The Federal Energy Regulatory Commission published a notice on April 14, 2026, announcing WBI Energy Transmission, Inc.'s pipeline application under Docket No. CP26-158-000. The notice establishes an intervention deadline for interested parties to intervene in the proceeding. The document spans pages 19127-19129 of Federal Register volume 91.

What changed

FERC published a notice announcing WBI Energy Transmission, Inc.'s application and establishing an intervention deadline. The notice is published under Docket No. CP26-158-000 in the Federal Register. The document does not contain substantive regulatory requirements but establishes procedural deadlines.

Affected parties—including potential interveners, landowners, and stakeholders—should file timely interventions to preserve their participation rights in the regulatory review process. The notice is a standard procedural step in FERC's review of pipeline applications under the Natural Gas Act.

What to do next

  1. File interventions by the deadline to participate in the proceeding
  2. Monitor FERC docket for updates on the application

Archived snapshot

Apr 14, 2026

GovPing captured this document from the original source. If the source has since changed or been removed, this is the text as it existed at that time.

Legal Status This site displays a prototype of a “Web 2.0” version of the daily
Federal Register. It is not an official legal edition of the Federal
Register, and does not replace the official print version or the official
electronic version on GPO’s govinfo.gov.

The documents posted on this site are XML renditions of published Federal
Register documents. Each document posted on the site includes a link to the
corresponding official PDF file on govinfo.gov. This prototype edition of the
daily Federal Register on FederalRegister.gov will remain an unofficial
informational resource until the Administrative Committee of the Federal
Register (ACFR) issues a regulation granting it official legal status.
For complete information about, and access to, our official publications
and services, go to About the Federal Register on NARA's archives.gov.

The OFR/GPO partnership is committed to presenting accurate and reliable
regulatory information on FederalRegister.gov with the objective of
establishing the XML-based Federal Register as an ACFR-sanctioned
publication in the future. While every effort has been made to ensure that
the material on FederalRegister.gov is accurately displayed, consistent with
the official SGML-based PDF version on govinfo.gov, those relying on it for
legal research should verify their results against an official edition of
the Federal Register. Until the ACFR grants it official status, the XML
rendition of the daily Federal Register on FederalRegister.gov does not
provide legal notice to the public or judicial notice to the courts.

Legal Status

Notice

WBI Energy Transmission, Inc.; Notice Of Application and Establishing Intervention Deadline

A Notice by the Federal Energy Regulatory Commission on 04/14/2026

  • 1.

1.

  • Document Details Published Content - Document Details Agencies Department of Energy Federal Energy Regulatory Commission Agency/Docket Number Docket No. CP26-158-000 Document Citation 91 FR 19127 Document Number 2026-07211 Document Type Notice Pages 19127-19129
    (3 pages) Publication Date 04/14/2026 Published Content - Document Details

  • PDF Official Content

  • Document Details Published Content - Document Details Agencies Department of Energy Federal Energy Regulatory Commission Agency/Docket Number Docket No. CP26-158-000 Document Citation 91 FR 19127 Document Number 2026-07211 Document Type Notice Pages 19127-19129
    (3 pages) Publication Date 04/14/2026 Published Content - Document Details

  • Table of Contents Enhanced Content - Table of Contents This table of contents is a navigational tool, processed from the
    headings within the legal text of Federal Register documents.
    This repetition of headings to form internal navigation links
    has no substantive legal effect.

    • Footnotes Enhanced Content - Table of Contents
  • Public Comments Enhanced Content - Public Comments This feature is not available for this document.

Enhanced Content - Public Comments
- Regulations.gov Data Enhanced Content - Regulations.gov Data Additional information is not currently available for this document.

Enhanced Content - Regulations.gov Data

- Sharing Enhanced Content - Sharing Shorter Document URL https://www.federalregister.gov/d/2026-07211 Email Email this document to a friend Enhanced Content - Sharing

  • Print Enhanced Content - Print
  • Other Formats Enhanced Content - Other Formats This document is also available in the following formats:

JSON Normalized attributes and metadata XML Original full text XML MODS Government Publishing Office metadata More information and documentation can be found in our developer tools pages.

