Shipbuilding Programs Billions Over Cost, Behind Schedule

Favicon for www.gao.gov GAO Reports
Published
Detected
Email

Summary

GAO testified before Congress on April 22, 2026, documenting persistent cost overruns and schedule delays in Navy and Coast Guard shipbuilding programs over two decades. The Navy's Constellation class frigate program suffered significant issues leading to a strategic shift away from the program in 2025 after exercising contract options worth over $3 billion. The Coast Guard paused work on two Offshore Patrol Cutter ships and terminated two others following a more than 5-year delay on the lead ship. GAO made two new recommendations to DOD requiring assessment of full submarine industrial base investment needs and documented oversight of existing investments exceeding $10 billion.

“For example, DOD does not know how much funding it expects to need—beyond the more than $10 billion DOD already invested—to solve submarine industrial base challenges such as ensuring needed parts get delivered on time.”

GAO , verbatim from source
Published by GAO on gao.gov . Detected, standardized, and enriched by GovPing. Review our methodology and editorial standards .

About this source

The Government Accountability Office is Congress's investigative arm. GAO reports audit federal programs, evaluate agency spending, review legal compliance with statutes, and rule on bid protests against federal contract awards. This feed tracks every new report and decision as it is published, around 60 a month. Reports often drive Congressional oversight hearings and statutory amendments. Recent reports cover unobligated federal budget authority, FEMA program effectiveness, and Medicare fraud prevention numbers. Watch this if you manage a federal program, advise agencies on compliance, follow federal contract protests, or research federal operations for private-sector or academic purposes.

What changed

GAO submitted congressional testimony summarizing its decades of reporting on Navy and Coast Guard shipbuilding challenges. The report highlights that shipbuilding programs have consistently fallen short, with the Constellation class frigate program overcome by issues leading to a strategic shift in 2025 after exercising contract options worth over $3 billion, and the Coast Guard's Offshore Patrol Cutter program experiencing a more than 5-year delay on the lead ship. DOD has invested more than $10 billion in submarine industrial base without knowing full future funding needs. GAO made two new recommendations to DOD regarding assessing full investment needs and documenting oversight processes for submarine industrial base investments. Prior unimplemented recommendations include 92 to the Navy and 45 to the Coast Guard since 2016.

Affected parties including DOD, the Navy, Coast Guard, and submarine industrial base contractors should note that GAO will continue monitoring agency progress on its more than 100 total recommendations. DOD agreed with the two new recommendations, signaling potential future compliance obligations around investment assessment and documented oversight processes for submarine construction investments.

Archived snapshot

Apr 23, 2026

GovPing captured this document from the original source. If the source has since changed or been removed, this is the text as it existed at that time.

GAO-26-109068 Published: Apr 22, 2026. Publicly Released: Apr 22, 2026.

Fast Facts

We testified before Congress on Navy and Coast Guard shipbuilding challenges.

Our testimony is largely based on:

Shipbuilding and Repair: Navy Needs a Strategic Approach for Private Sector Industrial Base Investments

Offshore Patrol Cutter: Coast Guard Should Gain Key Knowledge Before Buying More Ships

Navy Shipbuilding: Increased Use of Leading Design Practices Could Improve Timeliness of Deliveries

Additionally, we shared preliminary observations from our ongoing work about the timeliness and cost of Navy and Coast Guard shipbuilding efforts, and the shipbuilding trades workforce. Further, we reviewed Department of Defense and Navy investments in strengthening the submarine-building industry and recommended that DOD address issues we found.

We also reported on the Navy and Coast Guard's progress in addressing our prior shipbuilding recommendations.

The U.S. Capitol building with the text, GAO Testimony to Congress.

Highlights

What GAO Found

Navy and Coast Guard shipbuilding programs have consistently fallen short of expectations over the last 2 decades. Collectively, they are billions of dollars over cost and years behind schedule. For example, the Navy’s Constellation class frigate program was overcome by issues. As a result, the Navy announced a strategic shift away from the program in 2025—having previously exercised contract options valued at over $3 billion dollars. Similarly, the Coast Guard paused work on two ships and terminated two other ships in its Offshore Patrol Cutter program after a more than 5-year delay in delivering the lead ship.

Constellation Class Frigate and Offshore Patrol Cutter

Proposed solutions by federal officials have included reorganizing how shipbuilding programs are managed, increasing shipbuilder workforce wages, and finalizing ship designs before beginning construction, among others. While there is no singular solution, implementing leading practices and GAO’s prior recommendations could help ensure smoother sailing.

