FERC Accepts Gate Inspection Report Extension for North Anna Project
Summary
FERC Atlanta Regional Office accepted an extension request from North Anna Power Station to delay submission of the 10-year detailed Gate Inspection Report for Project P-6335. The extension request was dated March 30, 2026. This is a routine administrative action that grants additional time without modifying substantive requirements.
What changed
FERC issued a letter accepting North Anna Power Station's extension request for the 10-year detailed Gate Inspection Report under Project P-6335 (North Anna Project). The extension was requested on March 30, 2026, and approved by FERC's Atlanta Regional Office on April 3, 2026.
Affected parties should ensure compliance with the newly established deadline for the Gate Inspection Report submission. While this action is administrative in nature and does not alter the underlying regulatory requirements, licensees must still meet their extended deadlines. No penalties or enforcement actions are associated with this extension approval.
What to do next
- Submit the 10-year Gate Inspection Report by the extended deadline established by FERC
Source document (simplified)
Document Info for Accession Number: 20260403-3005
Details Document: 04/03/2026
Filed: 04/03/2026
Posted: 04/03/2026 08:55:05 AM
First Received Date: 04/03/2026 08:49:39 AM
Security Level: Public
Official: Yes
E-filing: No
Non-decisional: No
Category: Issuance
Library: Hydro
Aperture: 0
File Type:
Description* :** Letter to North Anna Power Station accepting the 03/30/2026 request for an extension of time to submit the 10-year detailed Gate Inspection Report for the North Anna Project under P-6335.
File List
| Docket | Sub-Docket | Type |
| --- | --- | --- |
| P-6335 | 000 | On Document |
| Document Class | Document Type |
| --- | --- |
| Order/Opinion | Delegated Order |
| Correspondent | Last Name | First Name | MI | Role/Org |
| --- | --- | --- | --- | --- |
| RECIPIENT | Jenkins | J | | NORTH ANNA POWER STATION |
| AUTHOR | BROWN | W | J | ATLANTA REGIONAL OFFICE |
Related changes
Source
Classification
Who this affects
Taxonomy
Browse Categories
Get Government General alerts
Weekly digest. AI-summarized, no noise.
Free. Unsubscribe anytime.
Get alerts for this source
We'll email you when FERC eLibrary: Hydropower Licensing - ChangeBridge publishes new changes.