The Federal Energy Regulatory Commission, through its Chicago Regional Office, issued correspondence to Zero 6 Energy regarding the Black Brook Hydroelectric Project (P-2894). The letter addresses the company's February 2, 2026 response and its 2025 Annual Spillway Gate Operation Certificate resubmittal, providing compliance direction on the certificate requirements.
What changed
FERC's Chicago Regional Office sent a letter to Zero 6 Energy regarding the Black Brook Project (P-2894), acknowledging receipt of the company's February 2, 2026 response and the 2025 Annual Spillway Gate Operation Certificate resubmittal. The letter is classified as compliance directives and general correspondence under FERC's hydropower licensing framework.
Hydropower operators holding FERC licenses for projects with spillway gate certification requirements should ensure their annual certificates are complete and submitted according to license conditions. Zero 6 Energy should review any specific feedback or requirements outlined in this correspondence and respond accordingly to maintain compliance with its project license.
What to do next
- Review the FERC letter for specific feedback on the 2025 Annual Spillway Gate Operation Certificate resubmittal
- Ensure any deficiencies identified are addressed and resubmitted as required
- Maintain records of spillway gate operation certifications per license conditions
Source document (simplified)
Document Info for Accession Number: 20260403-3043
Details Document: 04/03/2026
Filed: 04/03/2026
Posted: 04/03/2026 01:47:07 PM
First Received Date: 04/03/2026 01:27:43 PM
Security Level: Public
Official: Yes
E-filing: No
Non-decisional: No
Category: Issuance
Library: Hydro
Aperture: 0
File Type:
Description* :** Letter to Zero 6 Energy discussing the 02/02/2026 response and the 2025 Annual Spillway Gate Operation Certificate resubmittal for the Black Brook Project under P-2894.
File List
| Docket | Sub-Docket | Type |
| --- | --- | --- |
| P-2894 | 000 | On Document |
| Document Class | Document Type |
| --- | --- |
| FERC Correspondence With Applicant | Compliance Directives |
| FERC Correspondence With Applicant | General Correspondence |
| Correspondent | Last Name | First Name | MI | Role/Org |
| --- | --- | --- | --- | --- |
| RECIPIENT | Neset | K | | ZERO 6 ENERGY |
| AUTHOR | Sabido | M | | CHICAGO REGIONAL OFFICE |
Named provisions
Related changes
Source
Classification
Who this affects
Taxonomy
Browse Categories
Get Government General alerts
Weekly digest. AI-summarized, no noise.
Free. Unsubscribe anytime.
Get alerts for this source
We'll email you when FERC eLibrary: Hydropower Licensing - ChangeBridge publishes new changes.