations.gov Data Additional information is not currently available for this document.
Enhanced Content - Regulations.gov Data
- Sharing Enhanced Content - Sharing Shorter Document URL https://www.federalregister.gov/d/2026-06398 Email Email this document to a friend Enhanced Content - Sharing
- Print Enhanced Content - Print
- Print this document Enhanced Content - Print
- Other Formats Enhanced Content - Other Formats This document is also available in the following formats:
JSON Normalized attributes and metadata XML Original full text XML MODS Government Publishing Office metadata More information and documentation can be found in our developer tools pages.
Enhanced Content - Other Formats
- Public Inspection Public Inspection This PDF is FR Doc. 2026-06398 as it appeared on Public Inspection on
04/01/2026 at 8:45 am.
It was viewed
15
times while on Public Inspection.
If you are using public inspection listings for legal research, you
should verify the contents of the documents against a final, official
edition of the Federal Register. Only official editions of the
Federal Register provide legal notice of publication to the public and judicial notice
to the courts under 44 U.S.C. 1503 & 1507. Learn more here.
Public Inspection
Published Document: 2026-06398 (91 FR 16550) This document has been published in the Federal Register. Use the PDF linked in the document sidebar for the official electronic format.
Document Headings Document headings vary by document type but may contain
the following:
- the agency or agencies that issued and signed a document
- the number of the CFR title and the number of each part the document amends, proposes to amend, or is directly related to
- the agency docket number / agency internal file number
- the RIN which identifies each regulatory action listed in the Unified Agenda of Federal Regulatory and Deregulatory Actions See the Document Drafting Handbook for more details.
Environmental Protection Agency
- 40 CFR Part 52
- EPA-R05-OAR-2025-0143; FRL-13000-02-R5 # AGENCY:
Environmental Protection Agency (EPA).
ACTION:
Final rule.
SUMMARY:
The Environmental Protection Agency (EPA) is approving revisions to Ohio air permitting rules into the State Implementation Plan (SIP) under the Clean Air Act (CAA). These revisions represent changes to the air permitting rules the Ohio Environmental Protection Agency (Ohio EPA) adopted on March 1, 2023, and July 25, 2025, which became effective at the State level on March 11, 2023, and August 14, 2025, respectively. These revisions will result in consistent requirements of rules at both the State and Federal level. The EPA proposed to approve this action on January 9, 2026, and received no adverse comments.
DATES:
This final rule is effective on May 4, 2026.
ADDRESSES:
The EPA has established a docket for this action under Docket ID No. EPA-R05-OAR-2025-0143. All documents in the docket are listed on the https://www.regulations.gov website. Although listed in the index, some information is not publicly available, i.e., Confidential Business Information (CBI), Proprietary Business Information (PBI), or other information whose disclosure is restricted by statute. Certain other material, such as copyrighted material, is not placed on the internet and will be publicly available only in hard copy form. Publicly available docket materials are available either through https://www.regulations.gov or at the Environmental Protection Agency, Region 5, Air and Radiation Division, 77 West Jackson Boulevard, Chicago, Illinois 60604. This facility is open from 8:30 a.m. to 4:30 p.m., Monday through Friday, excluding Federal holidays. We recommend that you telephone Skyler Sanderson, at (312) 886-4454, before visiting the Region 5 office.
FOR FURTHER INFORMATION CONTACT:
Skyler Sanderson, Air and Radiation Division (AR-18J), Environmental Protection Agency, Region 5, 77 West Jackson Boulevard, Chicago, Illinois 60604, telephone number: (312) 886-4454, email address: sanderson.skyler@epa.gov.
SUPPLEMENTARY INFORMATION:
Throughout this document whenever “we,” “us,” or “our” is used, we mean the EPA.
