Summary

FERC Atlanta Regional Office accepted an extension request from North Anna Power Station to delay submission of the 10-year detailed Gate Inspection Report for Project P-6335. The extension request was dated March 30, 2026. This is a routine administrative action that grants additional time without modifying substantive requirements.

What changed

FERC issued a letter accepting North Anna Power Station's extension request for the 10-year detailed Gate Inspection Report under Project P-6335 (North Anna Project). The extension was requested on March 30, 2026, and approved by FERC's Atlanta Regional Office on April 3, 2026.

Affected parties should ensure compliance with the newly established deadline for the Gate Inspection Report submission. While this action is administrative in nature and does not alter the underlying regulatory requirements, licensees must still meet their extended deadlines. No penalties or enforcement actions are associated with this extension approval.

What to do next

  1. Submit the 10-year Gate Inspection Report by the extended deadline established by FERC

Source document (simplified)

Document Info for Accession Number: 20260403-3005

Details Document: 04/03/2026
Filed: 04/03/2026
Posted: 04/03/2026 08:55:05 AM
First Received Date: 04/03/2026 08:49:39 AM
Security Level: Public
Official: Yes
E-filing: No
Non-decisional: No
Category: Issuance
Library: Hydro
Aperture: 0
File Type:
Description* :** Letter to North Anna Power Station accepting the 03/30/2026 request for an extension of time to submit the 10-year detailed Gate Inspection Report for the North Anna Project under P-6335.
File List

| Docket | Sub-Docket | Type |
| --- | --- | --- |
| P-6335 | 000 | On Document |

| Document Class | Document Type |
| --- | --- |
| Order/Opinion | Delegated Order |

| Correspondent | Last Name | First Name | MI | Role/Org |
| --- | --- | --- | --- | --- |
| RECIPIENT | Jenkins | J | | NORTH ANNA POWER STATION |
| AUTHOR | BROWN | W | J | ATLANTA REGIONAL OFFICE |

Classification

Agency
FERC
Published
April 3rd, 2026
Instrument
Notice
Legal weight
Non-binding
Stage
Final
Change scope
Minor
Docket
P-6335

Who this affects

Applies to
Energy companies
Industry sector
2210 Electric Utilities
Activity scope
Hydropower Licensing
Geographic scope
United States US

Taxonomy

Primary area
Energy
Operational domain
Compliance
Topics
Infrastructure Environmental Protection

Get Government General alerts

Weekly digest. AI-summarized, no noise.

Free. Unsubscribe anytime.

Get alerts for this source

We'll email you when FERC eLibrary: Hydropower Licensing - ChangeBridge publishes new changes.

Optional. Personalizes your daily digest.

Free. Unsubscribe anytime.