Summary

FERC staff will prepare an environmental document under NEPA for Kinder Morgan Louisiana Pipeline LLC's (KMLP) Texas Access Project, a natural gas pipeline extension from Jefferson County, Texas into Cameron and Calcasieu Parishes, Louisiana. The proposed project involves approximately 3 miles of 48-inch diameter pipeline capable of transporting up to 1,300,000 dekatherms per day. FERC requests public comments on the scope of environmental issues by 5:00 p.m. Eastern Time on May 18, 2026, to be submitted in Docket No. CP26-136-000.

“The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental document that will discuss the environmental impacts of the Texas Access Project involving construction and operation of facilities by Kinder Morgan Louisiana Pipeline LLC (KMLP) from Jefferson County, Texas into Cameron and Calcasieu Parishes, Louisiana.”

FERC , verbatim from source
Why this matters

Pipeline developers, energy companies with interests in Gulf Coast natural gas infrastructure, and landowners along the proposed Jefferson County, Texas to Cameron and Calcasieu Parish, Louisiana corridor should consider submitting scoping comments by May 18, 2026. Once FERC issues a Certificate of Public Convenience and Necessity, KMLP will have statutory eminent domain authority under the Natural Gas Act regardless of individual landowner objection.

AI-drafted from the source document, validated against GovPing's analyst note standards . For the primary regulatory language, read the source document .
Published by FERC on regulations.gov . Detected, standardized, and enriched by GovPing. Review our methodology and editorial standards .

About this source

Every Federal Energy Regulatory Commission document on regulations.gov, the federal rulemaking portal: tribal consultation notices, combined filings of electric rate applications, pipeline environmental reviews, LNG certificate proceedings, and the procedural rules that shape FERC practice. Around 150 a month. This complements FERC's eLibrary docket system by carrying the higher-visibility proceedings with public comment periods. Watch this if you intervene in FERC cases, advise pipeline developers on certificate proceedings, follow transmission planning under Order 1920, or track the LNG export authorization work. GovPing publishes each posting with the docket, document type, and comment deadline where applicable.

What changed

FERC has initiated the scoping phase for the Texas Access Project under the National Environmental Policy Act (NEPA), inviting public comment on the environmental impacts, reasonable alternatives, and mitigation measures to be addressed in the environmental document. KMLP proposes to construct pipeline facilities capable of transporting up to 1,300,000 Dth/d of natural gas from new Texas interconnections.

Landowners along the proposed route should be aware that pipeline companies may contact them regarding easement acquisition, and if the project is approved, the Natural Gas Act conveys eminent domain authority to the company. State and local government representatives are encouraged to notify constituents of the proposed project and solicit comments on areas of concern.

Archived snapshot

Apr 23, 2026

GovPing captured this document from the original source. If the source has since changed or been removed, this is the text as it existed at that time.

Content

The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental document that will
discuss the environmental impacts of the Texas Access Project involving construction and operation of facilities by Kinder
Morgan Louisiana Pipeline LLC (KMLP) from Jefferson County, Texas into Cameron and Calcasieu Parishes, Louisiana. The Commission
will use this environmental document in its decision-making process to determine whether the project is in the public convenience
and necessity.

This notice announces the opening of the scoping process the Commission will use to gather input from the public and interested
agencies regarding the project. As part of the National Environmental Policy Act (NEPA) review process, the Commission takes
into account concerns the public may have about proposals and the environmental impacts that could result from its action
whenever it considers the issuance of a Certificate of Public Convenience and Necessity. This gathering of public input is
referred to as “scoping.” The main goal of the scoping process is to focus the analysis in the environmental document on the
important environmental issues. Additional information about the Commission's NEPA process is described below in the NEPA Process and Environmental Document section of this notice.

