Shyam Narayan And Bros vs P N Writer And Company Pvt Ltd - Arbitration Petition
Summary
The Bombay High Court is reviewing an arbitration petition challenging an arbitral award dated January 7, 2013. The core issue is whether the rejection of the petitioner's claims due to being barred by limitation warrants judicial interference. The case involves a dispute over excavation work and delays in its completion.
What changed
The Bombay High Court is adjudicating Arbitration Petition No. 526 of 2015, which challenges an Arbitral Award issued on January 7, 2013. The central point of contention is the arbitral tribunal's decision to dismiss the petitioner's claims on the grounds that they were time-barred by the statute of limitations. The underlying dispute stems from excavation work performed by the petitioner for the respondent, involving issues of delay and accountability for project completion.
This judicial review requires a careful examination of the limitation period applicable to the claims presented in the arbitration. Compliance officers should note that the court's decision on whether to uphold or set aside the arbitral award will have significant implications for the finality of arbitration decisions and the interpretation of limitation periods in contractual disputes. The outcome could influence how similar claims are assessed in future arbitration proceedings.
What to do next
- Review case law on limitation periods for arbitration claims in India.
- Assess the factual basis for the arbitral tribunal's finding of limitation.
- Prepare arguments regarding the application of Section 34 of the Arbitration and Conciliation Act, 1996.
Source document (simplified)
Select the following parts of the judgment
| Facts | Issues |
| Petitioner's Arguments | Respondent's Arguments |
| Analysis of the law | Precedent Analysis |
| Court's Reasoning | Conclusion |
For entire doc: Unmark Mark View how precedents are cited in this document View precedents: Unmark Mark View only precedents: Unmark Mark Select precedent ... Filter precedents by opinion of the court
| Accepted by Court |
## Unlock Advanced Research with PRISM AI
Integrated with over 4 crore judgments and laws — designed for legal practitioners, researchers, students and institutions
- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc -... Upgrade to Premium [Cites 14, Cited by 0 ] ### Bombay High Court
Shyam Narayan And Bros vs P N Writer And Company Pvt Ltd. on 23 March, 2026
2026:BHC-OS:6929
Judgment-ARBP-526-2015-F.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
Digitally
signed by
CHAITANYA
CHAITANYA ASHOK
ASHOK
JADHAV
JADHAV
Date:
ARBITRATION PETITION NO. 526 OF 2015
2026.03.23
15:31:37
+0530
Shyam Narayan and Bros. ...Petitioner
Versus
P N. Writer and Company Pvt. Ltd. ...Respondent
Mr. Madhuranjan Shetty, for Petitioner.
Mr. Hasmit Trivedi a/w. Mr. Neeraj Salodkar i/b. Praxis
Legal, for Respondent.
CORAM : SOMASEKHAR SUNDARESAN, J.
DATE : MARCH 23, 2026.
JUDGEMENT : Context and Factual Background:
- This is a Petition filed under Section 34 of the Arbitration and
Conciliation Act, 1996 ("the Act"), challenging an Arbitral Award dated
January 07, 2013, passed by the Arbitral Tribunal ("Impugned
Award"). The core issue that arises in this matter is whether the
rejection of the claims on the ground that it was barred by limitation,
deserves interference.
March 23, 2026
Chaitanya
Judgment-ARBP-526-2015-F.doc
- The Impugned Award relates to certain excavation work
carried out by the Petitioner, Shyam Narayan and Brothers ("Shyam"),
upon being engaged by the Respondent, P N. Writer and Company Pvt.
Ltd. ("Writer"), pursuant to a Work Order.
- The Work Order was for a value of Rs.49,61,100/- with a
stipulated commencement date of October 27, 2005, with the work
having to be completed within a period of 45 days, i.e. by December 11,
- Eventually, additional work was assigned and the cost of the work
was enhanced to Rs.65,28,565/-. It is common ground that the work
could not be completed by December 11, 2005, and was instead
completed on March 15, 2006. The conflict between the parties relates
to the reasons for the delay and the allocation of accountability for what
caused such delay.
- According to Shyam, once the work was certified by
consultants appointed by Writer, payment was to be released for the
work done. The specifications and instructions for the work were also
issued by such consultants. After completion of the work on March 15,
2006, the final bill dated March 18, 2006 was raised, and the
consultants are said to have certified the final bill for an amount of
Rs.65,28,565/-. This is also said to have been confirmed by the
consultants in their letter dated November 15, 2008.
