Scout V Hugoton Gathering LP and Pan-Hugoton Gathering Company LLC Joint Application Under Natural Gas Act Sections 7(b) and 7(c)

Favicon for www.federalregister.gov FR: Energy Department
Published
Detected
Email

Summary

The Federal Energy Regulatory Commission published notice of a joint application from Scout V Hugoton Gathering, LP and Pan-Hugoton Gathering Company LLC under Sections 7(b) and 7(c) of the Natural Gas Act. Scout seeks permission to abandon by sale approximately 249.1 miles of pipeline and related facilities (West Hugoton System). PHGC seeks a certificate to own and operate the system, provide transportation services under existing tariff terms, and obtain blanket certificates for transportation and routine construction activities. The Commission establishes an intervention deadline of May 6, 2026.

Published by Energy Department on federalregister.gov . Detected, standardized, and enriched by GovPing. Review our methodology and editorial standards .

What changed

FERC published notice of a joint application under the Natural Gas Act requesting authorization for the sale and transfer of ownership of approximately 249.1 miles of natural gas pipeline (West Hugoton System) from Scout V Hugoton Gathering, LP to Pan-Hugoton Gathering Company LLC, along with associated blanket certificate requests for transportation services and routine construction activities.

Affected parties including other pipeline operators, shippers, landowners, and state or federal agencies that wish to participate in this proceeding must file motions to intervene by the May 6, 2026 deadline. Protests may be filed in accordance with Commission regulations, and comments supporting or opposing the application may be submitted electronically via the Commission's eComment or eFiling systems. The Commission will conduct environmental review within 90 days of this notice.

What to do next

  1. File motions to intervene or protests on or before 5:00 p.m. Eastern Time on May 6, 2026

Archived snapshot

Apr 18, 2026

GovPing captured this document from the original source. If the source has since changed or been removed, this is the text as it existed at that time.

Notice

Scout V Hugoton Gathering, LP, Pan-Hugoton Gathering Company LLC; Notice of Application and Establishing Intervention Deadline

A Notice by the Federal Energy Regulatory Commission on 04/20/2026

  • PDF

  • Document Details

- Table of Contents

  • Public Comments
  • Regulations.gov Data

- Sharing

  • Print
  • Document Statistics
  • Other Formats
  • Public Inspection Published Document: 2026-07657 (91 FR 20992) Document Headings ###### Department of Energy
Federal Energy Regulatory Commission
  1. [Docket No. CP26-183-000] Take notice that on April 2, 2026, Scout V Hugoton Gathering, LP (Scout), 13800 Montfort Drive, Dallas, Texas 75240, and Pan-Hugoton Gathering Company LLC (PHGC), 370 17th Street, Suite 2900, Denver, Colorado, 80202, filed a joint application under sections 7(b) and 7(c) of the Natural Gas Act (NGA) and Part 157 of the Commission's regulations requesting (1) permission for Scout to abandon, by sale, approximately 249.1 miles of 1-inch to 26-inch-diameter pipeline and related facilities and appurtenances (West Hugoton System); and (2) a certificate for PHGC to own and operate the West Hugoton System, and to provide transportation services thereupon under the same rates, terms, and conditions as under Scout's currently effective tariff. PHGC also requests a blanket certificate pursuant to Part 284 of the Commission's regulations, authorizing PHGC to transport natural gas for others on a firm and interruptible basis, and a blanket certificate pursuant to Part 157 of the Commission's regulations, authorizing PHGC to perform certain routine construction, operation, and abandonment activities, all as more fully set forth in the application which is on file with the Commission and open for public inspection.

In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission's Home Page (http://www.ferc.gov). From the Commission's Home Page on the internet, this information is available on eLibrary. The full text of this document is available on eLibrary in PDF and Microsoft Word format for viewing, printing, and/or downloading. To access this document in eLibrary, type the docket number excluding the last three digits of this document in the docket number field.

User assistance is available for eLibrary and the Commission's website during normal business hours from FERC Online Support at (202) 502-6652 (toll free at 1-866-208-3676) or email at ferconlinesupport@ferc.gov, or the Public Reference Room at (202) 502-8371, TTY (202) 502-8659. Email the Public Reference Room at public.referenceroom@ferc.gov.

Any questions regarding the proposed project should be directed to John Phelan, Counsel & Chief Compliance Officer, Scout Energy Management LLC, 13800 Montfort Drive, Dallas, Texas 75240, by phone at (469) 200-0853, or by email at John.Phelan@scoutep.com and Craig Gleaton, General Counsel, Jonah Energy Parent, LLC, 370 17th Street, Suite 2900, Denver, Colorado 80202, by phone at (720) 577-1234, or by email at craig.gleaton@jonahenergy.com.

