Changeflow GovPing State Courts Court reverses dismissal of claims against Nest...
Routine Notice Added

Court reverses dismissal of claims against Nestle Purina

Favicon for www.courtlistener.com Ohio Court of Appeals
Detected March 2nd, 2026
Email

Summary

Court reverses dismissal of claims against Nestle Purina

Source document (simplified)

Jump To

Top Caption Syllabus Combined Opinion

Support FLP

CourtListener is a project of Free
Law Project
, a federally-recognized 501(c)(3) non-profit. Members help support our work and get special access to features.

Please become a member today.

Join Free.law Now

March 2, 2026 Get Citation Alerts Download PDF Add Note

Concrete Recovery, L.L.C. v. Nestle Purina Petcare Co.

Ohio Court of Appeals

Syllabus

The trial court erred in dismissing plaintiff's declaratory judgment, breach of contract, and promissory estoppel claims against defendant. Assuming the allegations of plaintiff's amended complaint and attached exhibits are true (as required when reviewing a motion to dismiss for failure to state a claim), plaintiff's assertion that defendant "accepted" plaintiff's bid for concrete pouring work and gave plaintiff "formal notice to proceed" with that work despite no contract being in hand set forth an actionable claim for declaratory judgment, breach of contract, and promissory estoppel.

Combined Opinion

[Cite as Concrete Recovery, L.L.C. v. Nestle Purina Petcare Co., 2026-Ohio-692.]

IN THE COURT OF APPEALS

TWELFTH APPELLATE DISTRICT OF OHIO

CLERMONT COUNTY

CONCRETE RECOVERY LLC, :
CASE NO. CA2025-05-042
Appellant, :
OPINION AND
vs. : JUDGMENT ENTRY
3/2/2026
NESTLE PURINA PETCARE :
COMPANY, et al.,
:
Appellees.
:

CIVIL APPEAL FROM CLERMONT COUNTY COURT OF COMMON PLEAS
Case No. 2025 CVH 00268

Sebaly Shillito + Dyer, and Toby K. Henderson and Kaitlyn C. Meeks, for appellant.

Stites & Harbison PLLC, and William G. Geisen and Cassandra L. Welch, for appellee
Nestle Purina Petcare Company.

UB Greensfelder LLP, and Jesse R. Lipcius and Kyle D. Greene, for appellee Lithko
Contracting, LLC


OPINION

SIEBERT, J.

{¶ 1} Concrete Recovery LLC appeals the trial court's dismissal of Concrete

Recovery's declaratory judgment, breach of contract, and promissory estoppel claims
Clermont CA2025-05-042

against Nestle Purina Petcare Company ("Nestle").1 The trial court determined that

Concrete Recovery failed to state a claim for which it could recover against Nestle.

Concrete Recovery argues the trial court erred because Nestle allegedly accepted

Concrete Recovery's bid for concrete pouring work and, among other things, gave

Concrete Recovery "formal notice to proceed" with that work. Assuming the allegations

of its amended complaint (as well as attached exhibits) are true, we agree that Concrete

Recovery set forth actionable claims against Nestle.

Background

{¶ 2} In October 2024, Nestle issued a request for bids (entitled the "Scope of

Work") for concrete work in connection with construction of Nestle's petfood factory in

Batavia, Clermont County (the "Project"). Generally speaking, the 28-page Scope of Work

described the services and labor needed as well as the responsibilities of any contractor

whose bid Nestle accepted. Among other provisions, the Scope of Work stated:

1.3.1 CONTRACT DOCUMENTS

The Contract Documents, together with all documents
incorporated by reference therein . . . including any drawings,
specifications, 3D Model, Addenda, Document Releases,
Document Supplement Information (DSI's), Request for
lamination (RFI's), Submittals, or other General Documents
that are issued by [Nestle], will be distributed via electronic
distribution . . . Contractor shall be responsible to determine,
extrapolate, and refer to all applicable drawing and
specifications to determine the complete contract scope of
work.