March 23, 2026
Chaitanya
Judgment-ARBP-526-2015-F.doc
- Writer, however, disputed the bill, which led to arbitration.
Writer had made part payments in the sum of Rs.4,84,997/- on October
11, 2005, and another payment of Rs.24,71,828/- on December 28,
2005, pursuant to two running bills raised by Shyam on Writer. A TDS
Certificate dated March 07, 2006, was issued by Writer indicating that
an amount of Rs. 11,52,256/- was paid by Writer to Shyam on February
8, 2006, but it is Shyam's contention that such an amount was actually
not released by Writer.
- Therefore, the total amount received by Shyam from Writer
was to the tune of Rs. 30,50,387/- and the balance amount of Rs.
34,78,178/- pursuant to the final bill was the subject matter of the
dispute. Shyam also claimed a refund of the earnest money deposited in
the sum of Rs.1,50,000/- and the retention amount of Rs.5,92,929/-
along with interest.
- On March 06, 2009, Shyam is said to have been approached
by Writer and it is contended that upon the request of an officer of
Writer, a copy of the final bill dated November 10, 2006, was handed
over to Writer. Thereafter, correspondence followed between the
parties, and Shyam wrote several letters to Writer, including letters
dated July 8, 2010 and September 18, 2010, demanding the balance
payment. In response, Shyam contends that Writer's officers invited
March 23, 2026
Chaitanya
Judgment-ARBP-526-2015-F.doc
Shyam for discussions for settlement of claims on October 1, 2010, and
at that meeting, certain calculations were scribbled, which, Shyam
contends, amounted to an admission of liability of Rs.23,95,618/-
towards the balance payment payable to Shyam.
- This meeting is said to have been recorded by Shyam in a
letter dated October 4, 2010, objecting to the calculations made,
protesting against the wrongful recovery of Rs.7,50,000/- towards
liquidated damages and other deductions of Rs.4,82,560/-. Shyam is
said to have threatened legal action, which led to Writer issuing a denial
in a letter dated January 28, 2011.
- A notice for winding up was issued by Shyam, and Company
Petition No. 359 of 2011 was filed in this Court on July 15, 2011, seeking
the winding up of Writer. Writer, thereafter, wrote a letter dated
September 22, 2011, indicating liquidated damages to the tune of
Rs.~47.50 lakhs and alluding to the existence of an arbitration clause in
the tender conditions. The certified balance amount of Rs.~23.95 lakhs
as stated to have been certified by the consultants was not disputed, but
Writer also raised a claim for liquidated damages of Rs.~47.50 lakhs.
March 23, 2026
Chaitanya
Judgment-ARBP-526-2015-F.doc
- This standoff led to invocation of arbitration by Shyam on
October 24, 2011, pursuant to which a three-member Arbitral Tribunal
was constituted to deal with the proceedings.
- At the threshold, Writer took up a defence that the claims
were hopelessly barred by limitation and called upon the Learned
Arbitral Tribunal to rule on its own jurisdiction in terms of Section 16 of
the Act. The Learned Arbitral Tribunal allowed the parties to lead
evidence in relation to certain disputed documents, and thereafter
placed the matter for arguments. According to Shyam, only the [Section
16](https://indiankanoon.org/doc/675839/) Application ought to have been considered, but the Learned Arbitral
Tribunal went on to deal with the matter in its entirety and passed the
Impugned Award on merits without rendering a separate decision on
the Application made under Section 16 of the Act. This course of action
was challenged under Section 37 of the Act; however, the challenge was
rejected on the premise that it ought to be filed under Section 34 of the
Act, leading to the present proceedings.
Contentions of the Parties:
- I have heard Mr. Madhuranjan Shetty, Learned Advocate for
Shyam and Mr. Hasmit Trivedi, Learned Advocate for Writer.
March 23, 2026
Chaitanya
Judgment-ARBP-526-2015-F.doc
- Shyam would contend that the Impugned Award is wholly
illegal since the Learned Arbitral Tribunal did not deal with the
jurisdictional question under Section 16 first, and instead went on to
pass the Impugned Award. According to him, the Tribunal was under a
legal obligation to decide the preliminary issue of jurisdiction first, and
only then proceed to pass the Award on merits in the matter. This, as
contended, would constitute an absence of a judicial approach.