Enhanced Content - Other Formats
- Public Inspection Public Inspection This PDF is FR Doc. 2026-07211 as it appeared on Public Inspection on
04/13/2026 at 8:45 am.

It was viewed
5
times while on Public Inspection.

If you are using public inspection listings for legal research, you
should verify the contents of the documents against a final, official
edition of the Federal Register. Only official editions of the
Federal Register provide legal notice of publication to the public and judicial notice
to the courts under 44 U.S.C. 1503 & 1507.
Learn more here.

Public Inspection
Published Document: 2026-07211 (91 FR 19127) This document has been published in the Federal Register. Use the PDF linked in the document sidebar for the official electronic format.

Document Headings Document headings vary by document type but may contain
the following:

  1. the agency or agencies that issued and signed a document
  2. the number of the CFR title and the number of each part the document amends, proposes to amend, or is directly related to
  3. the agency docket number / agency internal file number
  4. the RIN which identifies each regulatory action listed in the Unified Agenda of Federal Regulatory and Deregulatory Actions See the Document Drafting Handbook for more details.
Department of Energy
Federal Energy Regulatory Commission
  1. [Docket No. CP26-158-000] Take notice that on March 31, 2026, WBI Energy Transmission, Inc. (WBI), 1250 West Century Avenue, Bismarck, North Dakota 58503, filed an application under section 7(c) of the Natural Gas Act (NGA) and Part 157 of the Commission's regulations requesting authorization for its Line Section 32 Expansion Project (Project). The Project consists of approximately 17 miles of new 24-inch-diameter pipeline lateral and associated facilities from WBI Energy's Line Section 32 to a proposed new delivery station in Williams County, North Dakota, and modifications at WBI's Northern Border Pipeline Elkhorn Creek interconnect in McKenzie County, North Dakota. The Project will allow WBI to provide 190,000 dekatherms per day of incremental firm transportation service ( printed page 19128) to a new electric generation facility in Williams County, North Dakota. WBI estimates the total cost of the Project to be $68,087,052 and proposes to use its existing FT-1 recourse rate for firm transportation service on the Project, all as more fully set forth in the application which is on file with the Commission and open for public inspection.

In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission's Home Page (http://www.ferc.gov). From the Commission's Home Page on the internet, this information is available on eLibrary. The full text of this document is available on eLibrary in PDF and Microsoft Word format for viewing, printing, and/or downloading. To access this document in eLibrary, type the docket number excluding the last three digits of this document in the docket number field.

User assistance is available for eLibrary and the Commission's website during normal business hours from FERC Online Support at (202) 502-6652 (toll free at 1-866-208-3676) or email at ferconlinesupport@ferc.gov, or the Public Reference Room at (202) 502-8371, TTY (202) 502-8659. Email the Public Reference Room at public.referenceroom@ferc.gov.

Any questions regarding the proposed project should be directed to Lori Myerchin, Vice President, Regulatory Affairs and Transportation Services, WBI Energy Transmission, Inc., P.O. Box 5601, Bismarck, North Dakota 58506, by phone at (701) 530-1563, or by email at lori.myerchin@wbienergy.com.

Pursuant to section 157.9 of the Commission's Rules of Practice and Procedure, [1 ] within 90 days of this Notice the Commission staff will either: complete its environmental review and place it into the Commission's public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff's issuance of the final environmental impact statement (FEIS) or environmental assessment (EA) for this proposal. The filing of an EA in the Commission's public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff's FEIS or EA.

Water Quality Certification

WBI stated that a water quality certificate under section 401 of the Clean Water Act is required for the Project from the North Dakota Department of Environmental Quality, Division of Water Quality. When available, WBI should submit to the Commission a copy of the request for certification for the Commission authorization, including the date the request was submitted to the certifying agency, and either (1) a copy of the certifying agency's decision or (2) evidence of waiver of water quality certification.