  1. Concrete Recovery also asserted claims for tortious interference with a contract and business relationship against Lithko Contracting, LLC, alleging that Lithko ultimately performed the work Nestle initially awarded to Concrete Recovery. The fact that these claims against Lithko remains unresolved "is irrelevant" and does not bar the instant appeal for lack of a final and appealable order because "at this point [Concrete Recovery] cannot recover from [Lithko]." Wisintainer v. Elcen Power Strut Co., 67 Ohio St.3d 352, 355 (1993). Stated differently, because the trial court found Concrete Recovery did not have a contract with Nestle and did not reasonably or foreseeably rely on any promises made by Nestle, Lithko cannot be found to have interfered with Concrete Recovery and Nestle's alleged contract or business relationship. We therefore conclude this appeal is properly before us. -2- Clermont CA2025-05-042

(Emphasis deleted.). The Scope of Work further stated that the selected contractor would

have to use Nestle's "project management and collaboration system . . . for all project

documentation" and required "Contractor to regularly check and review updated

documents as they are added." To facilitate this, the Scope of Work stated "[a]pplicable

team members of the Contractor are required to complete a free, one-hour Contractor

training certification course . . . within TWO (2) weeks following contract execution."

(Emphasis deleted.). Finally, as relevant to this opinion, the Scope of Work noted that

"[a]ny discrepancies between [the Scope of Work] and the Contract shall be brought to the

attention of [Nestle] prior to signing the contract and [Nestle] shall provide guidance on

the controlling terms."

{¶ 3} That same month, Concrete Recovery submitted an estimate to perform the

Project for $471,277 (the "Bid"). The Bid provided that it may be accepted by telephone

or email. The Bid further stated, "We do require half of the estimate prior to day or day of

starting the job, the remaining balance is due upon completion of the job" and "We do

offer a one year warranty on anything over a hairline fracture." Concrete Recovery alleged

that "[o]n or about October 14, 2024 . . . [Nestle] informed Concrete Recovery of

acceptance [of the Bid] by phone call." Nestle does not contest the phone call occurred

on this date, but asserts it was "to inform Concrete Recovery it had been selected as the

preferred bidder" for the Project.

{¶ 4} After this call, Concrete Recovery completed forms and paperwork required

by Nestle and cooperated with being added to Nestle's vendor management system.

Concrete Recovery workers also completed online orientation/safety training with Nestle

and provided Nestle with a certificate of liability insurance as required by the Scope of

Work. In late October, Nestle sent Concrete Recovery an "Amended Notice of

Commencement" which included an exhibit listing "all contractors contracting directly with

-3-
Clermont CA2025-05-042

[Nestle]." The list included "Concrete Restorations, 150E Forest Ave, South Lebanon,

Ohio 45065." Although its name was not correct, the listed address was that of Concrete

Recovery's office.

{¶ 5} On November 1, 2024, Nestle emailed a "Letter of Intent" to Concrete

Recovery which stated Nestle's "intention to engage in a direct agreement with [Concrete

Recovery] for work associated with the [the Project]." The letter further invited Concrete

Recovery to advise Nestle "if there are other critical path items to be addressed while we

finalize this agreement" and that Nestle "sincerely appreciate[s] the opportunity to work

with you as we continue to develop our pending agreement." In another email sent later

that day, Nestle stated, "work is slated to start on Monday [November 4, 2024]. We won't

have the contract in hand by then. Attached is our formal notice to proceed. Please let

me know if this will work for you guys to move forward with the work."

{¶ 6} However, on November 4, 2024, Nestle emailed Concrete Recovery

advising that "[Nestle] will not be able to comply with the request for downpayment within

the 14-day period . . . Given the current schedule demands and financial considerations,

[Nestle] will not be proceeding with this contract at this time."

{¶ 7} Concrete Recovery subsequently filed suit. Concrete Recovery's amended

complaint (the operative complaint on appeal) sought a declaratory judgment that the

parties entered into a binding contract. Concrete Recovery also claimed Nestle breached

the parties' contract. Finally, Concrete Recovery pled a claim for promissory estoppel,

asserting that if no contract between the parties existed, Nestle's selection of the Bid and

its later directive to "move forward with the work" were promises that reasonably and

foreseeably induced Concrete Recovery to incur time and expense to get ready for the

project.

