FRA Repeals Bridge Load Capacity Evaluation Scheduling Requirement Under 49 CFR 237.71(e)
Summary
The Federal Railroad Administration (FRA) has issued a final rule removing 49 CFR 237.71(e), which required track owners to complete initial bridge load capacity determinations within five years of adopting a Bridge Management Program (BMP). The requirement was a transitional measure adopted when bridge safety regulations first became effective approximately 15 years ago. FRA determined the provision is now obsolete because the transitional compliance period has fully elapsed. All other bridge load capacity requirements in section 237.71 remain [unverified terminal claim removed], including the ongoing obligation for track owners to determine load capacity using appropriate engineering methods. The rule is classified as an E.O. 14192 deregulatory action with total costs expected to be less than zero. Three comments were received during the NPRM phase: a private citizen opposed the repeal, while BMWED and TTD supported it and recommended broader alignment with Federal Highway Administration bridge inspection practices through the Railroad Safety Advisory Committee.
“Removing this regulatory text removes an obsolete provision from the CFR, improving readability of this CFR part.”
About this source
GovPing monitors FR: Transportation Department for new transportation regulatory changes. Every update since tracking began is archived, classified, and available as free RSS or email alerts — 97 changes logged to date.
What changed
FRA removed paragraph (e) from 49 CFR 237.71, which had mandated that track owners complete initial bridge load capacity determinations within five years of adopting a Bridge Management Program under section 237.31. The removed text imposed scheduling restrictions on how track owners could organize their bridge evaluation processes. Paragraphs (f) through (h) were redesignated as (e) through (g), preserving the substantive requirements that bridge load capacity be determined when inspections reveal potentially adverse conditions, that capacity be expressed in terms compatible with transportation personnel, and that operations exceeding normal capacity be subject to railroad bridge engineer restrictions.
Railroad track owners and operators are directly affected by this repeal, which reduces regulatory scheduling constraints on bridge evaluation timing. The change does not affect the substantive obligation to determine bridge load capacity using appropriate engineering methods, nor does it affect FRA's oversight authority. Small entities are not expected to experience significant economic impact since the provision was already past its compliance window.
Archived snapshot
Apr 28, 2026GovPing captured this document from the original source. If the source has since changed or been removed, this is the text as it existed at that time.
Legal Status This site displays a prototype of a “Web 2.0” version of the daily
Federal Register. It is not an official legal edition of the Federal
Register, and does not replace the official print version or the official
electronic version on GPO’s govinfo.gov.
The documents posted on this site are XML renditions of published Federal
Register documents. Each document posted on the site includes a link to the
corresponding official PDF file on govinfo.gov. This prototype edition of the
daily Federal Register on FederalRegister.gov will remain an unofficial
informational resource until the Administrative Committee of the Federal
Register (ACFR) issues a regulation granting it official legal status.
For complete information about, and access to, our official publications
and services, go to About the Federal Register on NARA's archives.gov.
The OFR/GPO partnership is committed to presenting accurate and reliable
regulatory information on FederalRegister.gov with the objective of
establishing the XML-based Federal Register as an ACFR-sanctioned
publication in the future. While every effort has been made to ensure that
the material on FederalRegister.gov is accurately displayed, consistent with
the official SGML-based PDF version on govinfo.gov, those relying on it for
legal research should verify their results against an official edition of
the Federal Register. Until the ACFR grants it official status, the XML
rendition of the daily Federal Register on FederalRegister.gov does not
provide legal notice to the public or judicial notice to the courts.
Legal Status
Rule
You may be interested in this older document that published on 07/01/2025 with action 'Notice of proposed rulemaking (NPRM).' View Document
Repealing Certain Bridge Load Capacity Evaluation Requirements
A Rule by the Federal Railroad Administration on 04/28/2026
- 1.
1.