I. Background Information
On January 9, 2026 (91 FR 937), the EPA proposed to approve revisions submitted on March 19, 2025, and August 5, 2025, to Ohio's air permitting rules into the SIP under the CAA, including incorporating by reference Ohio rule(s) 3745-31-01 [with the exception of OAC 3745-31-01(A)(8), (E)(3)(b)(ii) and (iii), (M)(10)(a)(ii), (P)(12), (Q), and (S)(11)], 3745-31-02, 3745-31-03 [with the exception of OAC 3745-31-03(B)(1)(p)], 3745-31-05 [with the exception of OAC 3745-31-05(E)], 3745-31-06, 3745-31-07, 3745-31-09, 3745-31-10, 3745-31-11, 3745-31-12, 3745-31-13 [with the exception of OAC 3745-31-13(H)(1)(c)], 3745-31-14, 3745-31-15, 3745-31-16, 3745-31-17, 3745-31-18, 3745-31-19, 3745-31-20, 3745-31-21, 3745-31-22 [with the exception of OAC 3745-31-22(A)(3)(b)], 3745-31-23 [with the exception of the 1-hour NO 2 SIL in 3745-31-23(A)], 3745-31-24 [with the exception of OAC 3745-31-24(F)], 3745-31-25, 3745-31-26 [with the exception of OAC 3745-31-26(D)], 3745-31-27 [with the exception of OAC 3745-31-27(A)(1)(b)], 3745-31-28, 3745-31-29, 3745-31-30, and 3745-31-32. An explanation of the CAA requirements, a detailed analysis of the revisions, and the EPA's reasons for proposing approval were provided in the notice of proposed rulemaking and will not be restated here. The public comment period for this proposed rule ended on February 9, 2026. The EPA received no comments on the proposal.
II. Final Action
The EPA is approving Ohio EPA's March 19, 2025, and August 5, 2025, submittals as revisions to its existing SIP. The EPA finds that the revisions are consistent with Federal requirements. As requested by Ohio EPA, the following provisions are not included in this proposed approval: OAC 3745-31-01(A)(8), (E)(3)(b)(ii) and (iii), (M)(10)(a)(ii), (P)(12), (Q), and (S)(11); 3745-31-03(B)(1)(p); 3745-31-05(E); 3745-31-13(H)(1)(c); 3745-31-22(A)(3)(b); 1-hour NO 2 SIL in 3745-31-23(A); 3745-31-24(F); 3745-31-26(D); 3745-31-27(A)(1)(b); and 3745-31-34(B), (C), and (D).
III. Incorporation by Reference
In this rule, the EPA is finalizing regulatory text that includes incorporation by reference. In accordance with requirements of 1 CFR 51.5, the EPA is finalizing the incorporation by reference of the Ohio Regulations described in section I. of this preamble and set forth in the amendments to 40 CFR part 52 below. The EPA has made, and will continue to make, these documents generally available through https://www.regulations.gov, and at the EPA Region 5 Office (please contact the person identified in the FOR FURTHER INFORMATION CONTACT section of this preamble for more information). Therefore, these materials have been approved by the EPA for inclusion in the SIP, have been incorporated by reference by the EPA into that plan, are fully federally enforceable under sections 110 and 113 of the CAA as of the effective date of the final rulemaking of the EPA's approval, and will be incorporated by reference in the next update to the SIP compilation. [1 ]
IV. Statutory and Executive Order Reviews
Under the CAA, the Administrator is required to approve a SIP submission that complies with the provisions of the CAA and applicable Federal regulations. 42 U.S.C. 7410(k); 40 CFR 52.02(a). Thus, in reviewing SIP submissions, the EPA's role is to approve State choices, provided that they meet the criteria of the CAA. Accordingly, this action merely approves State law as meeting Federal requirements and does not impose additional requirements beyond those imposed by State law. For these reasons, this action:
- Is not a significant regulatory action subject to review by the Office of Management and Budget under Executive Order 12866 (58 FR 51735, October 4, 1993);
- Is not subject to Executive Order 14192 (90 FR 9065, February 6, 2025) because SIP actions are exempt from review under Executive Order 12866;
- Does not impose an information collection burden under the provisions of the Paperwork Reduction Act (44 U.S.C. 3501 et seq.);
- Is certified as not having a significant economic impact on a substantial number of small entities under the Regulatory Flexibility Act (5 U.S.C. 601 et seq.);
- Does not contain any unfunded mandate or significantly or uniquely affect small governments, as described in the Unfunded Mandates Reform Act of 1995 (Pub. L. 104-4);
- Does not have federalism implications as specified in Executive Order 13132 (64 FR 43255, August 10, 1999); ( printed page 16551)
- Is not subject to Executive Order 13045 (62 FR 19885, April 23, 1997) because it approves a State program;
- Is not a significant regulatory action subject to Executive Order 13211 (66 FR 28355, May 22, 2001); and
- Is not subject to requirements of section 12(d) of the National Technology Transfer and Advancement Act of 1995 (15 U.S.C. 272 note) because application of those requirements would be inconsistent with the CAA. In addition, the SIP is not approved to apply on any Indian reservation land or in any other area where the EPA or an Indian Tribe has demonstrated that a Tribe has jurisdiction. In those areas of Indian country, the rule does not have Tribal implications and will not impose substantial direct costs on Tribal governments or preempt Tribal law as specified by Executive Order 13175 (65 FR 67249, November 9, 2000).