{¶ 8} Nestle filed a motion to dismiss the amended complaint. The trial court

-4-
Clermont CA2025-05-042

granted Nestle's motion, concluding that there was no valid and enforceable contract

between Nestle and Concrete Recovery. The trial court found the "Scope of Work itself is

not a contract and anticipates that important matters such as discrepancies must be

addressed prior to the execution of a formal, written contract." The decision also rested

on the Letter of Intent, its reference of Nestle's "intention to engage in a direct agreement"

with Concrete Recovery, and its inquiry into whether Concrete Recovery "has other critical

path items to be addressed while we finalize this agreement." (Emphasis deleted.).

{¶ 9} The trial court concluded these documents "clearly indicate[d] that further

action [was] required before a contract [could] be formalized" between Concrete

Recovery and Nestle. As a result, the trial court concluded the parties had no contract

(dismissing both the breach of contract and declaratory judgment claims). The trial court

also concluded that "no clear and unambiguous promises were made upon which

Concrete [Recovery] could have reasonably relied" and dismissed the promissory

estoppel claim.

{¶ 10} Concrete Recovery now appeals that order.

Motion to Dismiss and Standard of Review

{¶ 11} A motion to dismiss for failure to state a claim upon which relief can be

granted tests the sufficiency of the complaint. Civ.R. 12(B)(6); Buckner v. Bank of New

York, 2014-Ohio-568, ¶ 13 (12th Dist.), citing State ex rel. Hanson v. Guernsey Cty. Bd.

of Commrs., 65 Ohio St.3d 545, 548, (1992). Such motion "only determines whether the

pleader's allegations set forth an actionable claim." Ward v. Graue, 2012-Ohio-760, ¶ 9

(12th Dist.). In addition, "all [of] the factual allegations of the complaint must be taken as

true and all reasonable inferences must be drawn in favor of the nonmoving party." Byrd

v. Faber, 57 Ohio St.3d 56, 60, (1991).

{¶ 12} For a complaint to be dismissed for a failure to state a claim, it must appear

-5-
Clermont CA2025-05-042

beyond a reasonable doubt from the complaint that the plaintiff can prove no set of facts

entitling him or her to recovery. LeRoy v. Allen, Yurasek & Merklin, 2007-Ohio-3608, ¶

  1. "'[A]s long as there is a set of facts, consistent with the plaintiff's complaint, which

would allow the plaintiff to recover, the court may not grant a defendant's motion to

dismiss.'" Conaway v. Mt. Orab, 2021-Ohio-4041, ¶ 13 (12th Dist.), quoting York v. Ohio

State Highway Patrol, 60 Ohio St.3d 143, 145 (1991). Importantly, "[a] court may not use

the motion to summarily review the merits of the cause of action." Home Builders Assn.

of Dayton & Miami Valley v. Lebanon, 2004-Ohio-4526, ¶ 8 (12th Dist.).

{¶ 13} When considering whether to dismiss a complaint based on the import of

written instruments attached to a complaint, courts "must avoid interpreting the [written

instrument] at such an early stage unless the instrument is so clear and unambiguous on

its face that the court can determine to a certainty that the plaintiff would be entitled to no

relief under any provable set of facts." Cash v. Seery, 1998 WL 103006, *3 (12th Dist. Mar.

9, 1998), Denlinger, Rosenthal & Greenberg, LPA v. Cohen, 2012-Ohio-4774, ¶ 17 (12th

Dist.).

{¶ 14} An appellate court reviews a trial court's decision to grant a motion to

dismiss de novo. Perrysburg Twp. v. Rossford, 2004-Ohio-4362, ¶ 5.

First Assignments of Error – Do the Circumstances Indicate the Parties May Have
Formed a Contract?2

{¶ 15} Concrete Recovery argues the trial court erred in concluding Concrete

Recovery and Nestle did not have a contract. Concrete Recovery asserts a contract was

formed when Nestle called on October 14, 2024, and advised it had accepted the Bid. In

  1. "[W]e confront [this] fairly basic question that vexes first-year law students . . . [a]lthough these sophisticated parties certainly knew how to dress up a contract in more formal attire . . ." N. Side Bank & Tr. Co. v. Trinity Aviation, LLC, 2020-Ohio-1470, ¶ 1 (1st Dist.).