Document Details Published Content - Document Details Agencies Department of Transportation Federal Railroad Administration Agency/Docket Numbers Docket No. FRA-2025-0129 Notice No. 2 CFR 49 CFR 237 Document Citation 91 FR 22745 Document Number 2026-08254 Document Type Rule Pages 22745-22747
(3 pages) Publication Date 04/28/2026 RIN 2130-AD28 Published Content - Document DetailsPDF Official Content
- View printed version (PDF) Official Content
Document Details Published Content - Document Details Agencies Department of Transportation Federal Railroad Administration Agency/Docket Numbers Docket No. FRA-2025-0129 Notice No. 2 CFR 49 CFR 237 Document Citation 91 FR 22745 Document Number 2026-08254 Document Type Rule Pages 22745-22747
(3 pages) Publication Date 04/28/2026 RIN 2130-AD28 Published Content - Document DetailsDocument Dates Published Content - Document Dates Effective Date 2026-05-28 Dates Text This rule is effective May 28, 2026. Published Content - Document Dates
Table of Contents Enhanced Content - Table of Contents This table of contents is a navigational tool, processed from the
headings within the legal text of Federal Register documents.
This repetition of headings to form internal navigation links
has no substantive legal effect.-
-
-
-
-
- Executive Order 14192 (Unleashing Prosperity Through Deregulation)
- Executive Order 13272
-
-
- Executive Order 13175 (Tribal Consultation)
- 49 CFR Part 237
-
Enhanced Content - Table of Contents
Related Documents Enhanced Content - Related Documents FederalRegister.gov uses the agency dockets published with the document to display related documents.
| Notice No. 2
(166 Documents) |
| --- |
| Date | | Action | Title |
| | 2026-04-28 | Final rule. | Repealing Certain Bridge Load Capacity Evaluation Requirements |
| | 2026-04-28 | Final rule. | Miscellaneous Revisions to the Qualification and Certification of Conductors |
| | 2026-04-28 | Final rule. | Regulatory Relief To Allow Speeds Up to 45 MPH for Non-Traversable Curbs |
| | 2026-04-28 | Final rule. | Qualification and Certification of Locomotive Engineers |
| | 2026-04-28 | Final rule. | Removing Stenciling Requirement for Freight Cars Used for Tourist, Historic, Excursion, Educational, Recreational, or Private Purposes and Not Interchanged |
| | 2026-04-28 | Final rule. | Allowing for the Electronic Posting of Reportable Injuries and Occupational Illnesses |
| | 2026-04-28 | Final rule. | Qualification and Certification of Locomotive Engineers and Conductors: Incorporation of Longstanding C3RS Waivers |
| | 2026-04-28 | Final rule. | Prosecutorial Discretion of Enforcement Attorneys |
| | 2026-04-28 | Final rule. | Removal of Unnecessary and Outdated Paperwork Reduction Act References |
| | 2026-04-28 | Final rule. | Repealing a Track Surface Requirement |
| | 2026-04-24 | Final rule. | Amendments to the Federal Railroad Administration's Procedures for Service of Documents in Railroad Safety Enforcement Proceedings |
| | 2022-11-17 | Final rule. | Safety Glazing Standards; Codifying Existing Waivers and Adding Test Flexibility |
| | 2018-11-20 | Notice of Safety Advisory. | Safety Advisory Related to Temporary Signal Suspensions |
| | 2017-04-03 | Final rule. | Implementation of the Federal Civil Penalties Inflation Adjustment Act Improvements Act for a Violation of a Federal Railroad Safety Law, Federal Railroad Administration Safety Regulation or Order, or the Hazardous Material Transportation Laws or Regulations, Orders, Special Permits, and Approvals Issued Under Those Laws |
| | 2017-02-13 | Notice of proposed rulemaking (NPRM); reopening of comment period. | Passenger Equipment Safety Standards; Standards for Alternative Compliance and High-Speed Trainsets |
| | 2011-12-14 | Final rule. | Alternate Passenger Rail Service Pilot Program |
| | 2011-11-09 | Final rule. | Conductor Certification |
| | 2011-06-10 | Notice of meeting; postponement. | Northeast Corridor Safety Committee; Meeting Postponement |
| | 2010-07-27 | Final rule. | Inflation Adjustment of the Ordinary Maximum and Aggravated Maximum Civil Monetary Penalties for a Violation of the Hazardous Material Transportation Laws and Regulations |
| | 2009-11-13 | Removal of direct final rule provisions. | State Highway-Rail Grade Crossing Action Plans |