- According to Mr. Shetty, the first unequivocal rejection of
Shyam's claims took place only on January 28, 2011, because this is the
first time that Writer used express language indicating its unwillingness
to pay even the amount certified by the consultants and earlier
admitted, and instead, offered a sum of Rs.~23.95 lakhs after
discussions with Shyam. He would submit that the right to sue accrued
only when such a complete repudiation took place, but the Learned
Arbitral Tribunal has erroneously taken a view that the right to sue had
accrued when the final bill was defaulted upon.
- It is also contended that Article 18 of the Limitation Act, 1963 (" Limitation Act ") would have no application to the facts of the case,
since the tender conditions themselves provided a timeline for payment
by insisting on certification by the consultants upon completion, and the
appropriate Article would be Article 113 of the Limitation Act, and the
March 23, 2026
Chaitanya
Judgment-ARBP-526-2015-F.doc
Learned Arbitral Tribunal was in error in not accepting this principle as
well. The starting point, according to Mr. Shetty, was wrongly held to be
the date of certification of the bill (November 10, 2006) rather than the
date of unequivocal denial of the bill (January 28, 2011). Mr. Shetty
would submit that the Learned Arbitral Tribunal, by not considering the
fact that the bills were not finalised, ought to have held that the claim
made by Shyam on July 8, 2010 was the date on which the cause of
action accrued, and therefore, it is from this date that the question of
limitation would have to be computed.
Analysis and Findings:
- The Impugned Award is a short one, running into six pages,
essentially holding against Shyam, primarily, on the ground of
extraordinary delay. The Learned Arbitral Tribunal noted that the
certification of the final bill by the consultants had been effected on
November 10, 2006, which was said to have been reaffirmed
subsequently on November 15, 2008. The Learned Arbitral Tribunal
noticed the contention on behalf of Writer that when one counts the
limitation of three years from November 10, 2006, the invocation of
arbitration took place only on October 24, 2011, which is nearly five
years after the certification of the final bill by the Consultants.
March 23, 2026
Chaitanya
Judgment-ARBP-526-2015-F.doc
- The Learned Arbitral Tribunal noticed the affidavit of one
Mr. Kaustubh Raikar, Executive Director of the Consultants, which
confirmed that he had issued a second certification on November 15,
- However, the said affidavit clearly asserted that Mr. Raikar would
not make himself available for cross-examination. Therefore, the
Learned Arbitral Tribunal specifically gave another opportunity to
Shyam to enable Mr. Raikar to attend, regardless of his earlier position
of not being willing to be subjected to cross-examination, but this was
not availed of by Shyam.
- The Learned Arbitral Tribunal took a view that under [Section
18](https://indiankanoon.org/doc/85586/) of the Limitation Act, intermittent letters dated October 13, 2008,
and November 15, 2008, the receipt of which was denied by Writer, in
any case, would not lead to an acknowledgment of liability on the part of
Writer. The Learned Arbitral Tribunal, upon appreciation of evidence,
came to the view that it was not convinced of these letters actually
having been served upon Writer. Yet, looking into their contents, the
Learned Arbitral Tribunal came to a view that the letters do not entail
any acknowledgment of liability and, therefore, the provisions of [Section
18](https://indiankanoon.org/doc/85586/) would not have any application, for extending the date from which
the clock of limitation must start ticking.
March 23, 2026
Chaitanya
Judgment-ARBP-526-2015-F.doc
- The Learned Arbitral Tribunal also examined the contention
that the entitlement to payment would commence only after the
Consultants certify the bill. This is precisely why the Learned Arbitral
Tribunal took the view that limitation must be computed from the date
on which the Consultants certified the final bill, namely November 10,
2006, and therefore held that the limitation period of three years
expired on November 10, 2009.
- According to Shyam, Article 113 of the Limitation Act must
apply, and towards the same, certain decisions were cited. However, the
Learned Arbitral Tribunal took the view that the period of limitation for
arbitration would start only when the dispute regarding arbitration is
first raised by the parties. Applying Article 113, the right to sue accrued
when Writer disputed and denied payment even after the certification
by the consultants on November 10, 2006, and the finding that the
claim was hopelessly barred by limitation cannot be faulted.
- Even if the reference to arbitration proceedings may not be
barred by limitation with reference to the invocation, whether the
underlying claims are barred by limitation would have reference to the
accrual of the underlying cause of action, and this was held against
Shyam. This approach cannot be faulted.
