Changeflow GovPing Government & Legislation NRC Consults on Duke Energy Belews Creek Nuclea...
Routine Consultation Added Consultation

NRC Consults on Duke Energy Belews Creek Nuclear Site EIS

Favicon for www.regulations.gov Regulations.gov Final Notices
Detected
Email

Summary

The U.S. Nuclear Regulatory Commission is initiating a 30-day public scoping period to gather input on the scope of an Environmental Impact Statement for Duke Energy Carolinas LLC's application for an Early Site Permit at the Belews Creek, NC site. Comments are due by June 8, 2026. The U.S. Army Corps of Engineers is serving as a cooperating agency in the NEPA review process.

“The public may submit comments on the scope of the EIS by June 8, 2026.”

NRC , verbatim from source
Published by NRC on regulations.gov . Detected, standardized, and enriched by GovPing. Review our methodology and editorial standards .

About this source

This feed pulls every final notice posted to regulations.gov across all federal agencies, around 240 a month. Final notices are the binding step in the federal rulemaking cycle: a final rule, a no-action determination, a self-regulatory organization rule change, or a procedural notice that takes effect on publication. Watch this for the actionable end of the rulemaking pipeline rather than the proposed-and-comment phase. GovPing publishes each notice with the issuing agency, docket ID, effective date where stated, and document type. Recent examples include Nasdaq ISE auction rule changes and an NYSE proposal enabling tokenized securities trading under the DTC pilot.

What changed

The NRC is seeking public comments on the scope of an Environmental Impact Statement for Duke Energy Carolinas' Early Site Permit application at Belews Creek, NC. Duke Energy submitted the application on December 30, 2025, under 10 CFR Part 52, proposing to use a plant parameter envelope approach for potential multiple nuclear reactor construction at the site in Stokes and Forsyth Counties. This scoping notice initiates the public participation process required under NEPA and 10 CFR 51.29.

Organizations with interests in nuclear development, environmental review, or North Carolina energy infrastructure should monitor this proceeding. While the scoping process does not create immediate compliance obligations, participation now may influence the scope of environmental analysis and issues addressed in the eventual draft EIS.

Archived snapshot

Apr 28, 2026

GovPing captured this document from the original source. If the source has since changed or been removed, this is the text as it existed at that time.

Content

ACTION:

Notice; request for comment.

SUMMARY:

Pursuant to the National Environmental Policy Act (NEPA) of 1969, the U.S. Nuclear Regulatory Commission (NRC) announces its
intent

to prepare an environmental impact statement (EIS) to evaluate the potential environmental impacts associated with Duke Energy
Carolinas, LLC (DEC) application for an Early Site Permit (ESP) for the Belews Creek, NC, site in Sauratown Township, Stokes
County, North Carolina, and Belews Creek Township, Forsyth County, North Carolina. The NRC is initiating a 30-day public scoping
period to gather input on the scope of the EIS. The U.S. Army Corps of Engineers is a cooperating agency, while the NRC will
be the lead Federal agency.

DATES:

The public may submit comments on the scope of the EIS by June 8, 2026. Comments received after this date will be considered
if it is practical to do so, but the NRC is able to ensure consideration only for comments received on or before this date.
Further information regarding the proposed applications can be found in Section V of this notice, “Virtual Project Information
and Engagement.”

ADDRESSES:

You may submit comments by any of the following methods; however, the NRC encourages electronic comment submission through
the Federal rulemaking website:

Federal rulemaking website: Go to https://regulations.gov and search for Docket ID NRC-2025-2161. Address questions about Docket IDs in Regulations.gov to Bridget Curran; telephone: 301-415-1003; email: Bridget.Curran@nrc.gov. For technical questions, contact the individual listed in the “For Further Information Contact” section of this document.

Email: Comments may be submitted to the NRC electronically using the email address BelewsCreekEnvironmental@nrc.gov.

Mail comments to: Office of Administration, Mail Stop: TWFN-5-A85, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, ATTN: Program
Management, Announcements and Editing Staff.

For additional direction on obtaining information and submitting comments, see “Obtaining Information and Submitting Comments”
in the
SUPPLEMENTARY INFORMATION
section of this document.

FOR FURTHER INFORMATION CONTACT:

William Burris, Office of Nuclear Material Safety and Safeguards, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001;
telephone: 301-415-1621; email: William.Burris@nrc.gov.

SUPPLEMENTARY INFORMATION:

I. Obtaining Information and Submitting Comments

A. Obtaining Information

Please refer to Docket ID NRC-2025-2161 when contacting the NRC about the availability of information regarding this document.
You may obtain publicly available information related to this document using any of the following methods:

Federal rulemaking website: Go to https://regulations.gov and search for Docket ID NRC-2025-2161.