| | 2009-07-20 | Direct final rule; confirmation of effective date. | Miscellaneous Revisions to the Procedures for Handling Petitions for Emergency Waiver of Safety Regulations and the Procedures for Disqualifying Individuals From Performing Safety-Sensitive Functions |
| | 2007-10-19 | Final rule. | Locomotive Safety Standards; Sanders |
| | 2005-07-06 | Final Rule; Response to Petitions for Reconsideration. | Defect and Noncompliance Responsibility and Reports Defect and Noncompliance Notification |
| | 2004-10-28 | Final rule; correcting amendments. | Inflation Adjustment of the Maximum and Minimum Civil Monetary Penalties for Violation of a Railroad Safety Law or Regulation; Corrections |
| | 2004-03-16 | Final rule. | Railroad Locomotive Safety Standards: Clarifying Amendments; Headlights and Auxiliary Lights |
| | 2001-09-28 | Final Rule. | Signal and Train Control; Miscellaneous Amendments |
| | 2001-03-06 | Notice of public hearing. | Locomotive Cab Sanitation Standards |
| View More Docket Documents |
| Docket No. FRA-2025-0129
(2 Documents) |
| --- |
| Date | | Action | Title |
| | 2025-07-01 | Notice of proposed rulemaking (NPRM). | Repealing Certain Bridge Load Capacity Evaluation Requirements |
Enhanced Content - Related Documents
- Public Comments Enhanced Content - Public Comments This feature is not available for this document.
Enhanced Content - Public Comments
- Regulations.gov Data Enhanced Content - Regulations.gov Data Additional information is not currently available for this document.
Enhanced Content - Regulations.gov Data
- Sharing Enhanced Content - Sharing Shorter Document URL https://www.federalregister.gov/d/2026-08254 Email Email this document to a friend Enhanced Content - Sharing
- Print Enhanced Content - Print
- Enhanced Content - Print
- Other Formats Enhanced Content - Other Formats This document is also available in the following formats:
JSON Normalized attributes and metadata XML Original full text XML MODS Government Publishing Office metadata More information and documentation can be found in our developer tools pages.
Enhanced Content - Other Formats
- Public Inspection Public Inspection This PDF is FR Doc. 2026-08254 as it appeared on Public Inspection on
04/27/2026 at 8:45 am.
It was viewed
23
times while on Public Inspection.
If you are using public inspection listings for legal research, you
should verify the contents of the documents against a final, official
edition of the Federal Register. Only official editions of the
Federal Register provide legal notice of publication to the public and judicial notice
to the courts under 44 U.S.C. 1503 & 1507. Learn more here.
Public Inspection
Published Document: 2026-08254 (91 FR 22745) This document has been published in the Federal Register. Use the PDF linked in the document sidebar for the official electronic format.
Document Headings Document headings vary by document type but may contain
the following:
- the agency or agencies that issued and signed a document
- the number of the CFR title and the number of each part the document amends, proposes to amend, or is directly related to
- the agency docket number / agency internal file number
- the RIN which identifies each regulatory action listed in the Unified Agenda of Federal Regulatory and Deregulatory Actions See the Document Drafting Handbook for more details.
Department of Transportation
Federal Railroad Administration
- 49 CFR Part 237
- [Docket No. FRA-2025-0129; Notice No. 2]
- RIN 2130-AD28
AGENCY:
Federal Railroad Administration (FRA), Department of Transportation (DOT).
ACTION:
Final rule.
SUMMARY:
This rule eliminates the Federal requirement that defines the process a track owner must follow when scheduling the evaluation of bridges with no load capacity determination. The requirement was intended as a transitional measure to phase in compliance after the bridge safety regulations became effective and is no longer necessary because the regulations have been in effect for almost 15 years and the transitional period for compliance has ended.
DATES:
This rule is effective May 28, 2026.
FOR FURTHER INFORMATION CONTACT:
Yu-Jiang Zhang, Staff Director, FRA Track & Structures Division, FRA, telephone: (202) 570-1508, email: Yujiang.Zhang@dot.gov; or Aaron Moore, Senior Attorney, FRA, telephone: (202) 853-4784, email: Aaron.Moore@dot.gov.