-6-
Clermont CA2025-05-042

turn, Nestle argues the Scope of Work contemplated the necessity of a formal written

agreement as a prerequisite to contract formation. Before addressing the parties'

arguments, we will review some basic contract principles.

Formation of a Contract, Generally

{¶ 16} "There are three types of contracts under Ohio law: (1) express contracts;

(2) implied in fact contracts; and (3) implied in law contracts." Baise v. Puckett, 2024-

Ohio-508, ¶ 11 (12th Dist.). Express contracts are perhaps the most conventionally

understood of these. Formation of an express contract, requires "an offer and acceptance

of written terms" to show that two parties came to an agreement. Id. Existence of implied

in fact and implied in law contracts, however, are inferred because no written contract

exists. Id. at ¶ 12-13. This case involves whether an implied in fact contract exists.

Formation of an implied in fact contract "is shown by the surrounding circumstances which

made it inferable that the contract exists as a matter of tacit understanding." Sterling

Constr., Inc. v. Alkire, 2014-Ohio-2897, ¶ 23 (12th Dist.).3 Regardless of whether a

contract is express or implied, its essential terms must be identifiable and include the

parties to be bound, subject matter of contract, consideration to be exchanged, and price

to be paid. Holloway v Moritz, 2019-Ohio-83, ¶ 17 (12th Dist.), N. Side Bank & Tr. Co. v.

Trinity Aviation, LLC, 2020-Ohio-1470, ¶ 15 (1st Dist.).

White Hat Mgt. LLC

{¶ 17} The parties' arguments on appeal largely surround their contrasting

applications of a case from one of our sister districts. See generally, White Hat Mgt. L.L.C.

  1. Though not important for resolving this case, an implied in law contract can be formed even when "there is no meeting of the minds, but civil liability arises out of the obligation cast by law upon a person in receipt of benefits which he is not justly entitled to retain and for which he may be made to respond to another in an action in the nature of assumpsit." JS Productions, Inc. v. G129, L.L.C., 2011-Ohio-4715, ¶ 15 (12th Dist.).

-7-
Clermont CA2025-05-042

v. Ohio Farmers Ins. Co., 2006-Ohio-3280 (9th Dist.). In White Hat, the court recognized

the general rule that, an implied contract can be "formed when a party soliciting bids

accepts a proposed bid and gives the bidder notice of the acceptance." White Hat at ¶ 8,

citing Commr. of Highland Cty. v. Rhoades (1875), 26 Ohio St. 411, paragraph one of the

syllabus. In such cases, later execution of a formally written contract is done merely "to

evidence the contract terms to which the parties previously agreed." Id. See also

Walbridge Indus. Process, LLC v. Vaughn Industries, LLC, 472 F.Supp.3d 420, 426

(N.D.Ohio 2020), quoting Id.

{¶ 18} However, White Hat recognized that "an exception to [this] general rule . . .

exists when it is understood that the acceptance of the bid and execution of a formal

written contract are both conditions of the formation of a contract between the parties.

(Emphasis added.) Id. "This two-part acceptance process may be imposed by the

information contained in the solicitation of bids or by virtue of the fact that the party

seeking the bid is authorized by statute to contract only by a formal written contract."

(Emphasis added.) Id., citing Hughes v. Clyde (1884), 41 Ohio St. 339, 340.4

Analysis

{¶ 19} Applying White Hat to this case, Concrete Recovery asserts a contract was

formed when (1) Nestle sent out its request for bids, (2) Concrete Recovery sent Nestle

the Bid, and (3) Nestle informed Concrete Recovery that it had accepted the Bid.

However, Nestle argues that no contract formed because Nestle's Scope of Work

  1. The White Hat court also observed that in cases involving government contracts for public improvements, Ohio statute "imposes a written requirement" for contracts, but the court also noted that such requirement would not "prohibit White Hat [a community school manager for the government] from entering into an oral contract and subsequently memorializing that agreement in a written contract." Id. at ¶ 11. Concrete Recovery, Nestle, and the trial court all noted this distinction, but the parties agree it plays no part in deciding this appeal because no government/public improvement contract is involved. The question before us, therefore, is simply whether this case meets the exception noted in White Hat and Ohio caselaw.

