Changeflow GovPing Government General Duke Energy Carolinas Attachment J interconnect...
Routine Rule Added Final

Duke Energy Carolinas Attachment J interconnection revisions accepted

Favicon for changeflow.com FERC eLibrary: Electric Orders
Published
Detected
Email

Summary

FERC Office of Energy Market Regulation issued a delegated order accepting Duke Energy Carolinas' filing of revisions to Attachment J, Large Generator Interconnection Procedure and Large Generator Interconnection Agreement under Tariff Volume No. 4. The acceptance applies to Duke Energy Carolinas, LLC (Docket ER26-1398).

What changed

FERC accepted Duke Energy Carolinas' tariff revisions to Attachment J, updating the Large Generator Interconnection Procedure and Large Generator Interconnection Agreement under ER26-1398. The revisions were filed on 02/13/2026 and accepted via delegated order on 04/06/2026. This is a routine tariff acceptance with no new compliance obligations imposed.

No immediate action is required by Duke Energy or other market participants beyond implementing the updated interconnection procedures under the revised tariff. The order is effective upon acceptance. No specific penalties or deadlines were mentioned as this is a standard acceptance of tariff modifications.

Archived snapshot

Apr 7, 2026

GovPing captured this document from the original source. If the source has since changed or been removed, this is the text as it existed at that time.

Document Info for Accession Number: 20260406-3052

Details Document: 04/06/2026
Filed: 04/06/2026
Posted: 04/06/2026 01:37:07 PM
First Received Date: 04/06/2026 01:31:17 PM
Security Level: Public
Official: Yes
E-filing: No
Non-decisional: No
Category: Issuance
Library: Electric
Aperture: 0
File Type:
Description* :** Letter order accepting Duke Energy Carolinas, LLC's 02/13/2026 filing of revisions to Attachment J, Large Generator Interconnection Procedure and the Large Generator Interconnection Agreement, under Tariff Volume No. 4 etc. under ER26-1398.
File List

Docket Sub-Docket Type
ER26-1398 000 On Document
Document Class Document Type
Order/Opinion Delegated Order
Correspondent Last Name First Name MI Role/Org
AUTHOR Khammal L OFFICE OF ENERGY MARKET REGULATION
RECIPIENT * * DUKE ENERGY CAROLINAS, LLC

Named provisions

Attachment J Large Generator Interconnection Procedure Large Generator Interconnection Agreement

Get daily alerts for FERC eLibrary: Electric Orders

Daily digest delivered to your inbox.

Free. Unsubscribe anytime.

About this page

What is GovPing?

Every important government, regulator, and court update from around the world. One place. Real-time. Free. Our mission

What's from the agency?

Source document text, dates, docket IDs, and authority are extracted directly from FERC.

What's AI-generated?

The summary, classification, recommended actions, deadlines, and penalty information are AI-generated from the original text and may contain errors. Always verify against the source document.

Last updated

Classification

Agency
FERC
Published
April 6th, 2026
Instrument
Rule
Legal weight
Binding
Stage
Final
Change scope
Minor
Document ID
ER26-1398
Docket
ER26-1398

Who this affects

Applies to
Energy companies
Industry sector
2210 Electric Utilities
Activity scope
Electric Utility Operations Generator Interconnection
Geographic scope
United States US

Taxonomy

Primary area
Energy
Operational domain
Compliance
Topics
Electricity Transportation

Get alerts for this source

We'll email you when FERC eLibrary: Electric Orders publishes new changes.

Free. Unsubscribe anytime.

You're subscribed!