This action is subject to the Congressional Review Act, and the EPA will submit a rule report to each House of the Congress and to the Comptroller General of the United States. This action is not a “major rule” as defined by 5 U.S.C. 804(2).
Under section 307(b)(1) of the CAA, petitions for judicial review of this action must be filed in the United States Court of Appeals for the appropriate circuit by June 1, 2026. Filing a petition for reconsideration by the Administrator of this final rule does not affect the finality of this action for the purposes of judicial review nor does it extend the time within which a petition for judicial review may be filed, and shall not postpone the effectiveness of such rule or action. This action may not be challenged later in proceedings to enforce its requirements. (See section 307(b)(2).)
List of Subjects in 40 CFR Part 52
- Environmental protection
- Air pollution control
- Carbon oxides
- Incorporation by reference
- Intergovernmental relations
- Lead
- Nitrogen oxides
- Ozone
- Particulate matter
- Reporting and recordkeeping requirements
- Sulfur oxides
- Volatile organic compounds Dated: March 26, 2026.
Cheryl Newton,
Acting Regional Administrator, Region 5.
For the reasons stated in the preamble, title 40 CFR part 52 is amended as follows:
PART 52—APPROVAL AND PROMULGATION OF IMPLEMENTATION PLANS
- The authority citation for part 52 continues to read as follows:
Authority: 42 U.S.C. 7401 et seq.
- In § 52.1870, amend the table in paragraph (c) by revising the section “Chapter 3745-31 Permit-to Install New Sources and Permit-to-Install and Operate Program”, consisting of entries 3745-31-01 through 2745-31-34, to read as follows:
§ 52.1870 Identification of plan. * * * * * (c) * * *
| Ohio
citation | Title/subject | Ohio
effective date | EPA Approval date | Notes |
| --- | --- | --- | --- | --- |
| | | | | |
| * | | | | |
| Chapter 3745-31 Permit-to-Install New Sources and Permit-to-Install and Operate Program | | | | |
| 3745-31-01 | Definitions | 3/11/2023 | 4/2/2026, 91 FR [Insert Federal Register page where the document begins] | Except for (A)(8), (E)(3)(b)(ii) and (iii), (M)(10)(a)(ii), (P)(12), (Q), and (S)(11). |
| 3745-31-02 | Applicability, requirements, and obligations | 3/11/2023 | 4/2/2026, 91 FR [Insert Federal Register page where the document begins] | |
| 3745-31-03 | Exemptions | 8/14/2025 | 4/2/2026, 91 FR [Insert Federal Register page where the document begins] | Except for (B)(1)(p). |
| 3745-31-04 | Applications | 5/29/2014 | 6/25/2015, 80 FR 36477 | |
| 3745-31-05 | Criteria for decision by the Director | 3/11/2023 | 4/2/2026, 91 FR [Insert Federal Register page where the document begins] | Except for (E). |
| 3745-31-06 | Completeness determinations, processing requirements, public participation, public notice, and issuance | 3/11/2023 | 4/2/2026, 91 FR [Insert Federal Register page where the document begins] | |
| 3745-31-07 | Termination, revocation, expiration, renewal, revision and transfer | 3/11/2023 | 4/2/2026, 91 FR [Insert Federal Register page where the document begins] | |
| 3745-31-08 | Registration status permit-to-operate | 5/29/2014 | 6/25/2015, 80 FR 36477 | |
| 3745-31-09 | Variances on operation | 3/11/2023 | 4/2/2026, 91 FR [Insert Federal Register page where the document begins] | |
| 3745-31-10 | NSR projects at existing emissions units at a major stationary source | 3/11/2023 | 4/2/2026, 91 FR [Insert Federal Register page where the document begins] | |
| 3745-31-11 | Attainment provisions—ambient air increments, ceilings, and classifications | 3/11/2023 | 4/2/2026, 91 FR [Insert Federal Register page where the document begins] | |
| 3745-31-12 | Attainment provisions—data submission requirements | 3/11/2023 | 4/2/2026, 91 FR [Insert Federal Register page where the document begins] | |
| ( printed page 16552) | | | | |
| 3745-31-13 | Attainment provisions—review of major stationary sources and major modifications, stationary source applicability, and exemptions | 3/11/2023 | 4/2/2026, 91 FR [Insert Federal Register page where the document begins] | Except for (H)(1)(c). |
