Proposed Rate Adjustment for Kerr-Philpott System
Summary
The Southeastern Power Administration has issued a notice proposing a rate adjustment and an adjustment to the true-up mechanism for the Kerr-Philpott System. The agency is seeking public comment and will hold a public forum on June 17, 2025.
What changed
The Southeastern Power Administration, under the Department of Energy, has published a notice proposing adjustments to the rates and the true-up mechanism for the Kerr-Philpott System. This action is a formal step in the rate adjustment process, inviting public input before finalization. The notice includes details on how to submit written comments and information about an upcoming public forum.
Regulated entities and interested parties should review the proposed adjustments and consider submitting comments by the deadline of August 13, 2025. Participation in the public forum, either in-person or virtually, is also encouraged for those wishing to provide direct feedback. Failure to engage in this process may result in acceptance of the proposed rates without further consideration of stakeholder concerns.
What to do next
- Review proposed rate and true-up mechanism adjustments for the Kerr-Philpott System.
- Submit written comments by August 13, 2025.
- Notify Southeastern Power Administration by June 16, 2025, if planning to attend the public forum on June 17, 2025.
Source document (simplified)
Legal Status This site displays a prototype of a “Web 2.0” version of the daily
Federal Register. It is not an official legal edition of the Federal
Register, and does not replace the official print version or the official
electronic version on GPO’s govinfo.gov.
The documents posted on this site are XML renditions of published Federal
Register documents. Each document posted on the site includes a link to the
corresponding official PDF file on govinfo.gov. This prototype edition of the
daily Federal Register on FederalRegister.gov will remain an unofficial
informational resource until the Administrative Committee of the Federal
Register (ACFR) issues a regulation granting it official legal status.
For complete information about, and access to, our official publications
and services, go to About the Federal Register on NARA's archives.gov.
The OFR/GPO partnership is committed to presenting accurate and reliable
regulatory information on FederalRegister.gov with the objective of
establishing the XML-based Federal Register as an ACFR-sanctioned
publication in the future. While every effort has been made to ensure that
the material on FederalRegister.gov is accurately displayed, consistent with
the official SGML-based PDF version on govinfo.gov, those relying on it for
legal research should verify their results against an official edition of
the Federal Register. Until the ACFR grants it official status, the XML
rendition of the daily Federal Register on FederalRegister.gov does not
provide legal notice to the public or judicial notice to the courts.
Legal Status
Notice
Proposed Rate Adjustment, Proposed Adjustment to True-Up Mechanism, Public Forum, and Opportunities for Public Review and Comment for Kerr-Philpott System
A Notice by the Southeastern Power Administration on 05/15/2025
- 1.
1.
Document Details Published Content - Document Details Agencies Department of Energy Southeastern Power Administration Document Citation 90 FR 20669 Document Number 2025-08617 Document Type Notice Pages 20669-20671
(3 pages) Publication Date 05/15/2025 Published Content - Document DetailsPDF Official Content
- View printed version (PDF) Official Content
Document Details Published Content - Document Details Agencies Department of Energy Southeastern Power Administration Document Citation 90 FR 20669 Document Number 2025-08617 Document Type Notice Pages 20669-20671
(3 pages) Publication Date 05/15/2025 Published Content - Document DetailsDocument Dates Published Content - Document Dates Comments Close 08/13/2025 Dates Text Written comments are due on or before August 13, 2025. A public information and comment forum will be held in-person at Southeastern Power Administration, 1166 Athens Tech Road, Elberton, Georgia, at 10 a.m. EDT on June 17, 2025. There will also be an option to attend the forum virtually via Microsoft Teams. Persons desiring to attend the forum should notify Southeastern by June 16, 2025, so a list of forum participants can be prepared. Persons desiring to speak at the forum should specify this in their notification to Southeastern; others may speak if time permits. Notifications should be submitted by email to Comments@sepa.doe.gov. If Southeastern has not been notified by close of business on June 16, 2025, that at least one person intends to be present at the forum, either in-person or virtually, the forum may be canceled with no further notice. Published Content - Document Dates
Table of Contents Enhanced Content - Table of Contents This table of contents is a navigational tool, processed from the
headings within the legal text of Federal Register documents.
