Siouxland Ethanol Construction Permit, Air Quality, Jackson Nebraska

Favicon for dee.nebraska.gov Nebraska DWEE Announcements
Published
Detected
Email

Summary

NDWEE proposes to issue a construction permit to Siouxland Ethanol LLC for an anhydrous ethanol manufacturing plant in Jackson, NE. The proposed permit would allow removal of TO/HRSG equipment and implementation of operational limitations for the CTG bypass stack, with net emissions changes including a 36.30 tpy increase in NOx and net decreases in PM, SO2, CO, VOC, and HAP.

What changed

NDWEE is proposing to issue a construction permit to Siouxland Ethanol LLC (FID 85434), an anhydrous ethanol manufacturing plant located at 1501 Knox Boulevard, Jackson, NE. The permit would allow removal of the TO/HRSG (C10A), removal of the HRSG (S130) fresh air firing operational limitation, and implementation of an operational limitation for the CTG bypass stack (S120). Projected emissions changes include: 36.30 tpy NOx increase, -0.83 tpy PM, -0.84 tpy PM10, -0.84 tpy PM2.5, -0.05 tpy SO2, -6.68 tpy CO, -5.31 tpy VOCs, and -0.16 tpy total HAP.

Manufacturers and energy companies in Nebraska should be aware that the public comment period runs through April 24, 2026. Interested parties may request a public hearing in writing, stating the nature of issues and supporting arguments. All Nebraska counties currently meet NAAQS standards. The permit and supporting materials are available at NDWEE offices in Lincoln or electronically at dwee.nebraska.gov.

What to do next

  1. Submit written comments to NDWEE by April 24, 2026
  2. Request a public hearing in writing if desired, stating issues and supporting arguments
  3. Contact dwee.airquality@nebraska.gov or (402) 471-2186 for details

Archived snapshot

Apr 10, 2026

GovPing captured this document from the original source. If the source has since changed or been removed, this is the text as it existed at that time.

Program Name Air Quality Program FID 85434 Location 1501 Knox Boulevard, Jackson, Dakota County, Nebraska 68743 Nearest City Jackson Link to Public Notice Documents Public Notice Documents Link to view all program documents All Program Documents May be slow to load depending on the number of documents

Permit Type Construction Comment Start Date

26 March 2026

End of Comment Period

24 April 2026

PUBLIC NOTICE

Nebraska Department of Water, Energy, and Environment

Permitting and Engineering Division

Notice is given to the public, according to Chapter 10 of Nebraska Administrative Code Title 129 - Nebraska Air Quality Regulations, that the Department is proposing to issue a construction permit to Siouxland Ethanol, LLC (FID 85434), an anhydrous ethanol manufacturing plant (Standard Industrial Classification 2869 – Industrial Organic Chemicals, Not Elsewhere Classified) located at 1501 Knox Boulevard, Jackson, Dakota County, Nebraska. The anticipated change in emissions of regulated air contaminants in tons per year (tpy) due to the proposed construction ** at this facility will be: -0.83 tpy of Particulate Matter (PM); -0.84 tpy of PM ≤ 10 microns (PM 10); -0.84 tpy PM ≤ 2.5 microns (PM 2.5); -0.05 tpy Sulfur Dioxide; 36.30 tpy Oxides of Nitrogen; -6.68 tpy Carbon Monoxide; -5.31 tpy Volatile Organic Compounds; and -0.16 tpy total Hazardous Air Pollutants (HAP).

All Counties in Nebraska currently meet the National Ambient Air Quality Standards (NAAQS) for those pollutants subject to a NAAQS. There are currently no Counties classified as being in non-attainment with the State Total Reduced Sulfur (TRS) standards. It is the source’s responsibility to ensure no take of threatened or endangered species results from the proposed hammermill project.

The Department proposes to issue a construction permit with specific conditions, based on Title 129, which allows for the removal of the TO/HRSG (C10A), the removal of the HRSG (S130) fresh air firing operational limitation; and the implementation of an operational limitation for the CTG bypass stack (S120).

The proposed permit and supporting materials are available Thursday, March 26 th, 2026 through Friday, April 24 th, 2026 at the NDWEE, 245 Fallbrook Blvd, Suite 100, Lincoln, Nebraska, and electronically at http://dwee.nebraska.gov. Comments received by the Department during this period will be considered prior to the final decision. During this period the applicant, or any interested person or group of persons, may request or petition the Director for a public hearing. The request must be in writing and state the nature of the issues to be raised and all arguments and factual grounds supporting their position. If a public hearing is granted by the Director, the hearing will be advertised by public notice at least 30 days prior to the hearing.

Inquiries may be made at (402) 471-2186 or dwee.airquality@nebraska.gov. Individuals requiring special accommodations or alternate formats of materials should notify the NDWEE by calling (402) 471-2186.  TDD users should call (800) 833-7352 and ask the relay operator to call the NDWEE at (402) 471-2186. For further information, to submit comments, or request a hearing you may contact the NDWEE by email “ dwee.airquality@nebraska.gov ” or by mail submitted to the attention of Air Construction Permitting Section Supervisor, 245 Fallbrook Blvd, Suite 100, Lincoln, Nebraska 68521.

The NDWEE does not discriminate on the basis of race, color, national origin, disability, age, or sex in administration of its programs or activities, and NDWEE does not intimidate or retaliate against any individual or group because they have exercised their rights to participate in or oppose actions protected/prohibited by 40 C.F.R. Parts 5 and 7, or for the purpose of interfering with such rights.

Si necesita traducción de documentos al Español, por favor llame a NDWEE al (402) 471-2186.

Get daily alerts for Nebraska DWEE Announcements

Daily digest delivered to your inbox.

Free. Unsubscribe anytime.

About this page

What is GovPing?

Every important government, regulator, and court update from around the world. One place. Real-time. Free. Our mission

What's from the agency?

Source document text, dates, docket IDs, and authority are extracted directly from NDWEE.

What's AI-generated?

The summary, classification, recommended actions, deadlines, and penalty information are AI-generated from the original text and may contain errors. Always verify against the source document.

Last updated

Classification

Agency
NDWEE
Published
March 26th, 2026
Comment period closes
April 24th, 2026 (11 days)
Compliance deadline
April 24th, 2026 (11 days)
Instrument
Consultation
Legal weight
Non-binding
Stage
Consultation
Change scope
Minor

Who this affects

Applies to
Manufacturers Energy companies
Industry sector
3254 Pharmaceutical Manufacturing
Activity scope
Construction permitting Air emissions management
Geographic scope
US-NE US-NE

Taxonomy

Primary area
Environmental Protection
Operational domain
Compliance
Topics
Energy

Get alerts for this source

We'll email you when Nebraska DWEE Announcements publishes new changes.

Free. Unsubscribe anytime.

You're subscribed!