NRC's Agencywide Documents Access and Management System (ADAMS): You may obtain publicly available documents online in the ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select “Begin ADAMS Public Search.” For problems with ADAMS, please contact the NRC's Public Document
Room (PDR) reference staff at 1-800-397-4209, at 301-415-4737, or by email to PDR.resource@nrc.gov. The ADAMS accession number for each document referenced in this document (if it is available in ADAMS) is provided the first
time that it is referenced.

NRC's PDR: The PDR, where you may examine and order copies of publicly available documents, is open by appointment. To make an appointment
to visit the PDR, please send an email to PDR.Resource@nrc.gov or call 1-800-397-4209 or 301-415-4737, between 8 a.m. and 4 p.m. eastern time, Monday through Friday, except Federal holidays.

NRC Public Project Website: Information regarding the project and engagement opportunities, is available at https://www.nrc.gov/reactors/new-reactors/advanced/who-were-working-with/applicant-projects/dukeenergy.

• The NRC encourages electronic comment submission through the Federal rulemaking website (https://www.regulations.gov). Please include Docket ID NRC-2025-2161 in the subject line of your comment submission in order to ensure that the NRC is
able to make your comment submission available to the public in this docket.

The NRC cautions you not to include identifying or contact information that you do not want to be publicly disclosed in your
comment submission. The NRC will post all comment submissions at https://www.regulations.gov as well as enter the comment submissions into ADAMS. The NRC does not routinely edit comment submissions to remove identifying
or contact information.

If you are requesting or aggregating comments from other persons for submission to the NRC, then you should inform those persons
not to include identifying or contact information that they do not want to be publicly disclosed in their comment submission.
Your request should state that the NRC does not routinely edit comment submissions to remove such information before making
the comment submissions available to the public or entering the comment into ADAMS.

II. Discussion

By letter dated December 30, 2025, (ADAMS Package Accession No. ML25364A004), DEC submitted to the NRC in accordance with
part 52 of title 10 of the Code of Federal Regulations (10 CFR), Subpart A, “Early Site Permits (ESP),” an application for an ESP to approve the Belews Creek, NC, site for future
construction of multiple nuclear reactors. DEC has not selected a reactor technology to be built at the project site and used
a plant parameter envelope approach. This submission initiated the NRC's proposed action of determining whether to grant the
ESP.

In accordance with 10 CFR 51.50(a), DEC submitted an environmental report (ER) as part of the ESP application. The ER was
prepared pursuant to 10 CFR part 51 and is publicly available in ADAMS under Accession No. ML25364A006. The ER will also be
available for viewing at https://www.nrc.gov/reactors/new-reactors/advanced/who-were-working-with/applicant-projects/dukeenergy.

The ER includes a discussion of the purpose of the project and alternatives.

The NRC staff determined that DEC submitted an application in accordance with 10 CFR part 52, and that the application is
acceptable for docketing under Docket No. 52-055. The NRC sent a letter of acceptance and docketing to DEC on February 8,
2026, (ADAMS Accession No. ML26016A624). A notice of acceptance for docketing of the application and notice of hearing were
published in the
Federal Register
on February 9, 2025, (91 FR 5787). These notices are available on the Federal rulemaking website (https://www.regulations.gov) by searching for Docket ID NRC-2025-2161.

The NRC is the lead Federal agency for the NEPA process for the proposed action. The NRC may invite any Federal, State, Tribal,
or local agency that has jurisdiction by law or special expertise with respect to any environmental impact involved in a proposal
to become cooperating agencies in the preparation of the EIS for the proposed

action. As such, the U.S Corps of Engineers is a cooperating agency.

The Council for Environmental Quality Identification for this EIS is EISX-429-00-000-1773367293.

III. Request for Comment

This notice informs the public of the NRC's intent to conduct environmental scoping and prepare an EIS for the NRC's review
of the ESP application for Belews Creek, NC, site and to provide the public an opportunity to participate in the environmental
scoping process, in accordance with 10 CFR 51.29, “Scoping-environmental impact statement and supplement to environmental
impact statement,” and 10 CFR 51.116, “Notice of intent.”

The regulations in 36 CFR 800.8, “Coordination with the National Environmental Policy Act,” allow agencies to use their NEPA
process to fulfill the requirements of Section 106 of the National Historic Preservation Act of 1966 (54 U.S.C. 300101, et seq.) (NHPA). Therefore, pursuant to 36 CFR 800.8(c), the NRC intends to use its process and documentation required for the preparation
of the EIS on the proposed action to comply with Section 106 of the NHPA, in lieu of the procedures set forth at 36 CFR 800.3
through 800.6.

The NRC intends to gather the information necessary to prepare an EIS related to the ESP application for the Belews Creek,
NC, site. The NRC is required by 10 CFR 51.20(b) to prepare an EIS in connection with the issuance of an ESP for a power reactor.
This notice is being published in accordance with NEPA and the NRC's regulations at 10 CFR part 51.