SUPPLEMENTARY INFORMATION:
I. Background
Consistent with Executive Order (E.O.) 14192, Unleashing Prosperity Through Deregulation (90 FR 9065, Feb. 6, 2025), and E.O. 14219, Ensuring Lawful Governance and Implementing the President's “Department of Government Efficiency” Deregulatory Initiative (90 FR 10583, Feb. 25, 2025), FRA is reviewing its regulatory requirements in parts 200 through 299 of title 49, Code of Federal Regulations (CFR) and repealing requirements that are outdated and redundant.
On July 1, 2025, FRA published a notice of proposed rulemaking (NPRM) that proposed the elimination of the Federal requirement in 49 CFR part 237, Bridge Safety Standards, that defines the process a track owner must follow when scheduling the evaluation of bridges with no load capacity determination. ] This requirement was intended as a transitional measure to phase in compliance after the bridge safety regulations became effective. The restrictions on the track owner's discretion to determine the process for evaluation of bridge load capacity are no longer necessary because the regulations have been in effect for almost 15 years and the transitional period for compliance has ended.
FRA received three comments in response to the NPRM. A private citizen expressed concern about the degradation of American infrastructure, including failing bridges, and opposes this rule because the citizen asserted it may lead to bridge failure. The Brotherhood of Maintenance of Way Employes Division of the International Brotherhood of Teamsters (BMWED) and Transportation Trades Department, AFL-CIO (TTD) both submitted comments in support of this proposal. Though they recognized differences in operational and structural characteristics of railroad bridges and public highway bridges, BMWED and TTD encouraged the increased alignment of part 237 with bridge inspection and evaluation practices employed by the Federal Highway Administration, citing the incorporation of standardized inspection intervals, load rating protocols, and common protocols as potential areas for alignment. In addition, BMWED and TTD recommended a structured review of part 237 involving industry, labor, and government representatives through the Railroad Safety Advisory Committee (RSAC).
The commenters and FRA have the same goal, which is to support rail bridge infrastructure and to make sure that it can safely handle the weight of trains operating over bridges. This rule does not impact FRA's regulatory oversight over bridge load capacity requirements, but rather it removes an obsolete provision from the CFR. Specifically, the requirement to be repealed in 49 CFR 237.71 requires an initial determination of load capacity that must be completed within five years of the required date for adoption of the track owner's bridge management program (BMP). See section 237.71(e).
In this final rule, FRA is revising section 237.71 as proposed. As acknowledged by BMWED and TTD, this requirement was intended as a transitional measure to phase in compliance after the bridge safety regulations became effective and more than five years had elapsed from the required BMP adoption dates in section 237.31. All other bridge load capacity requirements in this section remain unchanged, including the requirement that each track owner must determine the load capacity of each of its railroad bridges as documented in the track owner's BMP using appropriate engineering methods and standards. In addition, FRA welcomes BMWED's and TTD's ideas about bridge load capacity regulation for other transportation modes and also agrees that RSAC may be the appropriate forum for the agency's various stakeholders to exchange information relating to the safety of rail operations.
II. Section-by-Section Analysis
Section 237.71 Determination of Bridge Load Capacities
This final rule removes the requirement in paragraph (e) that defines the process a track owner must follow when scheduling the evaluation of bridges with no load capacity determination. The existing requirement imposes a restriction on a track owner's ability to establish a BMP and evaluate bridge load capacity as the track owner sees fit. The existing regulation requires an initial determination of load capacity to be completed within five years of the required date for adoption of a BMP under section 237.31. Under the existing regulation, a period of more than five years has elapsed from the required adoption dates in section 237.31. This requirement was intended as a transitional measure to phase in compliance after the bridge safety regulations became effective. Removing this regulatory text removes an obsolete provision from the CFR, improving readability of this CFR part.
