Changeflow GovPing Courts & Legal Mohamad Ezzeddine v. City of Burien – LUPA Serv...
Routine Enforcement Amended Final

Mohamad Ezzeddine v. City of Burien – LUPA Service Requirements

Favicon for www.courtlistener.com Washington Court of Appeals Opinions (CourtListener)
Filed
Detected
Email

Summary

The Court of Appeals of Washington affirmed summary judgment dismissal of a land use petition under the Land Use Petition Act (LUPA). The court held that petitioner Mohamad Ezzeddine's service of his LUPA petition was untimely because he emailed the petition to an administrative assistant and legal counsel rather than to designated agents as required by RCW 36.70C.040(3). The court rejected Ezzeddine's argument that the three-day mailing extension applied, finding the statute's strict service requirements were not satisfied.

“Ezzeddine's filing and service of his land use petition did not comply with the strict requirement of RCW 36.70C.040(3).”

Published by WA Court of Appeals on courtlistener.com . Detected, standardized, and enriched by GovPing. Review our methodology and editorial standards .

What changed

The court affirmed summary judgment dismissal because Ezzeddine's service of his LUPA petition failed to comply with the strict statutory requirement of RCW 36.70C.040(3). Ezzeddine emailed the petition at 4:02 p.m. on April 2, 2025, to an administrative assistant, legal counsel, and an apparent law firm address—none designated as authorized agents to receive LUPA service. The 21-day appeal deadline from the March 12 hearing examiner decision had not been met. The court rejected application of the three-day mailing extension under RCW 36.70C.040(4)(a), which applies only when a land use decision is 'mailed.'\n\nProperty owners and practitioners filing LUPA petitions in Washington must ensure service on designated agents within statutory deadlines. The strict requirements of RCW 36.70C.040(3) are jurisdictional—failure to comply can result in dismissal for lack of subject matter jurisdiction, as occurred here.

Archived snapshot

Apr 21, 2026

GovPing captured this document from the original source. If the source has since changed or been removed, this is the text as it existed at that time.

Jump To

Top Caption Lead Opinion

Support FLP

CourtListener is a project of Free
Law Project
, a federally-recognized 501(c)(3) non-profit. Members help support our work and get special access to features.

Please become a member today.

Join Free.law Now

April 20, 2026 Get Citation Alerts Download PDF Add Note

Mohamad Ezzeddine, V. City Of Burien

Court of Appeals of Washington

Lead Opinion

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

MOHAMAD EZZEDDINE,
No. 88598-7-I
Appellant,
DIVISION ONE
v.
UNPUBLISHED OPINION
CITY OF BURIEN,

Respondent.

BUI, J. —This case concerns the statutory requirements for filing and

serving a municipality with a land use petition under the land use petition act

(LUPA) ch. 36.70C RCW. The LUPA sets strict timelines to complete filing and

service, with a three-day tolling provision applicable to land use decisions that

are “mailed.” RCW 36.70C.040(4)(a). Ezzeddine’s filing and service of his land

use petition did not comply with the strict requirement of RCW 36.70C.040(3).

We affirm the trial court’s summary judgment dismissal of Ezzeddine’s land use

petition.

FACTS

In 2021, Mohamad Ezzeddine purchased property located in the city of

Burien (City). In 2024, after receiving a report that Ezzeddine was operating an

Airbnb business on the property without a permit, the City visited the property in

question. During the visit, code enforcement officer Michael Amaya saw

structures on the property matching listings on Airbnb. The City also observed
No. 88598-7-I/2

“several lettered parking spaces” near the driveway. When asked about and

shown the Airbnb listings advertising structures on the property as available for

short-term rentals, Ezzeddine stated the listings were a “future aspiration.”

Based on the Airbnb listings, the City suspected the A-frame and white

shed structures lacked proper construction and building permits for amenities,

such as electricity and plumbing. As part of its investigation, the City also

referenced aerial photographs, a preliminary Geotech Evaluation, and a draft

critical area report, to determine the observed A-frame structure, bridge, and

man-made pond were constructed within 50 feet of an “Ns” 1 class stream, in

violation of Burien Municipal Code (BMC). Burien’s and King County’s permitting

systems yielded no records of requisite permits for conducting business

physically in Burien, construction, or compliance with the stream buffer.