This repetition of headings to form internal navigation links
has no substantive legal effect.- AGENCY:
- ACTION:
- SUMMARY:
- DATES:
- ADDRESSES:
- FOR FURTHER INFORMATION CONTACT:
- SUPPLEMENTARY INFORMATION:
- Rate Schedule VA-1-E
- Rate Schedule VA-2-E
- Rate Schedule VA-3-E
- Rate Schedule VA-4-E
- Rate Schedule DEP-1-E
- Rate Schedule DEP-2-E
- Rate Schedule DEP-3-E
- Rate Schedule DEP-4-E
- Rate Schedule AP-1-E
- Rate Schedule AP-2-E
- Rate Schedule AP-3-E
- Rate Schedule AP-4-E
- Rate Schedule NC-1-E
- Rate Schedule Replacement-2-D
- Signing Authority Enhanced Content - Table of Contents
Public Comments Enhanced Content - Public Comments Comments are no longer being accepted.
See DATES for details.
Enhanced Content - Public Comments
- Regulations.gov Data Enhanced Content - Regulations.gov Data Additional information is not currently available for this document.
Enhanced Content - Regulations.gov Data
- Sharing Enhanced Content - Sharing Shorter Document URL https://www.federalregister.gov/d/2025-08617 Email Email this document to a friend Enhanced Content - Sharing
- Print Enhanced Content - Print
- Print this document Enhanced Content - Print
- Document Statistics Enhanced Content - Document Statistics Document page views are updated periodically throughout the day and are cumulative counts for this document. Counts are subject to sampling, reprocessing and revision (up or down) throughout the day.
Page views 58
as of
03/14/2026 at 2:15 pm EDT Enhanced Content - Document Statistics
- Other Formats Enhanced Content - Other Formats This document is also available in the following formats:
JSON Normalized attributes and metadata XML Original full text XML MODS Government Publishing Office metadata More information and documentation can be found in our developer tools pages.
Enhanced Content - Other Formats
- Public Inspection Public Inspection This PDF is FR Doc. 2025-08617 as it appeared on Public Inspection on
05/14/2025 at 8:45 am.
It was viewed
0
times while on Public Inspection.
If you are using public inspection listings for legal research, you
should verify the contents of the documents against a final, official
edition of the Federal Register. Only official editions of the
Federal Register provide legal notice of publication to the public and judicial notice
to the courts under 44 U.S.C. 1503 & 1507. Learn more here.
Public Inspection
Published Document: 2025-08617 (90 FR 20669) This document has been published in the Federal Register. Use the PDF linked in the document sidebar for the official electronic format.
Document Headings Document headings vary by document type but may contain
the following:
- the agency or agencies that issued and signed a document
- the number of the CFR title and the number of each part the document amends, proposes to amend, or is directly related to
- the agency docket number / agency internal file number
- the RIN which identifies each regulatory action listed in the Unified Agenda of Federal Regulatory and Deregulatory Actions See the Document Drafting Handbook for more details.
Department of Energy
Southeastern Power Administration
AGENCY:
Southeastern Power Administration, Department of Energy (DOE).
ACTION:
Notice of proposed rate and true-up mechanism adjustment.
SUMMARY:
Southeastern Power Administration (Southeastern or SEPA) proposes to revise existing schedules of rates and charges applicable to the sale of power from the Kerr-Philpott System effective for a 5-year period, from October 1, 2025, through September 30, 2030. Opportunities will be available for interested persons to review the present rates and the proposed rates, supporting studies, to participate in a public forum and to submit written comments. Southeastern will evaluate all comments received in this process.
DATES:
Written comments are due on or before August 13, 2025. A public information and comment forum will be held in-person at Southeastern Power Administration, 1166 Athens Tech Road, Elberton, Georgia, at 10 a.m. EDT on June 17, 2025. There will also be an option to attend the forum virtually via Microsoft Teams. Persons desiring to attend the forum should notify Southeastern by June 16, 2025, so a list of forum participants can be prepared. Persons desiring to speak at the forum should specify this in their notification to Southeastern; others may speak if time permits. Notifications should be submitted by email to Comments@sepa.doe.gov. If Southeastern has not been notified by close of business on June 16, 2025, that at least one person intends to be present at the forum, either in-person or virtually, the forum may be canceled with no further notice.