March 23, 2026
Chaitanya
Judgment-ARBP-526-2015-F.doc
- The Learned Arbitral Tribunal took the view, rightly in my
view, that the right to sue accrued right after the Consultants certified
the final bill and despite such certification, Writer was denying its
obligation to pay; therefore, the cause of action accrued from that point
of time. Arbitration was admittedly invoked only on October 24, 2011.
This was five years after the cause of action for recovery of the final bill
had accrued on November 10, 2006.
- Having examined the material on record with the assistance
of Learned Advocates for the parties, it is also apparent that on the face
of it, the contentions raised by Shyam before the Learned Arbitral
Tribunal have been squarely examined and exhaustively dealt with, with
particular regard to the facet of limitation. Necessarily, limitation was a
mixed question of fact and law for the Learned Arbitral Tribunal, and on
the basis of the evidence available before the Arbitral Tribunal, the
Tribunal, being the master of the evidence, has examined the relevant
contents of the evidence and returned a finding.
- The test for this Court, in exercise of jurisdiction under Section 34 of the Act, is to see whether in doing so, the Tribunal has
ignored any vital evidence or whether the Tribunal has taken into
account any extraneous facet as relevant for consideration. The Tribunal
has indeed tested the communications claimed to have been issued in
March 23, 2026
Chaitanya
Judgment-ARBP-526-2015-F.doc
the interregnum. The said letters dated October 13, 2008, and
November 15, 2008, have been rightly held not to constitute any
acknowledgment of liability on Writer's part. Such a finding is quite
logical and reasonable, and it could not be possible for this Court to
second guess and interpret the same on the basis of its own assessment
of how such correspondence should be read.
- That apart, when it is claimed that the consultants issued
another certification on November 15, 2008, it ought to have been
necessary for Shyam to produce the Consultant for cross-examination.
In any case, the basis for a second certification of the same work done
would not result in the accrual clock being reset, unless the parties had
agreed to have some facet re-examined and that led to the second
certification. Even if Mr. Kaustubh Raikar was unwilling to come for
cross-examination, recourse could have been had to Section 27 of the
Act, to have a witness summons issued to Mr. Raikar, particularly when
the affidavit filed by him was sought to be pressed into service by Shyam
in the arbitration proceedings. When Shyam, of its own accord, was
unwilling to have its witness, i.e., Mr. Raikar, step into the box to defend
his affidavit and have the same tested in the course of the arbitration
proceedings, the view taken by the Learned Arbitral Tribunal in relation
March 23, 2026
Chaitanya
Judgment-ARBP-526-2015-F.doc
to resetting the date to November 15, 2008 cannot be lightly interfered
with.
- As regards the refund of the earnest money deposit, the same,
having fallen due on May 07, 2005, was held to be barred by limitation
by 2011 when the claim was made. The Learned Arbitral Tribunal went
on to deal with the return of the retention amount. Shyam's pleadings
indicated that these amounts were due from September 15, 2006.
- The issue of retention money also came up for consideration.
It was contended that 50% was to be released along with the final bill
and the balance 50% was to be released after the defect liability period
of one year from the issue of the final completion certificate. Relying on
the second purported certification claimed by Shyam, it was contended
that the claim for at least 50% of the retention amount was not barred
by limitation. However, having examined the work order that was
actually issued by Writer to Shyam, the Arbitral Tribunal noted that the
work order provided for 10% of the retention amount having to be given
against a bank guarantee for six months after completion and handover.
The Arbitral Tribunal returned a finding that the refund of the retention
amount is covered by the work order and that it was due after six
months from the completion of the contract, which indeed is consistent
with the pleadings made by Shyam in the arbitration proceedings.
March 23, 2026
Chaitanya
Judgment-ARBP-526-2015-F.doc
- Even if the tender conditions were applied (ignoring the work
order), considering that the work had been completed by March 15,
2006, which is a stated date of completion asserted by Shyam, the
period for computing the deadline for refund of retention money ought
to be computed from that date, and one year from such date would lead
to the deadline being March 15, 2007. The claim, therefore, applying a
period of three years, was held to be alive until March 15, 2010, but the
arbitration was invoked only in October 2011, thereby resulting in this
claim being barred by limitation.