The City advised Ezzeddine to remove all Airbnb listings associated with

the property until he acquired appropriate permits and posted placards on the

four structures marking them as “Unfit for Human Occupancy.”

Months later, the City visited Ezzeddine’s property again, where it

observed the previously posted “Unfit for Human Occupancy” notices were

removed, the previously observed violations remained, and all four structures’

Airbnb listings were active.

Thereafter, the City mailed two notices of civil violations to Ezzeddine on

June 13, 2024, and August 6, 2024. Ezzeddine requested an administrative

1 “Non-seasonal stream.”

2
No. 88598-7-I/3

hearing to contest the violations. At the first administrative hearing, Ezzeddine

did not dispute the violations but questioned the City’s evidence, namely the

accuracy of their aerial photographs, geographic information system (GIS) maps,

screenshots of Airbnb listings, and the accuracy of Burien and King County’s

permitting systems. Ezzeddine also claimed the second violation notice was

improperly served, and the City improperly posted an “Unfit for Human

Occupancy” sign on the residential structure as it was not cited as a structure in

violation of BMC.

At the end of the hearing, the hearing examiner left the record open to

allow the City to respond to the exhibits Ezzeddine presented on the day of the

hearing. A second hearing was held to address the rebuttal materials. Ezzeddine,

again, did not dispute his violations but disputed the accuracy of the City’s

evidence and accuracy of a witness’s recollection.

On March 12, 2025, the hearing examiner entered a written decision

finding that substantial evidence supported four out of the five cited violations,

dismissing one violation. The hearing examiner found the City’s evidence of

aerial photographs, witnesses’ testimony, and the permitting system’s absence of

records supported the violations. Although the trial court found Ezzeddine made

some headway poking holes in the accuracy of the City’s permitting system,

overall, the court found it did not override Ezzeddine’s lack of evidence that

requisite permits existed during periods of building and modification to his

property.

3
No. 88598-7-I/4

The hearing examiner sent the decision to Ezzeddine by e-mail and

regular mail on the same day. The “Right of Appeal” section of the decision

contained an advisement that “[a]ppeals must be served and filed within 21 days

of issuance of this decision as specified in LUPA.”

On April 2, 2025, at 4:02 p.m., Ezzeddine sent an e-mail to City of Burien

Administrative Assistant Michele Barrera, the City’s legal counsel, and to an

individual whose e-mail address appeared to be a law firm. In the e-mail,

Ezzeddine wrote “Hello All. I just filed an LUPA appeal for the hearing examiner’s

decision on March 12.” In her capacity as Administrative Assistant, Barrera

processes and maintains records related to code enforcement and legal

proceedings, which included the records of Ezzeddine’s LUPA case. Barrera

stated that none of the three recipients of the e-mail and the attached LUPA

petition were designated agents to receive the LUPA. On April 7, 2025,

Ezzeddine filed and served an amended LUPA petition via electronic and

personal service.

King County Superior Court received the e-filing of the LUPA petition on

April 2, 2025. On the same day of receipt, the court issued a case schedule order

setting the matter for hearing on September 8, 2025. The City filed a motion for

summary judgment to dismiss Ezzeddine’s amended LUPA petition. On July 17,

2025, trial court granted the motion, finding that Ezzeddine’s untimely appeal of

the hearing examiner’s land use decision deprived the court of subject matter

4
No. 88598-7-I/5

jurisdiction under RCW 36.70C.040(2)-(3). 2 Ezzeddine moved for

reconsideration, which was denied.

Ezzeddine timely appealed.

ANALYSIS

Ezzeddine contends the trial court erred in dismissing his Land Use

Petition because it did not consider the three-day mailing extension. We

disagree.

A trial court’s order granting summary judgment is reviewed de novo,

performing the same inquiry as the trial court. Gardens Condo. v. Farmers Ins.

Exch., 2 Wn.3d 832, 838, 544 P.3d 499 (2024). “We may affirm an order granting

summary judgment if there are no genuine issues of material fact and the moving

party is entitled to judgment as a matter of law.” Berst v. Snohomish County, 114

Wn. App. 245, 251, 57 P.3d 273 (2002). “A genuine issue of material fact exists

where reasonable minds could differ on the facts controlling the outcome of the

litigation.” Ranger Ins. Co. v. Pierce County, 164 Wn.2d 545, 552, 192 P.3d 886

(2008). “When determining whether an issue of material fact exists, [we] must

construe all facts and inferences in favor of the nonmoving party.” Ranger, 164

Wn.2d at 552.