ADDRESSES:
Written comments should be submitted to: Administrator, Southeastern Power Administration, Department of Energy, 1166 Athens Tech Road, Elberton, Georgia 30635-6711; Email: Comments@sepa.doe.gov. The URL and call in information for the public information and comment forum is as follows: https://bit.ly/Kerr-PhilpottRateForum2025; +1 (404) 796-9216, Access Code: 927891434#.
FOR FURTHER INFORMATION CONTACT:
Alexa Webb, Acting Power Marketing Advisor, Southeastern Power Administration, Department of Energy, 1166 Athens Tech Road, Elberton, ( printed page 20670) Georgia 30635-6711, (706) 213-3800; Email: Alexa.Webb@sepa.doe.gov.
SUPPLEMENTARY INFORMATION:
The Federal Energy Regulatory Commission (FERC) confirmed and approved on a final basis, Wholesale Power Rate Schedules VA-1-D, VA-2-D, VA-3-D, VA-4-D, DEP-1-D, DEP-2-D, DEP-3-D, DEP-4-D, AP-1-D, AP-2-D, AP-3-D, AP-4-D, NC-1-D, and Replacement-2-C, applicable to Kerr-Philpott System for a period ending September 30, 2025. (FERC Docket No. EF20-5-000 (Dec. 11, 2020)).
Discussion: Existing rate schedules are predicated upon a February 2020 repayment study and other supporting data. The annual revenue requirement in this study was $31,800,000 per year. An updated repayment study, dated March 2025, indicates rates are not adequate to recover cost increases identified and therefore do not meet repayment criteria. The revised repayment study demonstrates an annual revenue requirement increase to $43,000,000 per year will meet repayment criteria. The increase in the annual revenue requirement is $11,200,000 per year, or 35.22 percent.
The existing rate schedules include an annual true-up mechanism for the capacity and energy rates based on the variance of the actual net revenue available for repayment from the planned net revenue available for repayment. The adjustment is for every $100,000 under-recovery of the planned net revenue available for repayment. The base capacity charge is increased by $0.02 per kilowatt per month, up to a maximum of $0.75 per kilowatt per month, and the base energy charge is increased by 0.10 mills per kilowatt-hour, up to a maximum of 3.0 mills per kilowatt-hour. For every $100,000 over-recovery of the planned net revenue available for repayment, the base capacity charge is reduced by $0.02 per kilowatt per month, up to a maximum of $0.75 per kilowatt per month, and the base energy charge is reduced by 0.10 mills per kilowatt-hour, up to a maximum of 3.0 mills per kilowatt-hour.
The initial base capacity charge for the current rate schedules was $4.40 per kilowatt per month. The initial base energy charge was 17.80 mills per kilowatt-hour. As of April 1, 2025, the rates for capacity and energy were not adjusted as they continued to meet their maximum increase set by the true-up mechanism. As of April 1, 2025, the capacity rate remained at $5.15 per kilowatt per month and the base energy charge remained at 20.80 mills per kilowatt-hour for net revenue available for repayment. The existing rates are not adequate to meet repayment criteria. The annual true-up mechanism incorporated in the rate schedules has not proven to be effective in matching revenue available for repayment to planned amounts. In years when net revenue was over-recovered, the adjusted current base rates fell below the initial base rates set in the 2020 rate filing causing lower than projected revenue in subsequent years. Southeastern is proposing to increase the initial base capacity rate to $5.95 per kilowatt per month and the initial base energy charge to 22.75 mills per kilowatt-hour. Southeastern also proposes updating the annual true-up mechanism to keep the true-up rates, during over-recovery periods, from being reduced below the initial base capacity rate and the initial base energy rate set in rate filings.
Proposed Unit Rates: The initial base rates for capacity and energy will be as follows:
Capacity: $5.95 per kW per month.