-8-
Clermont CA2025-05-042

contemplated the necessity of a formal written agreement as a prerequisite to contract

formation. Nestle points primarily to (1) the Letter of Intent's acknowledgement that the

parties "continue[d] to develop [their] pending agreement" and (2) the Scope of Work's

requirement that discrepancies between it and the parties' contract "be brought to the

attention of [Nestle] prior to signing" the written contract. Nestle also asserts the Scope

of Work and the Bid cannot be used to form a contract because they are not consistent

on or did not speak to various "key terms" or "essential construction contract terms"

including "payment . . . warrant[ies], insurance requirements, and permitting and

inspection costs" as well as "the time of performance, change orders and variations,

consequences for non-performance or delayed performance . . . and termination rights."

{¶ 20} After construing the facts of this case in favor of Concrete Recovery, the

non-moving party, multiple issues arise with Nestle's arguments. First, they essentially

frame the Scope of Work as if it was an offer. However, it was not until concrete Recovery

submitted the Bid were the essential terms of a potential contract identified, including the

parties to be bound (Nestle and Concrete Recovery), subject matter of the contract

(concrete pouring at a Nestle facility), consideration to be exchanged (money for

performance of concrete pouring), and price to be paid ($471,277). If, as Concrete

Recovery contends, Nestle called on October 14, 2024, to accept the Bid, the facts of this

case, taken together and in a light most favorable to Concrete Recovery, make it inferable

that the contract existed as a matter of tacit understanding at that point.

{¶ 21} The Scope of Work's requirement that discrepancies between the Scope of

Work and the parties' written contract be identified before signing the contract could just

as likely indicate Nestle's contemplation of the execution of a formal written agreement

rather than requiring one. Moreover, assuming an enforceable contract existed after the

October 14, 2024, phone call, any subsequently exchanged document, including the

-9-
Clermont CA2025-05-042

Letter of Intent, is wholly superfluous as to the issue of contract formation. What Nestle

contends are "key terms" of the parties' contract that were not yet settled, including the

timing of payment, weather delays, warranties, insurance requirements, and

miscellaneous costs, are relevant only to determine whether the parties' contract was

breached. Indeed, Section 1.3.1 of the Scope of Work expressly contemplated that

various documents, specifications sheets, and other "General Documents" would, taken

together, constitute the "Contract Documents" for which the contractor Nestle selected

would be responsible to review and "determine the complete contract scope of work."

Ultimately, nothing in the record before us leads us to conclude that Nestle's purported

acceptance of the bid depended on the parties' agreement to other "key" or "essential

terms" (as defined solely by Nestle) or by the execution of a single, written document.5

{¶ 22} The parties' behavior following the October 14, 2024, phone call, when

viewed in a light most favorable to Concrete Recovery, also suggests that execution of a

formal written agreement was not essential to contract formation. For example, Concrete

Recovery workers completed Nestle's required onboarding processes for contractors,

filled out necessary forms, and provided Nestle with a certificate of insurance as required

by the Scope of Work. In addition, prior to sending the Letter of Intent, Nestle's "Amended

Notice of Commencement" identified Concrete Recovery as one contractor "contracting

directly with [Nestle]." Perhaps most importantly, though acknowledging the parties would

not have a "contract in hand by" the time Concrete Recovery started work on the Project,

Nestle sent Concrete Recovery a "formal notice to proceed" with the Project. This

  1. We also note that the Scope of Work and Bid did in fact discuss some of the purportedly missing "key" or "essential" terms described by Nestle. For example, the Bid stated Concrete Recovery "offer[ed] a one year warranty on anything over a hairline [concrete] fracture." Moreover, the Scope of Work provided, among other things, that the work be completed on the "North Side of office building walks, stoops and curbs so occupancy can take place no later than December 1" and that Nestle could withhold payment if identified deficiencies were not timely corrected.
  • 10 - Clermont CA2025-05-042

occurred three days before the Project was set to begin.