III. Regulatory Impact and Notices
A. Executive Order (E.O.) 12866 (Regulatory Planning and Review) and DOT Regulatory Policies and Procedures
FRA has considered the impact of this final rule under E.O. 12866 (58 FR ( printed page 22746) 51735, Oct. 4, 1993), Regulatory Planning and Review, and DOT Regulatory Policies and Procedures. The Office of Information and Regulatory Affairs within the Office of Management and Budget (OMB) determined that this final rule is not a significant regulatory action under section 3(f) of E.O. 12866.
FRA analyzed the potential costs and benefits of this final rule. This final rule removes obsolete requirements, and therefore it imposes no additional burdens on regulated entities. Moreover, implementing this rule will provide benefits, improving readability of this CFR part.
B. Executive Order 14192 (Unleashing Prosperity Through Deregulation)
E.O. 14192, Unleashing Prosperity Through Deregulation, requires that for “each new [E.O. 14192 regulatory action] issued, at least ten prior regulations be identified for elimination.” ] Implementation guidance for E.O. 14192 issued by OMB (Memorandum M-25-20, Mar. 26, 2025) defines two different types of E.O. 14192 actions: an E.O. 14192 deregulatory action, and an E.O. 14192 regulatory action. ]
An E.O. 14192 deregulatory action is defined as “an action that has been finalized and has total costs less than zero.” FRA determined that issuing this final rule is expected to have total costs less than zero, and therefore this final rule is considered an E.O. 14192 deregulatory action.
C. Regulatory Flexibility Act and Executive Order 13272
The Regulatory Flexibility Act (5 U.S.C. 601 et seq.), as amended by the Small Business Regulatory Enforcement Fairness Act of 1996, ] requires Federal agencies to consider the effects of the regulatory action on small entities and to minimize any significant economic impact. Accordingly, DOT policy requires an analysis of the impact of all regulations on small entities and mandates that agencies strive to lessen any adverse effects on these businesses. The term small entities encompasses small businesses, not-for-profit organizations that are independently owned and operated and are not dominant in their fields, and governmental jurisdictions with populations of less than 50,000 (5 U.S.C. 601(6)).
A regulatory flexibility analysis is not required, however, if the head of an Agency or an appropriate designee certifies that the rule will not have a significant economic impact on a substantial number of small entities. This final rule would not preclude small entities from continuing practices that comply with part 237 as amended; it merely removes obsolete provisions from the CFR and improves readability. Consequently, FRA certifies that this final rule will not have a significant economic impact on a substantial number of small entities.
D. Paperwork Reduction Act
This final rule offers regulatory flexibilities, and it contains no new information collection requirements, in accordance with the Paperwork Reduction Act of 1995, 44 U.S.C. 3501 et seq., and therefore, an information collection submission to OMB is not required. OMB approved the existing recordkeeping and reporting requirements contained in part 237 on April 1, 2026. The OMB control number is 2130-0586, and OMB approval expires on April 30, 2029.
E. Environmental Assessment
FRA has analyzed this rule for the purposes of the National Environmental Policy Act of 1969 (NEPA). In accordance with 42 U.S.C. 4336 and DOT NEPA Order 5610.1D, FRA has determined that this rule is categorically excluded pursuant to 23 CFR 771.116(c)(15). This rulemaking is not anticipated to result in any environmental impacts, and there are no unusual or extraordinary circumstances present in connection with this rulemaking.
F. Federalism Implications
This final rule will not have a substantial effect on the States, on the relationship between the national government and the States, or on the distribution of power and responsibilities among the various levels of government. Thus, in accordance with E.O. 13132, Federalism (64 FR 43255, Aug. 10, 1999), preparation of a Federalism Assessment is not warranted.
G. Unfunded Mandates Reform Act of 1995
This final rule will not result in the expenditure, in the aggregate, of $100,000,000 or more, adjusted for inflation, in any one year by State, local, or Indian Tribal governments, or the private sector. Thus, consistent with section 202 of the Unfunded Mandates Reform Act of 1995 (Pub. L. 104-4, 2 U.S.C. 1532), FRA is not required to prepare a written statement detailing the effect of such an expenditure.
