Routine Rule Added Final

PSC Grants Jackson Purchase Energy Schedule Delay, Case 2026-00033

Favicon for psc.ky.gov Kentucky PSC Orders
Published
Detected
Email

Summary

The Kentucky Public Service Commission granted Jackson Purchase Energy Corporation's motion to amend the procedural schedule in Case No. 2026-00033. The utility's sole witness, CFO Meredith Kendall, had a previously scheduled obligation outside the United States until April 30, 2026, necessitating the schedule adjustments. The amended deadlines require initial information requests to Jackson Purchase Energy by May 1, 2026, and responses by May 11, 2026. The last day for parties to request a public hearing or submit a request for written-record determination is May 21, 2026.

Published by KY PSC on psc.ky.gov . Detected, standardized, and enriched by GovPing. Review our methodology and editorial standards .

About this source

The Kentucky Public Service Commission regulates investor-owned utilities and rural electric cooperatives in Kentucky: electricity, natural gas, water, wastewater, and select telephone services. Orders publish as the commission acts on rate cases, complaints, construction certificate applications, and tariff amendments. Around 125 orders a month. Kentucky is a traditionally regulated state (no retail choice), so the PSC's rate-case decisions directly set what customers pay for utility service. Watch this if you advise utility clients in Kentucky, follow Duke Energy Kentucky or Kentucky Power regulatory activity, intervene in rate cases, or track rural electric cooperative regulatory matters.

What changed

The Kentucky Public Service Commission issued an order granting Jackson Purchase Energy Corporation's motion to amend the procedural schedule in Case No. 2026-00033. The amendment extends two deadlines: initial requests for information to Jackson Purchase Energy are now due by May 1, 2026, and Jackson Purchase Energy's responses are now due by May 11, 2026. The order was entered on April 24, 2026.

The primary impact is procedural: parties to this rate case proceeding (Case No. 2026-00033) must adjust their workflow timelines accordingly. Jackson Purchase Energy must ensure responses are filed by May 11. Other parties and intervenors should note the May 21 deadline for requesting a public hearing or requesting the matter be decided on the written record. No substantive regulatory obligations or compliance requirements are created by this scheduling order.

Archived snapshot

Apr 25, 2026

GovPing captured this document from the original source. If the source has since changed or been removed, this is the text as it existed at that time.

COMMONWEALTH OF KENTUCKY BEFORE THE PUBLIC SERVICE COMMISSION In the Matter of:

O R D E R On April 8, 2026, Jackson Purchase Energy Corporation (Jackson Purchase Energy) filed a motion seeking to amend the Commission's procedural schedule that was issued on April 8, 2026. In support of Jackson Purchase Energy's request, it stated that its sole witness, Meredith Kendall, who is the chief financial officer and vice-president of finance and accounting, had a previously scheduled obligation outside of the United States until April 30, 2026. Jackson Purchase Energy requested that the Commission amend the procedural schedule in two ways. First, that the initial request for information be issued to Jackson Purchase Energy no later than May 1, 2026, instead of April 24, 2026, as originally ordered; and secondly, that Jackson Purchase Energy's responses be due no later than May 11, 2026, instead of May 1, 2026, as originally ordered. Based on the foregoing, the Commission finds that Jackson Purchase Energy's motion should be granted and that the procedural schedule issued on April 8, 2026, should be amended. The procedural schedule should be amended to require initial requests for information to Jackson Purchase Energy be issued no later than May 1, 2026,

ELECTRONIC APPLICATION OF JACKSON ) PURCHASE ENERGY CORPORATION FOR ) CASE NO. AUTHORITY TO EXTEND ITS DEBT LIMIT; ) 2026-00033 ESTABLISH A PERPETUAL LINE OF CREDIT; ) AND ENTER DEBT OBLIGATIONS

and that Jackson Purchase Energy respond to any initial requests for information no later than May 11, 2026. IT IS THEREFORE ORDERED that:

  1. Jackson Purchase Energy's April 8, 2026 motion is granted.
  2. All initial requests for information to Jackson Purchase Energy shall be filed
    no later than May 1, 2026.

  3. Jackson Purchase Energy shall file responses to initial requests for
    information no later than May 11, 2026.

  4. The last day for parties to request a public hearing or submit a request for
    the matter to be decided based upon the written record will be May 21, 2026.

  5. All portions of the Commission's April 8, 2026 Order not in conflict with this

Order shall remain in effect.

-2- Case No. 2026-00033

Entered on this 24th day of April, 2026. PUBLIC SERVICE COMMISSION

___________________________ Angie Hatton Chair

___________________________ Mary Pat Regan Commissioner

___________________________ Andrew W. Wood Commissioner

ATTEST:

______________________ Linda C. Bridwell, PE Executive Director

Case No. 2026-00033

Service List for 2026-00033

  • Allyson Honaker Honaker Law Office, PLLC
    1795 Alysheba Way Suite 1203 Lexington, KY 40509

  • Jackson Purchase Energy Corporation 6525 US Highway 60 W Paducah, KY 42001

  • Greg Grissom Jackson Purchase Energy Corporation 6525 US Highway 60 W Paducah, KY 42001

  • Heather Temple Honaker Law Office, PLLC 1795 Alysheba Way Suite 1203 Lexington, KY 40509

  • Meredith Kendall Jackson Purchase Energy Corporation 6525 US Highway 60 W Paducah, KY 42001

  • Meredith L. Cave Honaker Law Office, PLLC 1795 Alysheba Way Suite 1203
    Lexington, KY 40509

  • Denotes served by Email

Get daily alerts for Kentucky PSC Orders

Daily digest delivered to your inbox.

Free. Unsubscribe anytime.

About this page

What is GovPing?

Every important government, regulator, and court update from around the world. One place. Real-time. Free. Our mission

What's from the agency?

Source document text, dates, docket IDs, and authority are extracted directly from KY PSC.

What's AI-generated?

The summary, classification, recommended actions, deadlines, and penalty information are AI-generated from the original text and may contain errors. Always verify against the source document.

Last updated

Classification

Agency
KY PSC
Published
April 24th, 2026
Instrument
Rule
Branch
Executive
Legal weight
Binding
Stage
Final
Change scope
Minor
Docket
2026-00033

Who this affects

Applies to
Energy companies
Industry sector
2210 Electric Utilities
Activity scope
Utility rate proceedings Procedural scheduling
Geographic scope
US-KY US-KY

Taxonomy

Primary area
Energy
Operational domain
Compliance

Get alerts for this source

We'll email you when Kentucky PSC Orders publishes new changes.

Free. Unsubscribe anytime.

You're subscribed!