- Finally, the Learned Arbitral Tribunal held that claims in
relation to loss suffered by Shyam because of a delay occasioned by
Writer constituted a claim for compensation for breach of contract, and
in this regard, it was held that Article 55 of the Limitation Act would
apply. As the contract had been completed on March 15, 2006, any
claim for compensation on account of delay ought to be computed from
March 15, 2006, and on this ground too, the claim for compensation in
view of delay was dismissed as being barred by limitation.
- As a result, it was stated that the claim for costs too would not
survive, since each of the claims made in the matter stood dismissed on
the ground of limitation.
March 23, 2026
Chaitanya
Judgment-ARBP-526-2015-F.doc
- Having examined the record and the notes of the settlement
meeting pressed into service by Mr. Shetty, it is apparent that the
unanimous decision of the three-member Learned Arbitral Tribunal
does not call for interference. The findings on limitation, even as a
mixed question of fact and law, are logical and reasoned. The
interpretation of evidence does not lend itself to a finding that any vital
evidence was ignored. The interpretation of law is in line with the
declared position in law.
Scope 0f Review:
- It is now well settled in the law, and repeatedly iterated by
the Supreme Court, that the Section 34 Court must not lightly interfere
with arbitral awards. The scope of review by the Section 34 Court is also
well covered in multiple judgements of the Supreme Court including
Dyna Technologies1, Associate Builders2, Ssyangyong3,
Konkan Railway4 and OPG Power5. To avoid prolixity, I do not
think it necessary to burden this judgement with quotations from these
judgements. Suffice it to say (to extract from just one of the foregoing),
in Dyna Technologies, the Supreme Court held thus:
1 Dyna Technologies Private Limited v. Crompton Greaves Ltd - (2019) 20 SCC 1
2 Associate Builders vs. Delhi Development Authority - (2015) 3 SCC 49
3 Ssangyong Engineering & Construction Co. Ltd. v. National Highways Authority of
India - (2019) 15 SCC 131
4 Konkan Railways v. Chenab Bridge Project Undertaking - 2023 INSC 742
5 OPG Power vs. Enoxio - (2025) 2 SCC 417March 23, 2026
ChaitanyaJudgment-ARBP-526-2015-F.doc
"24. There is no dispute that Section 34 of the Arbitration Act limits a
challenge to an award only on the grounds provided therein or as interpreted
by various courts. We need to be cognizant of the fact that arbitral awards
should not be interfered with in a casual and cavalier manner, unless the court
comes to a conclusion that the perversity of the award goes to the root of the
matter without there being a possibility of alternative interpretation which
may sustain the arbitral award. Section 34 is different in its approach and
cannot be equated with a normal appellate jurisdiction. The mandate
under Section 34 is to respect the finality of the arbitral award and the party
autonomy to get their dispute adjudicated by an alternative forum as provided
under the law. If the courts were to interfere with the arbitral award in the
usual course on factual aspects, then the commercial wisdom behind opting
for alternate dispute resolution would stand frustrated.
- Moreover, umpteen number of judgments of this Court have categorically held that the courts should not interfere with an award merely because an alternative view on facts and interpretation of contract exists. The courts need to be cautious and should defer to the view taken by the Arbitral Tribunal even if the reasoning provided in the award is implied unless such award portrays perversity unpardonable under Section 34 of the Arbitration Act." [Emphasis Supplied]
- In the facts of this case, having examined the record and for
the reasons set out above, in my view, it would not be appropriate for
this Court to interfere with an eminently reasonable and logical view
taken by the Arbitral Tribunal and replace it with a competing view
March 23, 2026
Chaitanya
Judgment-ARBP-526-2015-F.doc
canvassed on behalf of Shyam. Considering the findings of fact based on
appreciation of evidence, regardless of the dispute sought to be raised
on the applicable Article in the Limitation Act, the distinction sought to
be pointed out would not make a difference in the facts of the case.
- In the result, the Section 34 Petition is finally disposed of
without any interference with the Impugned Award.
- All actions required to be taken pursuant to this order shall
be taken upon receipt of a downloaded copy as available on this Court's
website.
[ SOMASEKHAR SUNDARESAN, J.]
March 23, 2026
Chaitanya
Named provisions
Related changes
Source
Classification
Who this affects
Taxonomy
Browse Categories
Get Courts & Legal alerts
Weekly digest. AI-summarized, no noise.
Free. Unsubscribe anytime.
Get alerts for this source
We'll email you when India Bombay High Court publishes new changes.