Public Participation

There are three ways to become involved in the Commission's review of this project: you can file comments on the project, you can protest the filing, and you can file a motion to intervene in the proceeding. There is no fee or cost for filing comments or intervening. The deadline for filing a motion to intervene is 5:00 p.m. Eastern Time on April 30, 2026. How to file protests, motions to intervene, and comments is explained below.

For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, contact the Office of Public Participation (OPP) at (202) 502-6595 or OPP@ferc.gov.

Comments

Any person wishing to comment on the project may do so. Comments may include statements of support or objections, to the project as a whole or specific aspects of the project. The more specific your comments, the more useful they will be.

Protests

Pursuant to sections 157.10(a)(4) [2 ] and 385.211 [3 ] of the Commission's regulations under the NGA, any person [4 ] may file a protest to the application. Protests must comply with the requirements specified in section 385.2001 [5 ] of the Commission's regulations. A protest may also serve as a motion to intervene so long as the protestor states it also seeks to be an intervenor.

To ensure that your comments or protests are timely and properly recorded, please submit your comments on or before 5:00 p.m. Eastern Time on April 30, 2026.

There are three methods you can use to submit your comments or protests to the Commission. In all instances, please reference the Project docket number CP26-158-000 in your submission.

(1) You may file your comments electronically by using the eComment feature, which is located on the Commission's website at www.ferc.gov under the link to Documents and Filings. Using eComment is an easy method for interested persons to submit brief, text-only comments on a project;

(2) You may file your comments or protests electronically by using the eFiling feature, which is located on the Commission's website (www.ferc.gov) under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on “eRegister.” You will be asked to select the type of filing you are making; first select “General” and then select “Comment on a Filing”; or

(3) You can file a paper copy of your comments or protests by mailing them to the following address below. Your written comments must reference the Project docket number (CP26-158-000).

To file via USPS: Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426.

To file via any other courier: Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852.

The Commission encourages electronic filing of comments (options 1 and 2 above) and has eFiling staff available to assist you at (202) 502-8258 or FercOnlineSupport@ferc.gov.

Persons who comment on the environmental review of this project will be placed on the Commission's environmental mailing list and will receive notification when the environmental documents (EA or EIS) are issued for this project and will be notified of meetings associated with the Commission's environmental review process.

The Commission considers all comments received about the project in determining the appropriate action to be taken. However, the filing of a comment alone will not serve to make the filer a party to the proceeding. To become a ( printed page 19129) party, you must intervene in the proceeding. For instructions on how to intervene, see below.

Interventions

Any person, which includes individuals, organizations, businesses, municipalities, and other entities, [6 ] has the option to file a motion to intervene in this proceeding. Only intervenors have the right to request rehearing of Commission orders issued in this proceeding and to subsequently challenge the Commission's orders in the U.S. Circuit Courts of Appeal.

To intervene, you must submit a motion to intervene to the Commission in accordance with Rule 214 of the Commission's Rules of Practice and Procedure [7 ] and the regulations under the NGA [8 ] by the intervention deadline for the project, which is 5:00 p.m. Eastern Time on April 30, 2026. As described further in Rule 214, your motion to intervene must state, to the extent known, your position regarding the proceeding, as well as your interest in the proceeding. For an individual, this could include your status as a landowner, ratepayer, resident of an impacted community, or recreationist. You do not need to have property directly impacted by the project in order to intervene. For more information about motions to intervene, refer to the FERC website at https://www.ferc.gov/​resources/​guides/​how-to/​intervene.asp.

There are two ways to submit your motion to intervene. In both instances, please reference the Project docket number CP26-158-000 in your submission.

(1) You may file your motion to intervene by using the Commission's eFiling feature, which is located on the Commission's website (www.ferc.gov) under the link to Documents and Filings. New eFiling users must first create an account by clicking on “eRegister.” You will be asked to select the type of filing you are making; first select “General” and then select “Intervention.” The eFiling feature includes a document-less intervention option; for more information, visit https://www.ferc.gov/​docs-filing/​efiling/​document-less-intervention.pdf.; or

(2) You can file a paper copy of your motion to intervene, along with three copies, by mailing the documents to the address below. Your motion to intervene must reference the Project docket number CP26-158-000.