By this notice, the Commission requests public comments on the scope

of issues to address in the environmental document. To ensure that your comments are timely and properly recorded, please
submit your comments so that the Commission receives them in Washington, DC on or before 5:00 p.m. Eastern Time on May 18,
2026. Comments may be submitted in written form. Further details on how to submit comments are provided in the Public Participation section of this notice.

Your comments should focus on the potential environmental effects, reasonable alternatives, and measures to avoid or lessen
environmental impacts. Your input will help the Commission staff determine what issues they need to evaluate in the environmental
document. Commission staff will consider all written comments during the preparation of the environmental document.

If you submitted comments on this project to the Commission before the opening of this docket on March 3, 2026, you will need
to file those comments in Docket No. CP26-136-000 to ensure they are considered as part of this proceeding.

This notice is being sent to the Commission's current environmental mailing list for this project. State and local government
representatives should notify their constituents of this proposed project and encourage them to comment on their areas of
concern.

If you are a landowner receiving this notice, a pipeline company representative may contact you about the acquisition of an
easement to construct, operate, and maintain the proposed facilities. The company would seek to negotiate a mutually acceptable
easement agreement. You are not required to enter into an agreement. However, if the Commission approves the project, the
Natural Gas Act conveys the right of eminent domain to the company. Therefore, if you and the company do not reach an easement
agreement, the pipeline company could initiate condemnation proceedings in court. In such instances, compensation would be
determined by a judge in accordance with state law. The Commission does not subsequently grant, exercise, or oversee the exercise
of that eminent domain authority. The courts have exclusive authority to handle eminent domain cases; the Commission has no
jurisdiction over these matters.

KMLP provided landowners with a fact sheet prepared by the FERC entitled “An Interstate Natural Gas Facility On My Land? What
Do I Need To Know?” which addresses typically asked questions, including the use of eminent domain and how to participate
in the Commission's proceedings. This fact sheet along with other landowner topics of interest are available for viewing on
the FERC website (www.ferc.gov) under the Natural Gas, Landowner Topics link.

Public Participation

There are three methods you can use to submit your comments to the Commission. Please carefully follow these instructions
so that your comments are properly recorded. The Commission encourages electronic filing of comments and has staff available
to assist you at (866) 208-3676 or FercOnlineSupport@ferc.gov.

(1) You can file your comments electronically using the eComment feature, which is located on the Commission's website (www.ferc.gov) under the link to FERC Online. Using eComment is an easy method for submitting brief, text-only comments on a project;

(2) You can file your comments electronically by using the eFiling feature, which is located on the Commission's website (www.ferc.gov) under the link to FERC Online. With eFiling, you can provide comments in a variety of formats by attaching them as a file
with your submission. New eFiling users must first create an account by clicking on “eRegister.” You will be asked to select
the type of filing you are making; a comment on a particular project is considered a “Comment on a Filing”; or

(3) You can file a paper copy of your comments by mailing them to the Commission. Be sure to reference the project docket
number (CP26-136-000) in your letter. Submissions sent via the U.S. Postal Service must be addressed to: Debbie-Anne A. Reese,
Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via
any other carrier must be addressed to: Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins
Avenue, Rockville, MD 20852.

Additionally, the Commission offers a free service called eSubscription which makes it easy to stay informed of all issuances
and submittals regarding the dockets/projects to which you subscribe. These instant email notifications are the fastest way
to receive notification and provide a link to the document files which can reduce the amount of time you spend researching
proceedings. Go to https://www.ferc.gov/ferc-online/overview to register for eSubscription.

For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, contact
the Office of Public Participation at (202) 502-6595 or OPP@ferc.gov.

Summary of the Proposed Project

KMLP proposes to construct, install, modify, operate, and maintain an extension of KMLP's interstate natural gas pipeline
system and certain related facilities located in Jefferson County, Texas and Cameron and Calcasieu parishes, Louisiana. The
proposed project would enable KMLP to transport up to 1,300,000 dekatherms per day (Dth/d) of natural gas from new Texas interconnections
for delivery to various points on the KMLP system.

