TVA Approves Allen Aeroderivative Combustion Turbine Project
Summary
The Tennessee Valley Authority (TVA) has approved the construction and operation of six aeroderivative combustion turbine units at its Allen CT facility in Memphis, Tennessee. This project aims to generate approximately 200 megawatts of power to support system load growth and enhance grid reliability. The decision follows the Final Environmental Impact Statement and is in accordance with the National Environmental Policy Act.
What changed
The Tennessee Valley Authority (TVA) has issued a Record of Decision approving the construction and operation of six aeroderivative combustion turbine (CT) units at its Allen CT facility in Memphis, Tennessee. This project, identified as the preferred alternative in the Final Environmental Impact Statement (EIS), will add approximately 200 megawatts of dispatchable generation capacity. The decision supports TVA's 2019 Integrated Resource Plan (IRP) which identified a need for new CT units to meet growing system load, improve flexibility, and integrate renewable energy sources.
This action is a final decision following the NEPA process, with the Final EIS Notice of Availability published on July 18, 2025. While this is a Record of Decision and not a rule with a direct compliance deadline for external entities, regulated parties within the energy sector, particularly those interacting with TVA's infrastructure or planning similar projects, should be aware of this development. The project aims to enhance the reliability and stability of TVA's power system in western Tennessee. Further information can be obtained from Matthew Higdon, NEPA Specialist at TVA.
Source document (simplified)
Content
ACTION:
Record of Decision.
SUMMARY:
Tennessee Valley Authority (TVA) has decided to implement the preferred alternative identified in its Final Environmental
Impact Statement (EIS; Document ID EISX-455-00-000-1730803146) for the construction and operation of six aeroderivative combustion
turbine (CT) units at its existing Allen CT facility located in Memphis, Tennessee. Under the preferred alternative, TVA would
construct and operate the new units to generate approximately 200 megawatts (MW) of power to provide dispatchable generation
to support the continued system load growth experienced in the TVA power service area and increase the flexibility and reliability
of TVA's power system by improving TVA's transmission system stability in western Tennessee.
FOR FURTHER INFORMATION CONTACT:
Matthew Higdon, NEPA Specialist, Tennessee Valley Authority, 400 West Summit Hill Drive, Knoxville, Tennessee 37902; telephone
865-632-8051; email mshigdon@tva.gov. The Final EIS, this Record of Decision, and other project documents are available on TVA's website at https://www.tva.gov/allenct.
SUPPLEMENTARY INFORMATION:
This notice is provided in accordance with the National Environmental Policy Act (NEPA), as amended (42 U.S. Code [U.S.C.]
§§ 4321 et seq.) and TVA's NEPA procedures (18 CFR part 1318).
TVA is a corporate agency and instrumentality of the United States that provides electricity for 153 local power companies
(LPC) serving approximately 10 million people as well as directly serving commercial, industrial, and government customers
in the Tennessee Valley—an 80,000-square-mile region comprised of Tennessee and parts of Virginia, North Carolina, Georgia,
Alabama, Mississippi, and Kentucky.
Planning Basis and Assumptions
In 2019, TVA completed its IRP and associated IRP EIS. The 2019 IRP identified various energy resource options that TVA may
pursue to meet the energy needs of the Tennessee Valley region over a 20-year planning period. The strategic direction established
by the 2019 IRP and results from recommended near-term actions formed the basis for TVA's asset strategy, which continues
to support affordable, reliable, and cleaner energy for customers. The 2019 IRP recommendation optimizes TVA's ability to
create a more flexible power-generation system that can successfully meet changing load demands and integrate increasing amounts
of
renewable energy sources while ensuring reliability. TVA's target power supply mix includes firm, dispatchable power, which
refers to a generating resource that can adjust power output up or down on demand within the specific operating limitations
of that resource, thus increasing system reliability and resiliency. The 2019 IRP remains valid and continues to guide future
generation planning until TVA updates its IRP and the TVA Board of Directors approves new recommendations.