Energy: 22.75 mills per kWh.
The rates are based on a repayment study estimating the Kerr-Philpott System will produce the following net revenue available for repayment (rounded to nearest $10,000):
| Fiscal year | Estimated annual
net revenue
available for
repayment | Cumulative net
revenue
available for
repayment |
| --- | --- | --- |
| 2025 | $1,840,000 | $1,840,000 |
| 2026 | 170,000 | 2,010,000 |
| 2027 | 3,530,000 | 5,540,000 |
| 2028 | 3,840,000 | 9,380,000 |
| 2029 | 3,930,000 | 13,310,000 |
| 2030 | 3,440,000 | 16,750,000 |
| 2031 | 3,600,000 | 20,350,000 |
| 2032 | 3,720,000 | 24,070,000 |
| 2033 | 3,860,000 | 27,930,000 |
| 2034 | 4,020,000 | 31,950,000 |
The proposed rates continue a true-up of the capacity and energy rates based on the cumulative net revenue available for repayment from the table above. For every 100,000 under-recovery of the planned cumulative net revenue available for repayment, Southeastern will increase the current base capacity charge by $0.02 per kilowatt per month, up to a maximum of $0.75 per kilowatt per month, and increase the current base energy charge by 0.10 mills per kilowatt-hour, up to a maximum of 3.0 mills per kilowatt-hour. For every $100,000 over-recovery of the planned cumulative net revenue available for repayment, Southeastern will reduce the current base capacity charge by $0.02 per kilowatt per month, up to a maximum of $0.75 per kilowatt per month but not below the initial base capacity charge set in the rate filing, and reduce the current base energy charge by 0.10 mills per kilowatt-hour, up to a maximum of 3.0 mills per kilowatt-hour but not below the initial base energy charge set in the rate filing, to be implemented April 1 of the next fiscal year. Southeastern will give written notice to customers of the amount of the true-up by February 1 of each year.
Southeastern is proposing the following rate schedules to be effective for the period from October 1, 2025, through September 30, 2030. The capacity charge and energy charge will be the same for all rate schedules. These rate schedules are necessary to accommodate the transmission and scheduling arrangements available in the Kerr-Philpott System.
Rate Schedule VA-1-E
Available to public bodies and cooperatives in Virginia and North Carolina to whom power may be transmitted and scheduled pursuant to contracts between the Government, Virginia Electric and Power Company (also known as Dominion Virginia Power [DVP]), and DVP's Transmission Operator, PJM Interconnection, LLC (PJM).
Rate Schedule VA-2-E
Available to public bodies and cooperatives in Virginia and North Carolina to whom power may be transmitted pursuant to contracts between the Government, DVP, and PJM. The customer is responsible for providing a scheduling arrangement with the Government.
Rate Schedule VA-3-E
Available to public bodies and cooperatives in Virginia and North Carolina to whom power may be scheduled pursuant to contracts between the Government, DVP, and PJM. The customer is responsible for providing a transmission arrangement.
Rate Schedule VA-4-E
Available to public bodies and cooperatives in the service area of DVP and PJM. The customer is responsible for providing a scheduling arrangement with the Government and for providing a transmission arrangement.
Rate Schedule DEP-1-E
Available to public bodies and cooperatives in North Carolina to whom power may be transmitted and scheduled pursuant to contracts between the Government and Duke Energy Progress. ( printed page 20671)
Rate Schedule DEP-2-E
Available to public bodies and cooperatives in North Carolina to whom power may be transmitted pursuant to contracts between the Government and Duke Energy Progress. The customer is responsible for providing a scheduling arrangement with the Government.
Rate Schedule DEP-3-E
Available to public bodies and cooperatives in North Carolina to whom power may be scheduled pursuant to contracts between the Government and Duke Energy Progress. The customer is responsible for providing a transmission arrangement.
Rate Schedule DEP-4-E
Available to public bodies and cooperatives in the service area of Duke Energy Progress. The customer is responsible for providing a scheduling arrangement with the Government and for providing a transmission arrangement.
