Rio Grande LNG Terminal and Rio Bravo Pipeline Field Inspection Report

Favicon for changeflow.com FERC eLibrary: Pipeline Certificates - ChangeBridge
Published April 6th, 2026
Detected April 7th, 2026
Email

Summary

The Federal Energy Regulatory Commission published a field inspection report for Rio Grande LNG Terminal and Rio Bravo Pipeline following an inspection conducted on March 25, 2026. The report documents construction inspection findings under dockets CP16-454, CP16-455, CP20-481, and CP23-519. This is a routine oversight document with no immediate compliance obligations or penalties identified.

What changed

FERC inspectors assessed construction activities and environmental compliance measures at the Rio Grande LNG Terminal and Rio Bravo Pipeline site. The field inspection report documents site conditions and adherence to approved construction plans as part of standard FERC oversight for LNG terminal and pipeline projects.

As a routine inspection report, this filing does not establish new regulatory requirements or compliance deadlines. Energy companies operating LNG infrastructure under FERC jurisdiction may reference this report for compliance documentation purposes. No penalties or corrective actions were specified in this filing. No immediate action is required by regulated entities.

Source document (simplified)

Document Info for Accession Number: 20260406-3067

Details Document: 04/06/2026
Filed: 04/06/2026
Posted: 04/06/2026 03:43:07 PM
First Received Date: 04/06/2026 03:28:24 PM
Security Level: Public
Official: Yes
E-filing: No
Non-decisional: No
Category: Issuance
Library: Gas
Aperture: 0
File Type:
Description* :** Field Inspection Report for Rio Grande LNG, LLC 's et al. Rio Grande LNG Terminal and Rio Bravo Pipeline Project, conducted on 03/25/2026 under CP16-454 et al.
File List

| Docket | Sub-Docket | Type |
| --- | --- | --- |
| CP16-454 | 000 | On Document |
| CP16-455 | 000 | On Document |
| CP20-481 | 000 | On Document |
| CP23-519 | 000 | On Document |

| Document Class | Document Type |
| --- | --- |
| FERC Report/Study | Construction Inspection Report |

| Correspondent | Last Name | First Name | MI | Role/Org |
| --- | --- | --- | --- | --- |
| AUTHOR | * | * | | FEDERAL ENERGY REGULATORY COMMISSION |

Classification

Agency
FERC
Published
April 6th, 2026
Instrument
Notice
Legal weight
Non-binding
Stage
Final
Change scope
Minor
Document ID
Accession No. 20260406-3067
Docket
CP16-454 CP16-455 CP20-481 CP23-519

Who this affects

Applies to
Energy companies Government agencies
Industry sector
4831 Maritime & Shipping
Activity scope
LNG Terminal Operations Pipeline Construction
Geographic scope
United States US

Taxonomy

Primary area
Energy
Operational domain
Compliance
Topics
Liquefied Natural Gas Pipeline Safety Infrastructure

Get Government General alerts

Weekly digest. AI-summarized, no noise.

Free. Unsubscribe anytime.

Get alerts for this source

We'll email you when FERC eLibrary: Pipeline Certificates - ChangeBridge publishes new changes.

Optional. Personalizes your daily digest.

Free. Unsubscribe anytime.