{¶ 23} While further discovery and litigation on this issue may demonstrate

otherwise, the record before us leads us to conclude that Concrete Recovery's pleadings

and attached documents show a set of facts which would allow Concrete Recovery to

recover damages from Nestle.

{¶ 24} We sustain Concrete Recovery's first assignment of error.

Second and Third Assignments of Error – Dismissal of Declaratory Judgment and
Promissory Estoppel Claims

{¶ 25} Concrete Recovery also asserts the trial court erred by dismissing the

declaratory judgment and promissory estoppel claims against Nestle. We apply the same

standard of review here and must determine whether Concrete Recovery's amended

complaint, in a light most favorable to Concrete Recovery, sets forth actionable claims

against Nestle. Ward, 2012-Ohio-760, at ¶ 9; Byrd, 57 Ohio St.3d at 60.

Declaratory Judgment

{¶ 26} Generally speaking, "a declaratory-judgment action may be filed only for the

purpose of deciding an 'actual controversy, the resolution of which will confer certain

rights or status upon the litigants.'" Calvary Industries, Inc. v. Coral Chem. Co., 2019-

Ohio-1288, ¶ 11 (12th Dist.), quoting Mid-Am. Fire & Cas. Co. v. Heasley, 2007-Ohio-

1248, ¶ 9. This can include determination of parties' contractual rights and obligations. Id

at ¶ 10.

{¶ 27} Our analysis within the first assignment of error makes it clear the trial court

also erred in dismissing Concrete Recovery's declaratory judgment claim. Because we

determined that Concrete Recovery's amended complaint sufficiently stated a claim for

breach of contract, it must follow that Concrete Recovery's complaint showed an actual

controversy that would be resolved by determining whether the parties formed a contract

  • 11 - Clermont CA2025-05-042

and deciding the rights or status between them.

Promissory Estoppel

{¶ 28} Meanwhile "[p]romissory estoppel is an equitable doctrine for enforcing the

right to rely on promises." Smith-Knabb v. Vesper, 2023-Ohio-259, ¶ 19 (12th Dist.). The

elements of promissory estoppel are: "(1) a clear and unambiguous promise was made;

(2) upon which it would be reasonable and foreseeable for the party to rely; (3) actual

reliance on the promise; and (4) the party was injured as a result of the reliance." RG

Long & Assocs., Inc. v. Kiley, 2015-Ohio-2467, ¶ 14 (12th Dist.).

{¶ 29} Here, Concrete Recovery alleged that Nestle accepted the Bid and later

sent Concrete Recovery a "formal notice to proceed" just days before work was scheduled

to begin. As a result of such express notice, Concrete Recovery alleged it foreseeably

and reasonably relied on these notices by, among things, completing onboarding tasks

for Nestle, gathering materials and laborers for the project, and forgoing other projects.

On the record before us, we conclude that Concrete Recovery could have reasonably

and foreseeably relied and acted on Nestle's "formal notice to proceed" despite not having

any potentially contemplated, written contract in hand.

{¶ 30} We therefore sustain Concrete Recovery's second and third assignments

of error.

{¶ 31} Judgment reversed and remanded for proceedings consistent with this

opinion.

PIPER, P.J. and M. POWELL, J., concur.

  • 12 - Clermont CA2025-05-042

JUDGMENT ENTRY

The assignments of error properly before this court having been ruled upon, it is
the order of this court that the judgment or final order appealed from be, and the same
hereby is, reversed and remanded for proceedings consistent with the above Opinion.

It is further ordered that a mandate be sent to the Clermont County Court of
Common Pleas for execution upon this judgment and that a certified copy of this Opinion
and Judgment Entry shall constitute the mandate pursuant to App.R. 27.

Costs to be taxed in compliance with App.R. 24.

/s/ Robin N. Piper, Presiding Judge

/s/ Mike Powell, Judge

/s/ Melena S. Siebert, Judge

  • 13 -

Get alerts for this source

We'll email you when Ohio Court of Appeals publishes new changes.

Free. Unsubscribe anytime.