Rate Schedule AP-1-E
Available to public bodies and cooperatives in Virginia to whom power may be transmitted and scheduled pursuant to contracts between the Government, American Electric Power Service Corporation and the American Electric Power Service Corporation's Transmission Operator, PJM.
Rate Schedule AP-2-E
Available to public bodies and cooperatives in Virginia to whom power may be transmitted pursuant to contracts between the Government, American Electric Power Service Corporation, and PJM. The customer is responsible for providing a scheduling arrangement with the Government.
Rate Schedule AP-3-E
Available to public bodies and cooperatives in Virginia to whom power may be scheduled pursuant to contracts between the Government, American Electric Power Service Corporation, and PJM. The customer is responsible for providing a transmission arrangement.
Rate Schedule AP-4-E
Available to public bodies and cooperatives in the service area of American Electric Power Service Corporation and PJM. The customer is responsible for providing a scheduling arrangement with the Government and for providing a transmission arrangement.
Rate Schedule NC-1-E
Available to public bodies and cooperatives in Virginia and North Carolina to whom power may be transmitted pursuant to a contract between the Government and PJM and scheduled pursuant to a contract between the Government and Duke Energy Progress.
Rate Schedule Replacement-2-D
This rate schedule shall be applicable to the sale of energy purchased to meet contract minimum energy and sold under appropriate contracts between the Government and the Customer.
The referenced repayment studies are available for examination at 1166 Athens Tech Road, Elberton, Georgia 30635-6711. The Proposed Rate Schedules VA-1-E, VA-2-E, VA-3-E, VA-4-E, DEP-1-E, DEP-2-E, DEP-3-E, DEP-4-E, AP-1-E, AP-2-E, AP-3-E, AP-4-E, NC-1-E, and Replacement-2-D are also available.
Legal Authority: By Delegation Order No. S1-DEL-RATES-2016, effective November 19, 2016, the Secretary of Energy delegated: (1) the authority to develop power and transmission rates to Southeastern's Administrator; (2) the authority to confirm, approve, and place such rates into effect on an interim basis to the Deputy Secretary of Energy; and (3) the authority to confirm, approve, and place into effect on a final basis, or to remand or disapprove such rates, to FERC. By Delegation Order No. S1-DEL-S3-2024, effective August 30, 2024, the Secretary of Energy also delegated the authority to confirm, approve, and place such rates into effect on an interim basis to the Under Secretary for Infrastructure. By Redelegation Order No. S3-DEL-SEPA-2023, effective April 10, 2023, the Under Secretary for Infrastructure redelegated the authority to confirm, approve, and place such rates into effect on an interim basis to the Administrator, Southeastern.
Environmental Compliance: Southeastern is in the process of determining whether an environmental assessment or an environmental impact statement should be prepared or if this action can be categorically excluded from those requirements.
Determination Under Executive Order 12866: Southeastern has an exemption from centralized regulatory review under Executive Order 12866; accordingly, no clearance of this notice by the Office of Management and Budget is required.
Signing Authority
This document of the Department of Energy was signed on May 12, 2025, by Virgil G. Hobbs III, Administrator for Southeastern Power Administration, pursuant to delegated authority from the Secretary of Energy. That document, with the original signature and date, is maintained by DOE. For administrative purposes only, and in compliance with requirements of the Office of the Federal Register, the undersigned DOE Federal Register Liaison Officer has been authorized to sign and submit the document in electronic format for publication, as an official document of the Department of Energy. This administrative process in no way alters the legal effect of this document upon publication in the Federal Register.
Signed in Washington, DC, on May 12, 2025.
Jennifer Hartzell,
Alternate Federal Register Liaison Officer, U.S. Department of Energy.
[FR Doc. 2025-08617 Filed 5-14-25; 8:45 am]
BILLING CODE 6450-01-P
Published Document: 2025-08617 (90 FR 20669)
Related changes
Source
Classification
Who this affects
Taxonomy
Browse Categories
Get Energy Regulation alerts
Weekly digest. AI-summarized, no noise.
Free. Unsubscribe anytime.
Get alerts for this source
We'll email you when FR: Southeastern Power Administration publishes new changes.