H. Energy Impact
E.O. 13211 requires Federal agencies to prepare a Statement of Energy Effects for any “significant energy action.” ] FRA has evaluated this final rule in accordance with E.O. 13211 and determined that this final rule is not a “significant energy action” within the meaning of E.O. 13211.
I. Executive Order 13175 (Tribal Consultation)
FRA has evaluated this final rule in accordance with the principles and criteria contained in E.O. 13175, Consultation and Coordination with Indian Tribal Governments (65 FR 67249, Nov. 6, 2000). The final rule will not have a substantial direct effect on one or more Indian tribes, will not impose substantial direct compliance costs on Indian tribal governments, and will not preempt tribal laws. Therefore, the funding and consultation requirements of E.O. 13175 do not apply, and a tribal summary impact statement is not required.
J. International Trade Impact Assessment
The Trade Agreement Act of 1979 prohibits Federal agencies from engaging in any standards or related activities that create unnecessary obstacles to the foreign commerce of the United States. Legitimate domestic objectives, such as safety, are not considered unnecessary obstacles. The statute also requires consideration of international standards and, where appropriate, that they be the basis for U.S. standards. This final rule is purely domestic in nature and is not expected to affect trade opportunities for U.S. firms doing business overseas or for foreign firms doing business in the United States.
List of Subjects in 49 CFR Part 237
- Bridges
- Penalties
- Railroad safety
- Reporting and recordkeeping requirements
The Final Rule
For the reasons discussed in the preamble, FRA amends part 237 of chapter II, subtitle B of title 49, Code of Federal Regulations as follows:
( printed page 22747)
PART 237—BRIDGE SAFETY STANDARDS
- The authority citation for part 237 continues to read as follows:
Authority: 49 U.S.C. 20102-20114; 28 U.S.C. 2461 note; and 49 CFR 1.89.
- Amend § 237.71 by removing paragraph (e) and redesignating paragraphs (f) through (h) as paragraphs (e) through (g) to read as follows:
Determination of bridge load capacities. * * * * * (e) Where a bridge inspection reveals that, in the determination of the railroad bridge engineer, the condition of a bridge or a bridge component might adversely affect the ability of the bridge to carry the traffic being operated, a new capacity shall be determined.
(f) Bridge load capacity may be expressed in terms of numerical values related to a standard system of bridge loads, but shall in any case be stated in terms of weight and length of individual or combined cars and locomotives, for the use of transportation personnel.
(g) Bridge load capacity may be expressed in terms of both normal and maximum load conditions. Operation of equipment that produces forces greater than the normal capacity shall be subject to any restrictions or conditions that may be prescribed by a railroad bridge engineer.
Issued in Washington, DC, under authority delegated in 49 CFR 1.89.
David A. Fink,
Administrator.
Footnotes
- 90 FR 28669 (July 1, 2025).
2.
Executive Office of the President, Executive Order 14192 of January 31, 2025, Unleashing Prosperity Through Deregulation, 90 FR 9065-9067 (Feb. 6, 2025).
3.
Executive Office of the President, Office of Management and Budget, Guidance Implementing Section 3 of Executive Order 14192, Titled “Unleashing Prosperity Through Deregulation,” Memorandum M-25-20 (Mar. 26, 2025).
Pub. L. 104-121, 110 Stat. 857 (Mar. 29, 1996).
66 FR 28355 (May 22, 2001).
[FR Doc. 2026-08254 Filed 4-27-26; 8:45 am]
BILLING CODE 4910-06-P
Published Document: 2026-08254 (91 FR 22745)
CFR references
Named provisions
Mentioned entities
Related changes
Get daily alerts for FR: Transportation Department
Daily digest delivered to your inbox.
Free. Unsubscribe anytime.
Source
About this page
Every important government, regulator, and court update from around the world. One place. Real-time. Free. Our mission
Source document text, dates, docket IDs, and authority are extracted directly from Transportation Department.
The summary, classification, recommended actions, deadlines, and penalty information are AI-generated from the original text and may contain errors. Always verify against the source document.
Classification
Who this affects
Taxonomy
Browse Categories
Get alerts for this source
We'll email you when FR: Transportation Department publishes new changes.
Subscribed!
Optional. Filters your digest to exactly the updates that matter to you.