Dominion Energy South Carolina Sluice Gate Decommissioning Required

Favicon for changeflow.com FERC eLibrary: Hydropower Licensing - ChangeBridge
Filed April 3rd, 2026
Detected April 4th, 2026
Email

Summary

FERC Atlanta Regional Office issued a compliance directive to Dominion Energy South Carolina Inc. requiring the company to file additional information within 30 days regarding the sluice gate decommissioning at the Parr Shoals Development under Project P-1894. The request stems from the hydropower licensing process and failure to respond could affect the project's continued operation.

What changed

FERC's Atlanta Regional Office issued a letter to Dominion Energy South Carolina requiring additional information to be filed within 30 days regarding the proposed sluice gate decommissioning for the Parr Shoals Development (P-1894). The letter constitutes a compliance directive under the Federal Power Act hydropower licensing framework.

Dominion Energy South Carolina must submit the requested additional information by the 30-day deadline. As a condition of holding a FERC hydropower license, the licensee is obligated to respond to agency requests for information. Non-compliance with this directive could result in enforcement action or affect the license status for the Parr Shoals Development.

What to do next

  1. File additional information with FERC within 30 days as specified in the April 3, 2026 letter
  2. Ensure the submitted information addresses all requirements related to the sluice gate decommissioning for Parr Shoals Development
  3. Coordinate with FERC Atlanta Regional Office to confirm receipt and adequacy of the filed information

Source document (simplified)

Document Info for Accession Number: 20260403-3009

Details Document: 04/03/2026
Filed: 04/03/2026
Posted: 04/03/2026 09:17:06 AM
First Received Date: 04/03/2026 08:57:10 AM
Security Level: Public
Official: Yes
E-filing: No
Non-decisional: No
Category: Issuance
Library: Hydro
Aperture: 0
File Type:
Description* :** Letter to Dominion Energy South Carolina Inc. requiring additional information to be filed with 30 days for the sluice gate decommissioning for the Parr Shoals Development of the Parr Shoals Development under P-1894.
File List

| Docket | Sub-Docket | Type |
| --- | --- | --- |
| P-1894 | 000 | On Document |

| Document Class | Document Type |
| --- | --- |
| FERC Correspondence With Applicant | Compliance Directives |

| Correspondent | Last Name | First Name | MI | Role/Org |
| --- | --- | --- | --- | --- |
| RECIPIENT | GRIFFIN | I | | DOMINION ENERGY SOUTH CAROLINA, INC |
| AUTHOR | BROWN | W | J | ATLANTA REGIONAL OFFICE |

Named provisions

Sluice Gate Decommissioning Parr Shoals Development

Classification

Agency
FERC
Filed
April 3rd, 2026
Compliance deadline
May 3rd, 2026 (27 days)
Instrument
Enforcement
Legal weight
Binding
Stage
Final
Change scope
Substantive
Docket
P-1894

Who this affects

Applies to
Energy companies
Industry sector
2210 Electric Utilities
Activity scope
Hydropower Licensing Infrastructure Decommissioning
Threshold
Hydropower Project P-1894 (Parr Shoals Development)
Geographic scope
US-SC US-SC

Taxonomy

Primary area
Energy
Operational domain
Compliance
Topics
Environmental Protection Hydropower Licensing

Get Government General alerts

Weekly digest. AI-summarized, no noise.

Free. Unsubscribe anytime.

Get alerts for this source

We'll email you when FERC eLibrary: Hydropower Licensing - ChangeBridge publishes new changes.

Optional. Personalizes your daily digest.

Free. Unsubscribe anytime.