The 2019 IRP identified the need for up to 5,200 MW of new CT units by 2028. Aeroderivative CT units are highly efficient
and can be operated year-round to meet the fluctuating demand on the power system, including overnight, during cold pre-dawn
winter mornings, and during warm summer evenings as solar generation fades.
Alternatives Considered
TVA prepared the Final EIS pursuant to NEPA to assess the environmental effects associated with constructing and operating
the new units at the existing facility site, utilizing existing natural gas and transmission infrastructure to meet system-wide
generation demands. The Notice of Availability (NOA) for the Final EIS was published in the
Federal Register
on July 18, 2025.
In the Final EIS, TVA assessed two alternatives: Alternative A—No Action, and Alternative B—Construction and operation of
six aeroderivative CT units at the Allen CT facility. In the Final EIS, TVA identified Alternative B as its preferred alternative
and summarized the other alternatives it considered but eliminated from detailed evaluation.
Alternative A: No Action Alternative —Under the No Action Alternative, TVA would not construct six new aero CT units or the associated support facilities to provide
generation of approximately 200 MW at the ACT Plant. TVA would continue to operate two existing units (units 19 and 20) at
the ACT Plant on a limited basis, consistent with the 2021 Paradise and Colbert Combustion Turbine EA. This alternative does
not meet the purpose and need of TVA's proposed action; however, consistent with the requirements of NEPA, it is included
in this evaluation because it represents current baseline conditions against which the proposed action alternative is compared.
Alternative B: Construction and operation of six aeroderivative CT units at the Allen CT facility —Under Alternative B, TVA would construct and operate six aero CT units (GE LM2500s) generating approximately 200 MW of power
and associated support facilities. TVA would continue to operate units 19 and 20 on a limited basis as well. At least four
of the new units would have black-start capability, meaning the ability to restore power without needing to rely upon inputs
from the external electric power transmission system. The new units would support fast startup dispatching and synchronous
condensing for transmission system stability in western Tennessee. TVA would install control systems to minimize and monitor
air emissions of the new units; reduction of emissions from each unit would be achieved through a dry-low emissions combustion
system and a selective catalytic reduction system. TVA would use potable water obtained from the existing public supply for
inlet air evaporative cooling in summer ambient temperatures.
Alternative B would meet TVA's purpose and need to support continued load growth within the Tennessee Valley and increase
the flexibility and reliability of the TVA power system by improving TVA's transmission system stability in western Tennessee.
These improvements would also help TVA expand and integrate renewable energy resources onto its transmission grid. Alternative
B also aligns with the 2019 IRP generation target power supply mix, which allows for the addition of up to 5,200 MW of CT
by 2028.
Summary of Environmental Effects
The anticipated environmental effects of the No Action Alternative and Alternative B are described in detail in the Final
EIS and summarized in Table 2.2-1. This section summarizes the anticipated environmental effects that would occur.
Under the No Action Alternative, TVA would not construct or operate new aeroderivative CT units at the Allen CT facility.
The No Action Alternative would avoid the adverse effects associated with constructing and operating new units at the existing
facility. For this reason, TVA identifies this alternative as environmentally preferable. However, TVA would be required to
obtain capacity from other sources to maintain reserves, if possible. Without peaking power available when needed, TVA would
purchase the power from the cheapest market source, a portion of which would likely be natural gas. Relying on purchased power
from a market source could potentially result in adverse effects to TVA generation system reliability and increased costs
to customers. Incorporation of renewable energy sources would be limited without the addition of the reliable dispatchable
generation.
As outlined in the Final EIS, TVA's proposed action under Alternative B would have no effect on the following resources: Floodplains,
Wetlands, Land Use, Geology/Soils, Vegetation, Prime Farmland, Aquatic Ecology, Visual Resources, Recreation, and Cultural
and Historic Resources. In the Final EIS, TVA described minor and temporary effects on the following resources: Groundwater,
Natural Areas, Threatened and Endangered Species, Transportation, Public Health and Safety, and Solid and Hazardous Waste.