The Texas Access Project would consist of the following facilities:

  • Installation of about 3 miles of 48-inch-diameter pipeline from Jefferson County, Texas to Cameron Parish, Louisiana (Mainline
    Extension);
    • Installation of two aboveground facilities with pig (1) assemblies at the beginning and terminus of the Mainline Extension;

  • Modification of KMLP's existing regulator and metering facilities at its existing Sabine Pass Metering Facility in Cameron
    Parish, Louisiana; and

  • Installation of a new interconnection with Louisiana LNG Gas Management LLC from KMLP's existing 42-inch-diameter mainline
    in Calcasieu Parish, Louisiana (Woodside Interconnect).
    The general location of the project facilities is shown in appendix 1. (2)

Land Requirements for Construction

Construction of the proposed facilities would disturb about 110.6 acres of land for the aboveground facilities and the pipeline.
Following construction, KMLP would maintain about 17.2 acres for permanent operation of the project's facilities, and the
remaining acreage would be restored and reverted to former uses. About 39 percent of the proposed pipeline route parallels
existing pipeline, utility, or road rights-of-way.

NEPA Process and the Environmental Document

Any environmental document issued by the Commission will discuss impacts that could occur as a result of the construction
and operation of the proposed project under the relevant general resource areas:

  • geology and soils;
  • water resources and wetlands;
  • vegetation and wildlife;
  • threatened and endangered species;
  • cultural resources;
  • land use;
  • air quality and noise; and
  • reliability and safety. Commission staff will also evaluate reasonable alternatives to the proposed project or portions of the project and make recommendations on how to lessen or avoid impacts on the various resource areas. Your comments will help Commission staff identify and focus on the issues that might have an effect on the human environment and potentially eliminate others from further study and discussion in the environmental document.

Following this scoping period, Commission staff will determine whether to prepare an Environmental Assessment (EA) or an Environmental
Impact Statement (EIS). The EA or the EIS will present Commission staff's independent analysis of the issues. If Commission
staff prepares an EA, a Notice of Schedule for the Preparation of an Environmental Assessment will be issued. The EA may be issued for an allotted public comment period. The Commission would consider timely comments
on the EA before making its decision regarding the proposed project. If Commission staff prepares an EIS, a Notice of Intent to Prepare an EIS/Notice of Schedule will be issued, which will open up an additional comment period. Staff will then prepare a draft EIS which will be issued
for public comment. Commission staff will consider all timely comments received during the comment period on the draft EIS
and revise the document, as necessary, before issuing a final EIS. Any EA or draft and final EIS will be available in electronic
format in the public record through eLibrary (3) and the Commission's natural gas environmental documents web page (https://www.ferc.gov/industries-data/natural-gas/environment/environmental-documents). If eSubscribed, you will receive instant email notification when the environmental document is issued.

With this notice, the Commission is asking agencies with jurisdiction by law and/or special expertise with respect to the
environmental issues of this project to formally cooperate in the preparation of the environmental document. (4) Agencies that would like to request cooperating agency status should follow the instructions for filing comments provided
under the Public Participation section of this notice.

Consultation Under Section 106 of the National Historic Preservation Act

In accordance with the Advisory Council on Historic Preservation's implementing regulations for section 106 of the National
Historic Preservation Act, the Commission is using this notice to initiate consultation with the applicable State Historic
Preservation Office(s), and to solicit their views and those of other government agencies, interested Indian tribes, and the
public on the project's potential effects on historic properties. (5) The environmental document for this project will document findings on the impacts on historic properties and summarize the
status of consultations under section 106.