Pursuant to section 157.9 of the Commission's Rules of Practice and Procedure, [1 ] within 90 days of this Notice the Commission staff will either: complete its environmental review and place it into the Commission's public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff's issuance of the final environmental impact statement (FEIS) or environmental assessment (EA) for this proposal. The filing of an EA in the Commission's public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff's FEIS or EA.

Public Participation

There are three ways to become involved in the Commission's review of this project: you can file comments on the project, you can protest the filing, and you can file a motion to intervene in the proceeding. There is no fee or cost for filing comments or intervening. The deadline for filing a motion to intervene is 5:00 p.m. Eastern Time on May 6, 2026. How to file protests, motions to intervene, and comments is explained below.

For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, contact the Office of Public Participation (OPP) at (202) 502-6595 or OPP@ferc.gov.

Comments

Any person wishing to comment on the project may do so. Comments may include statements of support or objections to the project as a whole or specific aspects of the project. The more specific your comments, the more useful they will be.

Protests

Pursuant to sections 157.10(a)(4) [2 ] and 385.211 [3 ] of the Commission's regulations under the NGA, any person [4 ] may file a protest to the application. Protests must comply with the requirements specified in section ( printed page 20993) 385.2001 [5 ] of the Commission's regulations. A protest may also serve as a motion to intervene so long as the protestor states it also seeks to be an intervenor.

To ensure that your comments or protests are timely and properly recorded, please submit your comments on or before 5:00 p.m. Eastern Time on May 6, 2026.

There are three methods you can use to submit your comments or protests to the Commission. In all instances, please reference the Project docket number CP26-183-000 in your submission.

(1) You may file your comments electronically by using the eComment feature, which is located on the Commission's website at www.ferc.gov under the link to Documents and Filings. Using eComment is an easy method for interested persons to submit brief, text-only comments on a project;

(2) You may file your comments or protests electronically by using the eFiling feature, which is located on the Commission's website (www.ferc.gov) under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on “eRegister.” You will be asked to select the type of filing you are making; first select “General” and then select “Comment on a Filing”; or

(3) You can file a paper copy of your comments or protests by mailing them to the following address below. Your written comments must reference the Project docket number (CP26-183-000).

To file via USPS: Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426.

To file via any other courier: Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852.

The Commission encourages electronic filing of comments (options 1 and 2 above) and has eFiling staff available to assist you at (202) 502-8258 or FercOnlineSupport@ferc.gov.

Persons who comment on the environmental review of this project will be placed on the Commission's environmental mailing list, and will receive notification when the environmental documents (EA or EIS) are issued for this project and will be notified of meetings associated with the Commission's environmental review process.

The Commission considers all comments received about the project in determining the appropriate action to be taken. However, the filing of a comment alone will not serve to make the filer a party to the proceeding. To become a party, you must intervene in the proceeding. For instructions on how to intervene, see below.

Interventions

Any person, which includes individuals, organizations, businesses, municipalities, and other entities, [6 ] has the option to file a motion to intervene in this proceeding. Only intervenors have the right to request rehearing of Commission orders issued in this proceeding and to subsequently challenge the Commission's orders in the U.S. Circuit Courts of Appeal.

To intervene, you must submit a motion to intervene to the Commission in accordance with Rule 214 of the Commission's Rules of Practice and Procedure [7 ] and the regulations under the NGA [8 ] by the intervention deadline for the project, which is 5:00 p.m. Eastern Time on May 6, 2026. As described further in Rule 214, your motion to intervene must state, to the extent known, your position regarding the proceeding, as well as your interest in the proceeding. For an individual, this could include your status as a landowner, ratepayer, resident of an impacted community, or recreationist. You do not need to have property directly impacted by the project in order to intervene. For more information about motions to intervene, refer to the FERC website at https://www.ferc.gov/​resources/​guides/​how-to/​intervene.asp.

There are two ways to submit your motion to intervene. In both instances, please reference the Project docket number CP26-183-000 in your submission.

(1) You may file your motion to intervene by using the Commission's eFiling feature, which is located on the Commission's website (www.ferc.gov) under the link to Documents and Filings. New eFiling users must first create an account by clicking on “eRegister.” You will be asked to select the type of filing you are making; first select “General” and then select “Intervention.” The eFiling feature includes a document-less intervention option; for more information, visit https://www.ferc.gov/​docs-filing/​efiling/​document-less-intervention.pdf.; or

(2) You can file a paper copy of your motion to intervene, along with three copies, by mailing the documents to the address below. Your motion to intervene must reference the Project docket number CP26-183-000.

