Summary

FERC issued a Notice of Denial of Rehearing by Operation of Law regarding Allegheny Electric Cooperative, Inc. et al. v. PJM Interconnection, L.L.C. (Docket EL25-49). The rehearing requests were automatically denied when the Commission failed to act within the statutory timeframe. The notice also provides for further consideration of the underlying matters.

What changed

FERC denied requests for rehearing in the consolidated proceedings Allegheny Electric Cooperative, Inc. et al. v. PJM Interconnection, L.L.C. (Docket EL25-49), with related proceedings in AD24-11 and EL25-20. The denial was by operation of law, meaning FERC did not issue a substantive decision within the required timeframe, triggering automatic denial. The notice provides that the matters will receive further consideration by the Commission.\n\nThis is a procedural document that does not create new compliance obligations for market participants. Parties seeking further review may need to consider appellate options or alternative remedies, though the notice itself does not specify deadlines or required actions beyond the procedural record documentation.

Source document (simplified)

Document Info for Accession Number: 20260220-3002

Details Document: 02/20/2026
Filed: 02/20/2026
Posted: 02/20/2026 08:13:39 AM
First Received Date: 02/20/2026 07:13:31 AM
Security Level: Public
Official: Yes
E-filing: No
Non-decisional: No
Category: Issuance
Library: Electric
Aperture: 0
File Type:
Description* :** Notice of Denial of Rehearing by Operation of Law and Providing for Further Consideration re Allegheny Electric Cooperative, Inc. et al. v. PJM Interconnection, L.L.C. under EL25-49 et al.
File List

| Docket | Sub-Docket | Type |
| --- | --- | --- |
| EL25-49 | 002 | On Document |
| AD24-11 | 001 | On Document |
| EL25-20 | 001 | On Document |

| Document Class | Document Type |
| --- | --- |
| Notice | Formal Notice |
| Order/Opinion | Delegated Order |

| Correspondent | Last Name | First Name | MI | Role/Org |
| --- | --- | --- | --- | --- |
| AUTHOR | REESE | D | A | SECRETARY OF THE COMMISSION - FERC |

| Associate Type | Associate Numbers |
| --- | --- |
| Ferc Cite Number | 194FERC62,089 |

Classification

Agency
FERC
Published
February 20th, 2026
Instrument
Notice
Legal weight
Non-binding
Stage
Final
Change scope
Minor
Document ID
194 FERC 62,089
Docket
EL25-49 AD24-11 EL25-20

Who this affects

Applies to
Energy companies Government agencies
Industry sector
2210 Electric Utilities
Activity scope
Electricity Market Regulation
Geographic scope
United States US

Taxonomy

Primary area
Energy
Operational domain
Legal
Topics
Electric Utilities Administrative Proceedings

Get Government General alerts

Weekly digest. AI-summarized, no noise.

Free. Unsubscribe anytime.

Get alerts for this source

We'll email you when FERC eLibrary: Administrative Proceedings - ChangeBridge publishes new changes.

Optional. Personalizes your daily digest.

Free. Unsubscribe anytime.