Minor, long-term effects anticipated are Socioeconomics, Climate Change, Utilities, Surface Water Resources, and Noise. Moderate,
long-term effects to air quality are anticipated and are discussed in the Final EIS. Generally, constructing and operating
the new aeroderivative CT units at the existing CT facility would minimize new ground disturbances and utilize existing natural
gas and transmission infrastructure, resulting in fewer environmental effects.
In the Final EIS, TVA also describes beneficial effects to Utilities resulting from implementing Alternative B. Overall, the
added dispatchable generation capacity as a result of Alternative B would have potential long-term beneficial effects by helping
to ensure that TVA can reliably meet required year-round generation, maximum capacity system demands, and planning reserve
margin targets while facilitating the integration of renewable energy onto the electric grid. The synchronous condensing and
black-start capabilities of the units would also benefit TVA's transmission system by improving reliability and flexibility.
Public Involvement
TVA initiated a 30-day public scoping period on October 12, 2023, when it published a Notice of Intent in the
Federal Register
announcing the preparation of an environmental document (88 FR 70693, October 12, 2023). TVA also announced the project and
requested public input in news releases; notices printed in relevant area newspapers; in letters or messages to federal, state,
and local agencies and federally recognized Indian tribes; and on its public web page (https://www.tva.com/allenct). TVA held a public scoping meeting on October 24, 2023, attended by 35 individuals. TVA also hosted a public webinar. During
the scoping period, TVA received 19 submissions from members of the public, federal agencies, and various organizations.
The NOA of the Draft EIS was published in the
Federal Register
on March 14, 2025, initiating a 45-day public comment period that ended on April 28, 2025 (90 FR 12158, March 14, 2025). The
availability of the Draft EIS and request for comments were announced in a news release, newspaper advertisements, and letters
or messages to interagency partners, and on social media and TVA's website. Postcards were mailed to over 9,000 addresses
within five miles of the project area as well. TVA held a public meeting about the Draft EIS on April 10, 2025, attended by
over 110 individuals. TVA also held a public webinar during the comment period. In total, TVA received 210 submissions from
the public, local officials, state and federal agencies, and community organizations during the comment period. Responses
to these comments are included in Appendix A of the Final EIS.
Decision
TVA has considered the alternatives, information, analyses, material in the record determined to be relevant, and comments
submitted by federal and state governments and public commenters for consideration in developing the Final EIS. TVA has decided
to implement Alternative B of the Final EIS to construct and operate six new aeroderivative CT units at its existing Allen
CT facility to generate approximately 200 MW of dispatchable power. This alternative best achieves TVA's purpose and need
to meet the growing system demand and load growth experience over the past few years. The addition of these units to TVA's
fleet also aligns with the 2019 IRP recommendation to develop new dispatchable generation sources and to enhance system reliability
and flexibility.
Mitigation
TVA would employ standard practices, routine measures, and other project-specific measures to avoid and minimize effects to
resources from the implementation of Alternative B. TVA would also implement minimization and mitigation measures based on
best management practices, permit requirements, and adherence to erosion and sediment control plans to minimize erosion during
construction, operation, and maintenance activities. As discussed in the Final EIS, TVA would also continue (under a prior
agreement with the U.S. Fish and Wildlife Service) to monitor the project area for the presence of potential nesting sites
for least terns and, if nests are found, would conduct no activities within 300 feet of the nests.
Authority: 18 CFR 1318.405.
Dated: September 25, 2025. Donald A. Moul, President and Chief Executive Officer.
Editorial Note:
This document was received for publication by the Office of the Federal Register on January 12, 2026.
[FR Doc. 2026-00570 Filed 1-13-26; 8:45 am] BILLING CODE 8120-08-P
Download File
Download
Related changes
Source
Classification
Who this affects
Taxonomy
Browse Categories
Get Energy alerts
Weekly digest. AI-summarized, no noise.
Free. Unsubscribe anytime.
Get alerts for this source
We'll email you when Regs.gov: Tennessee Valley Authority publishes new changes.