To file via USPS: Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426.

To file via any other courier: Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852.

The Commission encourages electronic filing of motions to intervene (option 1 above) and has eFiling staff available to assist you at (202) 502-8258 or FercOnlineSupport@ferc.gov.

Protests and motions to intervene must be served on the applicant either by mail at: John Phelan, Counsel & Chief Compliance Officer, Scout Energy Management LLC, 13800 Montfort Drive, Dallas, Texas 75240, or by email (with a link to the document) at John.Phelan@scoutep.com and Craig Gleaton, General Counsel, Jonah Energy Parent, LLC, 370 17th Street, Suite 2900, Denver, Colorado 80202, or by email (with a link to the document) at craig.gleaton@jonahenergy.com. Any subsequent submissions by an intervenor must be served on the applicant and all other parties to the proceeding. Contact information for parties can be downloaded from the service list at the eService link on FERC Online. Service can be via email with a link to the document.

All timely, unopposed [9 ] motions to intervene are automatically granted by operation of Rule 214(c)(1). [10 ] Motions to intervene that are filed after the intervention deadline are untimely, and may be denied. Any late-filed motion to intervene must show good cause for being late and must explain why the time limitation should be waived and provide justification by reference to factors set forth in Rule 214(d) of the Commission's Rules and Regulations. [11 ] A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies (paper or electronic) of all documents filed by the applicant and by all other parties.

Tracking the Proceeding

Throughout the proceeding, additional information about the project will be available from OPP at (202) 502-6595 or on the FERC website at ( printed page 20994) www.ferc.gov using the “eLibrary” link as described above. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings.

In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. For more information and to register, go to www.ferc.gov/​docs-filing/​esubscription.asp.

Intervention Deadline: 5:00 p.m. Eastern Time on May 6, 2026.

(Authority: 18 CFR 2.1)

Dated: April 15, 2026.

Debbie-Anne A. Reese,

Secretary.

Footnotes

  1. 18 CFR 157.9.

Back to Citation 2. 18 CFR 157.10(a)(4).

Back to Citation 3. 18 CFR 385.211.

Back to Citation 4.

 Persons include individuals, organizations, businesses, municipalities, and other entities. 18 CFR 385.102(d).

Back to Citation 5. 18 CFR 385.2001.

Back to Citation 6. 18 CFR 385.102(d).

Back to Citation 7. 18 CFR 385.214.

Back to Citation 8. 18 CFR 157.10.

Back to Citation 9.

 The applicant has 15 days from the submittal of a motion to intervene to file a written objection to the intervention.

Back to Citation 10. 18 CFR 385.214(c)(1).

Back to Citation 11. 18 CFR 385.214(b)(3) and (d).

Back to Citation [FR Doc. 2026-07657 Filed 4-17-26; 8:45 am]

BILLING CODE 6717-01-P

Published Document: 2026-07657 (91 FR 20992)

CFR references

18 CFR 157 18 CFR 385.2001 18 CFR 385.211

Named provisions

Section 7(b) of the Natural Gas Act Section 7(c) of the Natural Gas Act Part 157 of the Commission's Regulations Part 284 of the Commission's Regulations

Get daily alerts for FR: Energy Department

Daily digest delivered to your inbox.

Free. Unsubscribe anytime.

About this page

What is GovPing?

Every important government, regulator, and court update from around the world. One place. Real-time. Free. Our mission

What's from the agency?

Source document text, dates, docket IDs, and authority are extracted directly from Energy Department.

What's AI-generated?

The summary, classification, recommended actions, deadlines, and penalty information are AI-generated from the original text and may contain errors. Always verify against the source document.

Last updated

Classification

Agency
Energy Department
Published
April 20th, 2026
Compliance deadline
May 6th, 2026 (18 days)
Instrument
Notice
Legal weight
Non-binding
Stage
Final
Change scope
Minor
Document ID
91 FR 20992 / Docket No. CP26-183-000
Docket
Docket No. CP26-183-000

Who this affects

Applies to
Energy companies
Industry sector
2111 Oil & Gas Extraction
Activity scope
Pipeline certificate application Natural gas transportation Blanket certificate request
Geographic scope
United States US

Taxonomy

Primary area
Energy
Operational domain
Regulatory Affairs
Topics
Environmental Protection Infrastructure

Get alerts for this source

We'll email you when FR: Energy Department publishes new changes.

Free. Unsubscribe anytime.

You're subscribed!