For example, ensuring that new ship design efforts, such as the Navy’s planned new attack submarine program, fully leverage ship design practices used by leading companies will be critical to long-term success. This would include practices like iterative design based on user feedback, completing ship design before beginning construction, and using digital tools. (See GAO-24-105503.)

Additionally, the shipbuilding industrial base—the private companies that build or supply the parts for ships—has not met the government’s submarine construction goals in recent years. GAO’s analysis of the Department of Defense’s (DOD) efforts to invest in the submarine industrial base to improve its capacity found shortcomings. For example, DOD does not know how much funding it expects to need—beyond the more than $10 billion DOD already invested—to solve submarine industrial base challenges such as ensuring needed parts get delivered on time. Without this understanding, decision-makers may not have the information needed to balance funding for the submarine industrial base with other shipbuilding priorities. Further, DOD has not taken key steps to ensure oversight for some of its costliest submarine industrial base investments. Without improvements, such as documented project monitoring, DOD cannot ensure those taxpayer dollars are helping achieve its goals as cost effectively as possible. These findings can provide lessons learned for the Navy, Coast Guard, and other federal agencies in their efforts to build up the maritime industrial base.

Why GAO Did This Study

The U.S. is in a period of heightened emphasis on improving shipbuilding to tackle pressing national security demands. The Navy and Coast Guard spend billions to procure ships each year and have ambitious plans to build new ships. GAO has reported for decades on the persistent issues that plague these shipbuilding programs and has made more than 100 recommendations to address them.

This statement addresses (1) the state of Navy and Coast Guard shipbuilding; (2) key challenges the Navy and Coast Guard need to address to achieve their ambitious shipbuilding goals; and (3) DOD’s efforts to support the submarine industrial base and the lessons that can be derived for future maritime industrial base investments.

This statement is based on prior and ongoing GAO work. In addition, GAO is issuing the results of its analysis of DOD’s management of submarine industrial base investments in this testimony statement. To perform this work, GAO analyzed relevant Navy and Coast Guard documentation and interviewed knowledgeable officials.

Recommendations

GAO is making two new recommendations to DOD to assess the full scope of investments needed to expand the submarine industrial base in support of the Navy’s construction goals and to improve oversight of these investments. DOD agreed with our recommendations.

Additionally, since 2016, GAO has made 92 recommendations to the Navy and 45 to the Coast guard to help improve their shipbuilding programs. Of these, many have yet to be addressed. GAO will continue to monitor each agency's progress in addressing the recommendations.

Recommendations for Executive Action

Agency Affected Recommendation Status
Department of Defense The Secretary of Defense should ensure that the Submarine Direct Reporting Portfolio Manager assesses the full cost and schedule of investments expected to be needed to expand the submarine industrial base to a state that it can support the Navy's submarine construction goal of producing one Columbia and two Virginia class submarines annually. (Recommendation 1) Open When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
Department of Defense The Secretary of Defense should ensure that the Submarine Direct Reporting Portfolio Manager and the Under Secretary of Defense for Acquisition and Sustainment consistently document and implement oversight processes for all submarine industrial base investments. (Recommendation 2) Open When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.

Full Report

View Full Report Online

Highlights Page (1 page)

Full Report (39 pages)

GAO Contacts

Shelby S. Oakley Director Contracting and National Security Acquisitions oakleys@gao.gov

Media Inquiries

Sarah Kaczmarek Managing Director Office of Public Affairs media@gao.gov

Public Inquiries

Contact Us

Topics

National Defense Military forces Industrial base Submarines Shipbuilding Navy ships Construction Naval shipyard Contractor performance Labor force Cost and schedule

Get daily alerts for GAO Reports

Daily digest delivered to your inbox.

Free. Unsubscribe anytime.

About this page

What is GovPing?

Every important government, regulator, and court update from around the world. One place. Real-time. Free. Our mission

What's from the agency?

Source document text, dates, docket IDs, and authority are extracted directly from GAO.

What's AI-generated?

The summary, classification, recommended actions, deadlines, and penalty information are AI-generated from the original text and may contain errors. Always verify against the source document.

Last updated

Classification

Agency
GAO
Published
April 22nd, 2026
Instrument
Notice
Branch
Executive
Legal weight
Non-binding
Stage
Final
Change scope
Minor
Document ID
GAO-26-109068

Who this affects

Applies to
Government agencies Defense contractors
Industry sector
3364 Aerospace & Defense
Activity scope
Defense procurement oversight Industrial base investment monitoring
Geographic scope
United States US

Taxonomy

Primary area
Defense & National Security
Operational domain
Compliance
Topics
Defense & National Security

Get alerts for this source

We'll email you when GAO Reports publishes new changes.

Free. Unsubscribe anytime.

You're subscribed!