Texas Eastern Line 31 Expansion Environmental Assessment Schedule
Summary
FERC announced the schedule for completing an environmental assessment for Texas Eastern Transmission's proposed Line 31 Expansion Project in Madison County, Mississippi. The EA will be issued June 15, 2026, with a 90-day federal authorization decision deadline of September 13, 2026. The project proposes to add 125,000 dekatherms per day of natural gas transportation capacity through approximately 11.8 miles of new pipeline and supporting facilities.
What changed
FERC issued a notice establishing the environmental assessment schedule for the Texas Eastern Line 31 Expansion Project. The EA will be issued June 15, 2026, followed by a 30-day public comment period. All federal authorization decisions must be completed by September 13, 2026 (90 days from EA issuance).
Affected parties including energy companies, local agencies, and stakeholders should monitor FERC proceedings and prepare comments on the EA. The project involves constructing pipeline loops, lateral lines, a new compressor station, and meter stations in Madison County, Mississippi totaling approximately 11.8 miles of new pipeline infrastructure.
What to do next
- Monitor FERC Docket No. CP26-75-000 for EA issuance
- Prepare comments on EA during 30-day comment period
- Review project details for potential impacts to stakeholders
Archived snapshot
Apr 9, 2026GovPing captured this document from the original source. If the source has since changed or been removed, this is the text as it existed at that time.
Notice
Texas Eastern Transmission, LP; Notice of Schedule for the Preparation of an Environmental Assessment for the Line 31 Expansion Project
A Notice by the Federal Energy Regulatory Commission on 04/09/2026
PDF
Document Details
Table of Contents
- Related Documents
- Public Comments
- Regulations.gov Data
- Sharing
- Other Formats
- Public Inspection Published Document: 2026-06887 (91 FR 17963) Document Headings ###### Department of Energy
Federal Energy Regulatory Commission
- [Docket No. CP26-75-000] On January 23, 2026, Texas Eastern Transmission, LP (Texas Eastern) filed an application in Docket No. CP26-75-000 requesting a Certificate of Public Convenience and Necessity pursuant to Section 7(c) of the Natural Gas Act to construct and operate certain natural gas pipeline facilities. The proposed project is known as the Line 31 Expansion Project (Project) and would provide up to an additional 125,000 dekatherms per day (Dth/d) of firm incremental natural gas transportation capacity on a segment of Texas Eastern's mainline pipeline system.
On February 6, 2026, the Federal Energy Regulatory Commission (Commission or FERC) issued its Notice of Application for the Project. Among other things, that notice alerted agencies issuing federal authorizations of the requirement to complete all necessary reviews and to reach a final decision on a request for a federal authorization within 90 days of the date of issuance of the Commission staff's environmental document for the Project.
This notice identifies Commission staff's intention to prepare an environmental assessment (EA) for the Project and the planned schedule for the completion of the environmental review. [1 ] The EA will be issued for a 30-day comment period.
Schedule for Environmental Review
Issuance of EA June 15, 2026
90-day Federal Authorization Decision Deadline [2 ] September 13, 2026
If a schedule change becomes necessary, additional notice will be provided so that the relevant agencies are kept informed of the Project's progress. ( printed page 17964)
Project Description
Texas Eastern proposes to construct and operate approximately 10.2 miles of 36-inch-diameter pipeline (Line 31 Pipeline Loop), 1.6 miles of 16-inch-diameter pipeline (Line 14-P Lateral), a new compressor station (Ridgeline Compressor Station), and a new meter and regulator station (Ridgeland Meter and Regulator Station) in Madison County, Mississippi. The Line 31 Pipeline Loop would connect to Texas Eastern's Lines 14 and 18 at two new 30-inch-diameter crossover valves. The Line 14-P Lateral is connecting to Lines 14 and 18 and extending southward to a terminus at an interconnect with Entergy Mississippi, LLC's proposed Traceview Advanced Power Station (Traceview) in Madison County. The Ridgeland Meter and Regulator Station would be installed at milepost 1.6 of the Line 14-P Lateral and at an interconnect with Traceview. Texas Eastern would also construct the new Ridgeland Compressor Station which would contain three compressor units, each having a capacity of about 1,500 horsepower. Additional aboveground facilities would include main line valves, inspection gauge pig [3 ] launcher/receivers, and cathodic protection along Line 31 Pipeline Loop and the Line 14-P Lateral.
Background
On March 4, 2026, the Commission issued a Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Line 31 Expansion Project (Notice of Scoping). The Notice of Scoping was sent to affected landowners; federal, state, and local government agencies; elected officials; environmental and public interest groups; Native American tribes; other interested parties; and local libraries and newspapers. In response to the Notice of Scoping, the Commission received comments from a potentially affected landowner. The primary issues raised include public safety, potential effects on ecosystems, soil compaction, compensation, property values, water resources, aquatic species, and cultural resources. All substantive comments will be addressed in the EA.
Additional Information
In order to receive notification of the issuance of the EA and to keep track of formal issuances and submittals in specific dockets, the Commission offers a free service called eSubscription. This service provides automatic notification of filings made to subscribed dockets, document summaries, and direct links to the documents. Go to https://www.ferc.gov/ferc-online/overview to register for eSubscription.
For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, contact the Office of Public Participation at (202) 502-6595 or OPP@ferc.gov.
Additional information about the Project is available from the FERC website (www.ferc.gov). Using the “eLibrary” link, select “General Search” from the eLibrary menu, enter the selected date range and “Docket Number” excluding the last three digits (i.e., CP26-75), and follow the instructions. For assistance with access to eLibrary, the helpline can be reached at (866) 208-3676, TTY (202) 502-8659, or at FERCOnlineSupport@ferc.gov. The eLibrary link on the FERC website also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rule makings.
(Authority: 18 CFR 2.1)
Dated: April 6, 2026.
Debbie-Anne A. Reese,
Secretary.
Footnotes
1.
For tracking purposes under the National Environmental Policy Act, the unique identification number for documents relating to this environmental review is EAXX-019-20-000-1773325462.
The Commission's deadline applies to the decisions of other federal agencies, and state agencies acting under federally delegated authority, that are responsible for federal authorizations, permits, and other approvals necessary for proposed projects under the Natural Gas Act. Per [18 CFR 157.22(a)](https://www.ecfr.gov/current/title-18/section-157.22#p-157.22(a)), the Commission's deadline for other agency's decisions applies unless a schedule is otherwise established by federal law.
Pig launchers are essential devices in pipeline systems that facilitate the introduction of pipeline inspection gauges (pigs) for maintenance, cleaning, and inspection purposes.
Back to Citation [FR Doc. 2026-06887 Filed 4-8-26; 8:45 am]
BILLING CODE 6717-01-P
Published Document: 2026-06887 (91 FR 17963)
Related changes
Get daily alerts for FR: Federal Energy Regulatory Commission
Daily digest delivered to your inbox.
Free. Unsubscribe anytime.
Source
About this page
Every important government, regulator, and court update from around the world. One place. Real-time. Free. Our mission
Source document text, dates, docket IDs, and authority are extracted directly from Energy Department.
The plain-English summary, classification, and "what to do next" steps are AI-generated from the original text. Cite the source document, not the AI analysis.
Classification
Who this affects
Taxonomy
Browse Categories
Get alerts for this source
We'll email you when FR: Federal Energy Regulatory Commission publishes new changes.