| 3745-31-14 | Attainment provisions—pre-application analysis | 3/11/2023 | 4/2/2026, 91 FR [Insert Federal Register page where the document begins] | |
| 3745-31-15 | Attainment provisions—control technology review | 3/11/2023 | 4/2/2026, 91 FR [Insert Federal Register page where the document begins] | |
| 3745-31-16 | Attainment provisions—major stationary source impact analysis | 3/11/2023 | 4/2/2026, 91 FR [Insert Federal Register page where the document begins] | |
| 3745-31-17 | Attainment provisions—additional impact analysis | 3/11/2023 | 4/2/2026, 91 FR [Insert Federal Register page where the document begins] | |
| 3745-31-18 | Attainment provisions—air quality models | 3/11/2023 | 4/2/2026, 91 FR [Insert Federal Register page where the document begins] | |
| 3745-31-19 | Attainment provisions—notice to the United States environmental protection agency | 3/11/2023 | 4/2/2026, 91 FR [Insert Federal Register page where the document begins] | |
| 3745-31-20 | Attainment provisions—innovative control technology | 3/11/2023 | 4/2/2026, 91 FR [Insert Federal Register page where the document begins] | |
| 3745-31-21 | Nonattainment provisions—review of major stationary sources and major modifications—stationary source applicability and exemptions | 3/11/2023 | 4/2/2026, 91 FR [Insert Federal Register page where the document begins] | |
| 3745-31-22 | Nonattainment provisions—conditions for approval | 3/11/2023 | 4/2/2026, 91 FR [Insert Federal Register page where the document begins] | Except for (A)(3)(b). |
| 3745-31-23 | Nonattainment provisions—stationary sources locating in designated clean or unclassifiable areas which would cause or contribute to a violation of a national ambient air quality standard | 3/11/2023 | 4/2/2026, 91 FR [Insert Federal Register page where the document begins] | Except for 1-hour NO2 SIL in (A). |
| 3745-31-24 | Nonattainment provisions—baseline for determining credit for emission and air quality offsets | 3/11/2023 | 4/2/2026, 91 FR [Insert Federal Register page where the document begins] | Except for (F). |
| 3745-31-25 | Nonattainment provisions—location of offsetting emissions | 3/11/2023 | 4/2/2026, 91 FR [Insert Federal Register page where the document begins] | |
| 3745-31-26 | Nonattainment provisions—offset ratio requirements | 3/11/2023 | 4/2/2026, 91 FR [Insert Federal Register page where the document begins] | Except for (D). |
| 3745-31-27 | Nonattainment provisions—administrative procedures for emission offsets | 3/11/2023 | 4/2/2026, 91 FR [Insert Federal Register page where the document begins] | Except for (A)(1)(b). |
| 3745-31-28 | Review of major stationary sources of hazardous air pollutants requiring MACT determinations | 3/11/2023 | 4/2/2026, 91 FR [Insert Federal Register page where the document begins] | |
| 3745-31-29 | General permit-to-install and general PTIO | 3/11/2023 | 4/2/2026, 91 FR [Insert Federal Register page where the document begins] | |
| 3745-31-30 | Permits-by-rule | 3/11/2023 | 4/2/2026, 91 FR [Insert Federal Register page where the document begins] | |
| 3745-31-32 | Plantwide applicability limit | 3/11/2023 | 4/2/2026, 91 FR [Insert Federal Register page where the document begins] | |
| 3745-31-34 | Permits to install for major stationary sources and major modifications of sources emitting greenhouse gases | 3/31/2011 | 2/14/2020, 85 FR 8406 | Except for (B), (C), and (D). |
| | | | | |
| ( printed page 16553) | | | | |
| * | | | | |
Footnotes
- 62 FR 27968 (May 22, 1997).
Back to Citation [FR Doc. 2026-06398 Filed 4-1-26; 8:45 am]
BILLING CODE 6560-50-P
Published Document: 2026-06398 (91 FR 16550)
CFR references
Named provisions
Related changes
Source
Classification
Who this affects
Taxonomy
Browse Categories
Get Environment alerts
Weekly digest. AI-summarized, no noise.
Free. Unsubscribe anytime.
Get alerts for this source
We'll email you when FR: Environmental Protection Agency publishes new changes.