DNR Issues 3 Enforcement Orders with $25,000 in Penalties

Favicon for www.iowadnr.gov DNR-News-Releases
Filed March 5th, 2026
Detected March 17th, 2026
Email

Summary

The Iowa Department of Natural Resources (DNR) has issued three enforcement orders against Shell Rock Soy Processing, LLC, Valero Renewable Fuels Company, LLC, and Flaherty Farms, totaling $25,000 in administrative penalties. These orders address violations related to environmental protection, including air emissions and water quality.

What changed

The Iowa DNR has issued three new enforcement orders, imposing a total of $25,000 in administrative penalties. Shell Rock Soy Processing, LLC faces a $10,000 penalty for violations related to oil suppression systems and bay curtains, requiring adherence to construction permit conditions and future permit application procedures. Valero Renewable Fuels Company, LLC was fined $10,000 for issues with equipment operation, emissions testing protocols, and excess emissions, mandating specific compliance plans and root cause analyses. Flaherty Farms received a $5,000 penalty for improper manure handling that caused water quality violations.

Responsible parties have 60 days to appeal these orders or pay the penalties. Businesses operating in Iowa must ensure strict compliance with environmental laws, including proper permitting, emissions control, and waste management practices. Failure to comply can result in significant financial penalties and potential operational disruptions. Companies should review their environmental compliance programs to align with the requirements outlined in these orders and similar enforcement actions.

What to do next

  1. Review environmental permits and operational procedures for compliance with state and federal laws.
  2. Ensure all necessary construction permits are obtained prior to equipment installation or alteration.
  3. Implement and maintain systems for proper handling of waste and control of emissions.

Penalties

$25,000 in total administrative penalties ($10,000 for Shell Rock Soy Processing, LLC; $10,000 for Valero Renewable Fuels Company, LLC; $5,000 for Flaherty Farms).

Source document (simplified)

DNR enforcement actions, published 03/05/2026

DES MOINES – DNR staff work with individuals, businesses and communities to help them protect our natural resources by complying with state and federal laws. This approach is very effective. In the few cases where compliance cannot be achieved, the DNR issues enforcement actions. The following list summarizes recent enforcement actions. Find the entire, original orders on DNR’s website at www.iowadnr.gov/EnforcementActions

Consent Orders A consent order is issued as an alternative to issuing an administrative order. A consent order indicates that the DNR has voluntarily entered into a legally enforceable agreement with the other party.

Butler County

Shell Rock Soy Processing, LLC

Utilize the oil suppression system and keep the exit doors on each soybean receiving bay shut as required by the current construction permit until the following conditions have been met: new construction permits have been issued, the equipment and control equipment required in the new construction permit are installed and operational, and all operating requirements contained in the new construction permits are implemented and DNR has approved removal of the oil suppression system; ensure plastic curtains separate Bays 1 and 2; complete all modifications and construction required by the new construction permits within 6 months of its issuance; submit quarterly updates on progress; in the future, submit construction permit applications and receive final construction permits prior to constructing, installing, reconstructing, or altering any equipment or control equipment; and pay a $10,000 administrative penalty.

Kossuth County

Valero Renewable Fuels Company, LLC

Maintain and operate equipment and control equipment at all times in a manner consistent with good practice for minimizing emissions; provide at least 30-days notice prior to all compliance stack tests (date and time); conduct all future compliance stack tests at the maximum rate continuous capacity of the source as required by law or as otherwise required by an applicable permit condition unless DNR approves an altenrative approach in writing; conduct quarterly Volatile Organic Compounds and Hazardous Air Pollutants compliance testing while achieving maximum production rates on Emission Point (EP) 240c, EPS10, EPS70, EPS10c, and EPS70b, with at least 45 days between test events; such tests shall occur until each emission point demonstrates compliance with the emission limits for four consecutive stack tests; provide hourly emission summaries and raw emissions data for each hour of emissions data collection prior to and for the express purpose of each scheduled compliance test event; submit two compliance plans within 30 days to address excess emissions documented on EP240c; submit progress reports every three months related to the work required by this Order; submit a permit determination request to the DNR detailing the reverse osmosis reject water recycling implemented in the EPS40c scrubber; submit a root cause analysis for the emission limit violations documented in 2023, 2024, and 2025 stack test events; submit construction permit applications for EPS10; and pay a $10,000 administrative penalty

Pocahontas County

Tim and Josh Flaherty dba Flaherty Farms

Ensure that all future handling, transferring, and land application of manure is done in accordance with law and does not cause water quality violations; and pay a $5,000 administrative penalty.

Administrative Orders

Responsible parties have 60 days to appeal the order or 60 days to pay the penalty.

Source

Analysis generated by AI. Source diff and links are from the original.

Classification

Agency
State DEQ
Filed
March 5th, 2026
Instrument
Enforcement
Legal weight
Binding
Stage
Final
Change scope
Substantive

Who this affects

Applies to
Energy companies Agricultural firms Manufacturers
Geographic scope
State (Iowa)

Taxonomy

Primary area
Environmental Protection
Operational domain
Compliance
Topics
Water Quality Air Emissions Permitting

Get Environment alerts

Weekly digest. AI-summarized, no noise.

Free. Unsubscribe anytime.

Get alerts for this source

We'll email you when DNR-News-Releases publishes new changes.

Free. Unsubscribe anytime.