We also review land use decisions de novo. “Judicial review of land use

decisions is governed by Land Use Petition Act (LUPA).” Whatcom County Fire

2 The trial court also found Ezzeddine failed to demonstrate statutory grounds for relief

under RCW 36.70C.130(1); the Hearing Examiner’s final decision was supported by substantial
evidence and was not legally erroneous; and there were no genuine issues of material fact.

5
No. 88598-7-I/6

Dist. No. 21 v. Whatcom County, 171 Wn.2d 421, 426, 256 P.3d 295, 297 (2011)

(citing Griffin v. Thurston County Bd. of Health, 165 Wn.2d 50, 54, 196 P.3d 141

(2008)). Appellate courts sit in the same position as the superior court and apply

the standards set forth in RCW 36.70C.130(1) to the administrative record that

was before the body responsible for the land use decision. Griffin, 165 Wn.2d at

54–55 (citing Isla Verde Int’l Holdings, Inc. v. City of Camas, 146 Wn.2d 740,

751, 49 P.3d 867 (2002)).

In 1995, LUPA was enacted to provide for “the exclusive means of judicial

review of land use decisions” made by local jurisdictions. RCW 36.70C.030(1). A

“land use decision” is a final determination made by a local jurisdiction. RCW

36.70C.020(2). Local jurisdictions include incorporated towns, counties, or cities.

RCW 36.70C.020(3). The local jurisdiction in this case is the municipality of

Burien.

LUPA’s statutory purpose is to “establish[ ] uniform, expedited appeal

procedures” that “provide consistent, predictable, and timely judicial review.”

RCW 36.70C.010. “A land use petition is barred, and the court may not grant

review, unless the petition is timely filed with the court and timely served on the

. . . local jurisdiction.” RCW 36.70C.040(2)(a).

Within the context of LUPA, “a superior court acts in an appellate capacity”

and cannot exercise its jurisdiction unless LUPA’s service and filing requirements

are satisfied. Conom v. Snohomish County, 155 Wn.2d 154, 157, 118 P.3d 344

(2005). A superior court that lacks appellate jurisdiction must dismiss a LUPA

petition. Conom, 155 Wn.2d at 157.

6
No. 88598-7-I/7

Service of a LUPA petition on a municipality is governed by RCW

36.70C.040 and RCW 4.28.080. Both statutes impose strict requirements for

service of petitions. Service of the petition on a municipality “must be by delivery

of a copy of the petition to the office of a person identified by or pursuant to RCW

4.28.080 to receive service of process, or as otherwise designated by the local

jurisdiction.” RCW 36.70C.040(5). RCW 4.28.080 specifies that the mode of

service is “personal service.” That same statute further specifies that personal

service on a municipality must be made on one of the following persons: “the

mayor, city manager, or, during normal office hours, to the mayor’s or city

manager’s designated agent or the city clerk thereof.” RCW 4.28.080(2).

Additionally, LUPA requires a petitioner to file a petition for review within

21 days of the date of the land use decision. RCW 36.70C.040(3). This is a

“stringent” deadline. Asche v. Bloomquist, 132 Wn. App. 784, 795, 133 P.3d 475

(2006), review denied, 159 Wn.2d 1005 (2007). It reflects a strong public policy

of finality in land use decisions. Samuel’s Furniture Inc. v. Dep’t of Ecology, 147

Wn.2d 440, 458-59, 54 P.3d 1194 (2002). Even illegal land use decisions will be

allowed to stand if not timely challenged under LUPA. Habitat Watch v. Skagit

County, 155 Wn.2d 397, 407, 120 P.3d 56 (2005).

LUPA provides two mutually exclusive pathways for determining the date

a written decision is issued. RCW 36.70C.040(4)(a). The issuance of a written

decision is either “[t]hree days after a written decision is mailed by the local

jurisdiction or, if not mailed, the date on which the local jurisdiction provides

notice that a written decision is publicly available.” RCW 36.70C.040(4)(a). A

7
No. 88598-7-I/8

written decision that is “mailed” is considered “issued” three days after it is sent.