To file via USPS: Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426.

To file via any other courier: Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852.

The Commission encourages electronic filing of motions to intervene (option 1 above) and has eFiling staff available to assist you at (202) 502-8258 or FercOnlineSupport@ferc.gov.

Protests and motions to intervene must be served on the applicant either by mail at: Lori Myerchin, Vice President, Regulatory Affairs and Transportation Services, WBI Energy Transmission, Inc., P.O. Box 5601, Bismarck, North Dakota 58506, or by email (with a link to the document) at lori.myerchin@wbienergy.com. Any subsequent submissions by an intervenor must be served on the applicant and all other parties to the proceeding. Contact information for parties can be downloaded from the service list at the eService link on FERC Online. Service can be via email with a link to the document.

All timely, unopposed [9 ] motions to intervene are automatically granted by operation of Rule 214(c)(1). [10 ] Motions to intervene that are filed after the intervention deadline are untimely and may be denied. Any late-filed motion to intervene must show good cause for being late and must explain why the time limitation should be waived and provide justification by reference to factors set forth in Rule 214(d) of the Commission's Rules and Regulations. [11 ] A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies (paper or electronic) of all documents filed by the applicant and by all other parties.

Tracking the Proceeding

Throughout the proceeding, additional information about the project will be available from OPP at (202) 502-6595 or on the FERC website at www.ferc.gov using the “eLibrary” link as described above. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings.

In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. For more information and to register, go to www.ferc.gov/​docs-filing/​esubscription.asp.

Intervention Deadline: 5:00 p.m. Eastern Time on April 30, 2026.

(Authority: 18 CFR 2.1)

Dated: April 9, 2026.

Carlos D. Clay,

Deputy Secretary.

Footnotes

  1. 18 CFR 157.9.

Back to Citation 2. 18 CFR 157.10(a)(4).

Back to Citation 3. 18 CFR 385.211.

Back to Citation 4.

                     Persons include individuals, organizations, businesses, municipalities, and other entities. [18 CFR 385.102(d)](https://www.ecfr.gov/current/title-18/section-385.102#p-385.102(d)).

Back to Citation 5. 18 CFR 385.2001.

Back to Citation 6. 18 CFR 385.102(d).

Back to Citation 7. 18 CFR 385.214.

Back to Citation 8. 18 CFR 157.10.

Back to Citation 9.

                     The applicant has 15 days from the submittal of a motion to intervene to file a written objection to the intervention.

Back to Citation 10. 18 CFR 385.214(c)(1).

Back to Citation 11. 18 CFR 385.214(b)(3) and (d).

Back to Citation [FR Doc. 2026-07211 Filed 4-13-26; 8:45 am]

BILLING CODE 6717-01-P

Published Document: 2026-07211 (91 FR 19127)

Get daily alerts for FR: Federal Energy Regulatory Commission

Daily digest delivered to your inbox.

Free. Unsubscribe anytime.

About this page

What is GovPing?

Every important government, regulator, and court update from around the world. One place. Real-time. Free. Our mission

What's from the agency?

Source document text, dates, docket IDs, and authority are extracted directly from Energy Department.

What's AI-generated?

The summary, classification, recommended actions, deadlines, and penalty information are AI-generated from the original text and may contain errors. Always verify against the source document.

Last updated

Classification

Agency
Energy Department
Published
April 14th, 2026
Instrument
Notice
Legal weight
Non-binding
Stage
Final
Change scope
Minor
Document ID
91 FR 19127 / Docket No. CP26-158-000
Docket
Docket No. CP26-158-000

Who this affects

Applies to
Energy companies Government agencies
Industry sector
2111 Oil & Gas Extraction
Activity scope
Pipeline applications Intervention filings Natural gas transmission
Geographic scope
United States US

Taxonomy

Primary area
Energy
Operational domain
Regulatory Affairs
Topics
Environmental Protection Transportation

Get alerts for this source

We'll email you when FR: Federal Energy Regulatory Commission publishes new changes.

Free. Unsubscribe anytime.

You're subscribed!