Environmental Mailing List

The environmental mailing list includes federal, state, and local government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other interested parties; and local libraries and newspapers.
This list also includes all affected landowners (as defined in the Commission's regulations) who are potential right-of-way
grantors, whose property may be used temporarily for project purposes, or who own homes within certain distances of aboveground
facilities, and anyone who submits comments on the project and includes a mailing address with their comments. Commission
staff will update the environmental mailing list as the analysis proceeds to ensure that Commission notices related to this
environmental review are sent to all individuals, organizations, and government entities interested in and/or potentially
affected by the proposed project.

If you need to make changes to your name/address, or if you would like to remove your name from the mailing list, please complete
one of the following steps:

(1) Send an email to GasProjectAddressChange@ferc.gov stating your request. You must include the docket number CP26-136-000 in your request. If you are requesting a change to your
address, please be sure to include your name and the correct address. If you are requesting to delete your address from the
mailing list, please include your name and address as it appeared on this notice. This email address is unable to accept comments.

or

(2) Return the attached “Mailing List Update Form” (appendix 2).

Additional Information

Additional information about the project is available from the FERC website at www.ferc.gov using the eLibrary link. Click on the eLibrary link, click on “General Search” and enter the docket number in the “Docket
Number” field. Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or (866) 208-3676, or for TTY, contact (202) 502-8659. The eLibrary link also provides access to the texts of all formal documents
issued by the Commission, such as orders, notices, and rulemakings.

Public sessions or site visits will be posted on the Commission's calendar located at https://www.ferc.gov/news-events/events along with other related information.

(Authority: 18 CFR 2.1)

Dated: April 17, 2026. Debbie-Anne A. Reese, Secretary. [FR Doc. 2026-07836 Filed 4-21-26; 8:45 am] BILLING CODE 6717-01-P

Footnotes

(1) A “pig” is a tool that the pipeline company inserts into and pushes through the pipeline for cleaning the pipeline, conducting
internal inspections, or other purposes.

(2) The appendices referenced in this notice will not appear in the
Federal Register
. Copies of the appendices were sent to all those receiving this notice in the mail and are available at www.ferc.gov using the link called “eLibrary.” For instructions on connecting to eLibrary, refer to the last page of this notice. For assistance,
contact FERC at FERCOnlineSupport@ferc.gov or call toll free, (886) 208-3676 or TTY (202) 502-8659.

(3) For instructions on connecting to eLibrary, refer to the last page of this notice.

(4) Cooperating agency responsibilities are addressed in Section 107(a)(3) of NEPA (42 U.S.C. 4336(a)(3)).

(5) The Advisory Council on Historic Preservation's regulations are at Title 36, Code of Federal Regulations, Part 800. Those
regulations define historic properties as any prehistoric or historic district, site, building, structure, or object included
in or eligible for inclusion in the National Register of Historic Places.

Download File

Download

Get daily alerts for Regs.gov: Federal Energy Regulatory Commission

Daily digest delivered to your inbox.

Free. Unsubscribe anytime.

About this page

What is GovPing?

Every important government, regulator, and court update from around the world. One place. Real-time. Free. Our mission

What's from the agency?

Source document text, dates, docket IDs, and authority are extracted directly from FERC.

What's AI-generated?

The summary, classification, recommended actions, deadlines, and penalty information are AI-generated from the original text and may contain errors. Always verify against the source document.

Last updated

Classification

Agency
FERC
Published
March 3rd, 2026
Comment period closes
May 18th, 2026 (25 days)
Instrument
Notice
Branch
Executive
Legal weight
Non-binding
Stage
Final
Change scope
Substantive
Docket
CP26-136-000

Who this affects

Applies to
Energy companies Importers and exporters Government agencies
Industry sector
2111 Oil & Gas Extraction
Activity scope
Natural gas pipeline construction Environmental review process Public comment submission
Geographic scope
United States US

Taxonomy

Primary area
Energy
Operational domain
Regulatory Affairs
Topics
Environmental Protection Transportation

Get alerts for this source

We'll email you when Regs.gov: Federal Energy Regulatory Commission publishes new changes.

Free. Unsubscribe anytime.

You're subscribed!