Chandrruangphen v. City of Sammamish, __Wn.3d __, 583 P.3d 604, 610

(2026). By contrast, LUPA expressly authorizes written decisions that are “not

mailed,” and the decision is considered “issued” on the date notice is provided

that a “decision is publicly available.” RCW 36.70C.040(4)(a).

In this case, Ezzeddine made two attempts to serve the City. While

Ezzeddine’s first attempt on April 2 was made within LUPA’s 21-day deadline, he

did not comply with the LUPA requirements because service was defective.

Ezzeddine did not follow the service requirement under RCW 4.28.080(2) in two

ways: he e-mailed, rather than personally served the petition; and the petition

was e-mailed to the wrong individuals because they were not the mayor, city

manager, or the mayor’s or city manager’s designated agent or the city clerk.

Ezzeddine’s second attempt on April 7 was outside the 21-day deadline.

The 21-day limitations period begins to run on the date a land use decision is

issued. RCW 36.70C.040(2), (3). For purposes of LUPA, when a decision is

“issued” depends on whether a decision is “written,” “made by ordinance or

resolution,” or, if neither of those options applies, “the date the decision is

entered into the public record.” RCW 36.70C.040(4)(a)-(c). On March 12, 2025,

the hearing examiner sent the decision to Ezzeddine by e-mail and regular mail.

Because the order was mailed, and not solely e-mailed, the date of

issuance was March 15, 2025. Chandrruangphen, 583 P.3d at 610 (concluding

LUPA’s three-day tolling provision does not apply to decisions transmitted solely

8
No. 88598-7-I/9

by e-mail). Twenty-one days after March 15 was April 6 not April 7, making

Ezzeddine’s second service attempt on April 7 untimely.

Ezzeddine’s land use petition is barred, and the court may not grant

review. RCW 36.70C.040(2). Our Supreme Court has stated that land use

decisions become unreviewable if not appealed to a superior court within LUPA’s

specified timeline. See Habitat Watch, 155 Wn.2d at 407. Trial court did not err in

granting summary judgment dismissal of Ezzeddine’s land use petition.

Ezzeddine requested an award of attorney fees, but he provides no

argument to support the awarding of fees and is not the prevailing party. 3 Thus,

his request is denied.

We affirm, and we deny Ezzeddine’s request for attorney fees.

WE CONCUR:

3 A party must “devote a section of its opening brief to the request for the fees or
expenses.” RAP 18.1(b). “Argument and citation to authority are required under the rule to advise
us of the appropriate grounds for an award of attorney fees as costs.” Wilson Ct. Ltd. P’ship v.
Tony Maroni’s, Inc., 134 Wn.2d 692, 710 n.4, 952 P.2d 590 (1998)). Requests that fail to comply
with these requirements are properly denied. Thompson v. Lennox, 151 Wn. App. 479, 485, 151
P.3d 597
(2009). Even if Ezzeddine complied with RAP 18.1(b), he is not the prevailing party,
thus fees would still be denied. RAP 18.1(a).

9

Named provisions

RCW 36.70C.040 LUPA

Get daily alerts for Washington Court of Appeals Opinions (CourtListener)

Daily digest delivered to your inbox.

Free. Unsubscribe anytime.

About this page

What is GovPing?

Every important government, regulator, and court update from around the world. One place. Real-time. Free. Our mission

What's from the agency?

Source document text, dates, docket IDs, and authority are extracted directly from WA Court of Appeals.

What's AI-generated?

The summary, classification, recommended actions, deadlines, and penalty information are AI-generated from the original text and may contain errors. Always verify against the source document.

Last updated

Classification

Agency
WA Court of Appeals
Filed
April 20th, 2026
Instrument
Enforcement
Branch
Judicial
Legal weight
Binding
Stage
Final
Change scope
Minor
Docket
88598-7

Who this affects

Applies to
Property owners Legal professionals
Industry sector
9211 Government & Public Administration
Activity scope
LUPA petition filing Land use appeal Administrative hearing
Geographic scope
Washington US-WA

Taxonomy

Primary area
Housing
Operational domain
Legal
Topics
Environmental Protection Judicial Administration

Get alerts for this source

We'll email you when Washington Court of Appeals Opinions (CourtListener) publishes new changes.

Free. Unsubscribe anytime.

You're subscribed!