The NRC will evaluate the environmental impacts of construction, operation and decommissioning of a nuclear power facility
at the Belews Creek, NC, site, and alternatives thereto.

As part of its environmental review, the NRC will first conduct a scoping process and, as soon as practicable thereafter,
will prepare a draft EIS for public comment. Participation in this scoping process by members of the public and local, State,
Tribal, and Federal government agencies is encouraged. The scoping process for the draft EIS will be used to accomplish the
following:

a. Define the proposed action that is to be the subject of the EIS;

b. Determine the scope of the EIS and identify the significant issues to be analyzed in depth;

c. Identify and eliminate from detailed study those issues that are peripheral or are not significant or that have been covered
by prior environmental review;

d. Identify any environmental assessments and other ElSs that are being or will be prepared that are related to, but are not
part of, the scope of the EIS under consideration;

e. Identify other environmental review and consultation requirements related to the proposed action;

f. Indicate the relationship between the timing of the preparation of the environmental analyses and the NRC's tentative planning
and decision-making schedule;

g. Identify any cooperating agencies and, as appropriate, allocate assignments for preparation and schedules for completing
the EIS to the NRC and any cooperating agencies; and

h. Describe how the EIS will be prepared, including any contractor assistance to be used.

The NRC invites the following entities to participate in scoping:

a. The applicant, Duke Energy Carolina, LLC;

b. Any Federal agency that has jurisdiction by law or special expertise with respect to any environmental impact involved
or that is authorized to develop and enforce relevant environmental standards;

c. Affected State and local government agencies, including those authorized to develop and enforce relevant environmental
standards;

d. Any affected Indian Tribe;

e. Any person who requests or has requested an opportunity to participate in the scoping process; and

f. Any person who has petitioned or intends to petition for leave to intervene under 10 CFR 2.309.

IV. Virtual Project Information and Engagement

The NRC is announcing that it will maintain project information and engagement opportunities for the DEC Belews Creek ESP
application located at the NRC project website at https://www.nrc.gov/reactors/new-reactors/advanced/who-were-working-with/applicant-projects/dukeenergy. Project information and stakeholder engagement will include: (1) an overview by the NRC of the environmental review process,
the proposed scope of the DEC Belews Creek project, and the proposed environmental review schedule; and (2) information regarding
the opportunity for interested government agencies, organizations, and individuals to submit comments or suggestions on environmental
issues or the proposed scope of the EIS.

Participation in the scoping process for the Belews Creek ESP EIS does not entitle participants to become parties to the proceeding
to which the EIS relates. Matters related to participation in any hearing are outside the scope of matters to be discussed
as part of the EIS process.

Authority: 42 U.S.C. 2011 et seq.

Dated: April 23, 2026. For the Nuclear Regulatory Commission.

Daniel Barnhurst, Chief, Environmental Project Management Branch, Division of Rulemaking, Environmental, and Financial Support, Office of Nuclear
Material Safety and Safeguards. [FR Doc. 2026-08155 Filed 4-24-26; 8:45 am] BILLING CODE 7590-01-P

Download File

Download

CFR references

10 CFR Part 52 10 CFR 51.50(a) 10 CFR 51.29 10 CFR 51.116 10 CFR 51.20(b)

Citations

10 CFR Part 52 Early Site Permit application requirements
10 CFR 51.50(a) Environmental report submission requirement
10 CFR 51.29 Scoping process requirements for EIS
10 CFR 51.116 Notice of intent requirements
36 CFR 800.8 NEPA/NHPA coordination provision
42 U.S.C. 2011 NRC statutory authority

Get daily alerts for Regulations.gov Final Notices

Daily digest delivered to your inbox.

Free. Unsubscribe anytime.

About this page

What is GovPing?

Every important government, regulator, and court update from around the world. One place. Real-time. Free. Our mission

What's from the agency?

Source document text, dates, docket IDs, and authority are extracted directly from NRC.

What's AI-generated?

The summary, classification, recommended actions, deadlines, and penalty information are AI-generated from the original text and may contain errors. Always verify against the source document.

Last updated

Classification

Agency
NRC
Comment period closes
June 8th, 2026 (41 days)
Instrument
Consultation
Branch
Executive
Legal weight
Non-binding
Stage
Consultation
Change scope
Minor
Document ID
91 FR 5787
Docket
NRC-2025-2161 52-055

Who this affects

Applies to
Energy companies
Industry sector
2211.1 Nuclear Energy
Activity scope
Nuclear site permitting Environmental impact assessment Public comment process
Geographic scope
United States US

Taxonomy

Primary area
Energy
Operational domain
Compliance
Topics
Environmental Protection

Get alerts for this source

We'll email you when Regulations.gov Final Notices publishes new changes.

Free. Unsubscribe anytime.

You're subscribed!